Registration approved No litigation declared Residential/Group Housing project

SHANTHI NIVAS

By M/S GRUHA CONSTRUCTIONS AND DEVELOPERS

RG-KA-99469 · RERA PRM/KA/RERA/1248/469/PR/190625/007852 · Last updated on RERA Karnataka portal: 14 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2028Possession promisedno revision filed
5 of 16Construction stages donefurthest along: Masonry Construction, 80%
9 of 9Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 85 documents Report an error

SHANTHI NIVAS is a Residential/Group Housing project by M/S GRUHA CONSTRUCTIONS AND DEVELOPERS in Ballari, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1248/469/PR/190625/007852 on 19 Jun 2025. Possession is promised by 31 May 2028. 0 of the 9 units on this registration are recorded sold or booked, and 5 of 16 construction stages are filed complete.

At a glance

Project

  • NameSHANTHI NIVAS
  • TypeResidential/Group Housing
  • Location
    • Ballari
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1248/469/PR/190625/007852
  • ReraGenie IDRG-KA-99469

Builder

  • NameM/S GRUHA CONSTRUCTIONS AND DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29ABAFG8319B1ZK
  • Authorized SignatoryS Mohammed Ayub

Key dates

this monthRegisteredJun 2025PromisedMay 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Jun 2025
  • Promised completion31 May 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Current status

0%0 of 9 units booked
6.6%Of the estimated cost spent so far

Figures as on 14 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---909

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 16 construction stages are filed complete. The stage furthest along is Masonry Construction, at 80%.

Building: 38% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction80%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing30%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes65%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
Mehaboob Basha S--
Rehana Begum--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.67 cr
Cost incurredRs 24.33 lakh
Spent of the estimate6.63%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 3.64 crRs 22.76 lakh
On-site expenditure-Consultants FeesRs 2.13 lakhRs 1.57 lakh
Administrative CostRs 1.31 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantosh B Shetty
EngineerSahana G
Chartered AccountantRajesh Bagrecha

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed85

As listed on the registration, under the names the promoter filed them with; the newest 80 of 85 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1248/469/PR/190625/007852 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CACertificate.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Balance Sheet 2024-2025File: 1 Balance Sheet 2024-2025.pdf29 May 2025
Profit & Loss 2024-2025File: 1 Profit & Loss 2024-2025.pdf29 May 2025
Source Of Funds with supporting Document- GruhaFile: 2 Source Of Funds with supporting Document- Gruha.pdf29 May 2025
Title Deed of Current land owner TS No 213-2B1File: 6 Title Deed of Current land owner TS No 213-2B1.pdf29 May 2025
Title Deed of Current land owner TS No 213-2B2File: 6 Title Deed of Current land owner TS No 213-2B2.pdf29 May 2025
Title Deed of Current land owner TS No 213-2AFile: 6 Title Deed of Current land owner TS No 213-2A.pdf29 May 2025
Single Layout PlanFile: 7 Single Layout Plan.pdf29 May 2025
Single layout orderFile: 8 Single layout order.pdf29 May 2025
Building License LetterFile: 9 Building License Letter.pdf29 May 2025
Approved Building PlanFile: 11 Approved Building Plan.pdf29 May 2025
Floor Plan Section & ElevationFile: 12 Floor Plan Section & Elevation.pdf29 May 2025
Commencement DeclarationFile: 13 Commencement Declaration.pdf29 May 2025
CDP PlanFile: 14 CDP Plan.pdf29 May 2025
Village mapFile: 15 Village map.pdf29 May 2025
AmenitesFile: 17 Amenites.pdf29 May 2025
Common AreaFile: 17 Common Area.pdf29 May 2025
Engineer LicenseFile: 18 Engineer License.pdf29 May 2025
Water NOCFile: 19 Water NOC.pdf29 May 2025
MR 2976 2021-2022File: 4 MR 2976 2021-2022.pdf29 May 2025
Sale Deed TS No 213-2B1File: 5 Sale Deed TS No 213-2B1.pdf29 May 2025
Sale Deed TS No 213-2B2File: 5 Sale Deed TS No 213-2B2.pdf29 May 2025
Sale Deed TS No 213-2AFile: 5 Sale Deed TS No 213-2A.pdf29 May 2025
old deed 2206-1991-92File: 5 Title deed 2206-1991-92.pdf29 May 2025
Old deed No. 2204-1991-92File: 5 Title deed No 2204-1991-92.pdf29 May 2025
old deed 2205-1991-92File: 5 Title deed 2205-1991-92.pdf29 May 2025
Query answersFile: Query Answer Document.pdf29 May 2025
Registration CertificateFile: Firm Registration Certificate.pdf-
GST CertificateFile: Firm GST certificate.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: 1 FORM 1.pdf-
Certificate issued by Architect Form 2File: Form 5 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 6 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation Declaration Affidavit.pdf-
Balance Sheet 2023 - 2024File: Balance sheet 2023-2024.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Profit & Loss 2023-2024.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR 2023-2024.pdf-
Approved Building License-
Approved Building Plan-
Approved Building Plan-
Structural Stability Certificate-
Project Specifications-
Brochure-
AGREEMENT FOR SALE-
ALLOTMENT LETTER-
6 FORM-B Affidavit Cum Declaration-
Sec3(1) Affidavit-
JDA affidavit-
Legal Report-
Gescom Noc Self Attested-
Water NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Abstract Estimation-
STP Drawing-
Guidance Value Copy-
Land Cost Calculation-
Single layout order-
Single Layout Plan-
BOOKING APPLICATION FORM-
ABSOLUTE SALE DEED-
Sale Deed TS No 213-2B1-
Sale Deed TS No 213-2B2-
Sale Deed TS No 213-2A-
Title deed 2206-1991-92_-
Title deed 2205-1991-92-

How this compares with Ballari

0%of this project is bookeddistrict median 29%
2%of Ballari projects moved their completion datethis one has not
0%of Ballari registrations are shown as withdrawn or revokedthis one is not

Computed across the 190+ Ballari projects on ReraGenie, from their own filings.

Keep SHANTHI NIVAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ballari190+ in Ballari

Builder: M/S GRUHA CONSTRUCTIONS AND DEVELOPERS

M/S GRUHA CONSTRUCTIONS AND DEVELOPERS has 1 registration on RERA Karnataka, including SHANTHI NIVAS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Ballari district page.

Frequently asked questions

What are my rights if SHANTHI NIVAS is delayed beyond 31 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHANTHI NIVAS?

The registered promoter entity is M/S GRUHA CONSTRUCTIONS AND DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29ABAFG8319B1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHANTHI NIVAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHANTHI NIVAS?

The professionals named in the filing: Architect: Santosh B Shetty; Engineer: Sahana G; Chartered Accountant: Rajesh Bagrecha. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHANTHI NIVAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHANTHI NIVAS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHANTHI NIVAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.