Home / Browse projects / Ballari, Karnataka / Axis Park West

Registration approved No litigation declared Residential/Group Housing project

Axis Park West

By AXIS INC

RG-KA-99313 · RERA PRM/KA/RERA/1248/440/PR/290323/005825 · Last updated on RERA Karnataka portal: 18 Feb 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jul 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 108 documents Report an error

Axis Park West is a Residential/Group Housing project by AXIS INC in Ballari, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1248/440/PR/290323/005825 on 29 Mar 2023. Possession is promised by 31 Jul 2025.

At a glance

Project

  • NameAxis Park West
  • TypeResidential/Group Housing
  • Location
    • Hospet
    • Ballari
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1248/440/PR/290323/005825
  • ReraGenie IDRG-KA-99313

Builder

  • NameAXIS INC
  • Entity typePartnership Firm
  • GSTIN29ABSFA9876F1ZK
  • Authorized SignatoryM. PRAMOD KUMAR

Key dates

this monthRegisteredMar 2023PromisedJul 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Mar 2023
  • Promised completion31 Jul 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed108 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Axis Park West---1040104

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 18 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 18 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
M/S AXIS INC--
M/S AXIS INC--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 48.28 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 44.33 cr-
Payment of taxesRs 1.27 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 78.46 lakh-
On-site expenditure-Site OverheadRs 67.25 lakh-
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 60.00 lakh-
On-site expenditure-Salaries of workersRs 50.62 lakh-
On-site expenditure-Consultants FeesRs 12.66 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANGAMESH CHANAMALLAPPA HAVARAGI
EngineerW LALITHA PRASAD
Chartered AccountantVISHAL JAYESHKUMAR JALALPORWALA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed108

As listed on the registration, under the names the promoter filed them with; the newest 80 of 108 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1248/440/PR/290323/005825 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
KSPCB CFEFile: KSPCB CFE.pdf18 Feb 2023
SINGLE PLOT LAYOUT ORDERFile: SINGLE PLOT LAYOUT.pdf18 Feb 2023
Estimated cost of construction for civil works to be certified by the EngineerFile: CERTIFIED COPY OF ESTIMATES.pdf18 Feb 2023
project ongoing status with the expenditure detailsFile: AXIS INC - SREE GEETHA CONSTRUCTION SJC_INVOICE_01.pdf18 Feb 2023
signed copy of the project specification.File: PROJECT SPECIFICATION.pdf18 Feb 2023
upload the proforma of Allotment letterFile: ALLOTMENT LETTER.PDF18 Feb 2023
Upload bank account statement or cheque leafFile: BANK STATEMENT_HDFC BANK.pdf20 Jan 2023
Upload profit and loss account and balance sheet for 2021-22 and 2020-21 with CA UDIN and ITRFile: FINANCIALS_2021.pdf20 Jan 2023
Upload profit and loss account and balance sheet for 2021-22 and 2020-21 with CA UDIN and ITRFile: FINANCIALS_2022.pdf20 Jan 2023
need MR for both synoFile: MR OR FORM 3.pdf20 Jan 2023
need to mention syno in project address column in project detail pageFile: PROJECT ADDRES.pdf20 Jan 2023
Upload all Clear and legible sanctioned drawings Floor plans, sectional drawings and elevations.File: APPROVED BUILDING DRAWINGS.pdf20 Jan 2023
Upload all Clear and legible sanctioned drawings Floor plans, sectional drawings and elevations.File: ELEVATION.pdf20 Jan 2023
Upload all Clear and legible sanctioned drawings Floor plans, sectional drawings and elevations.File: FLOOR PLANS.pdf20 Jan 2023
Upload all Clear and legible sanctioned drawings Floor plans, sectional drawings and elevations.File: PARKING PLAN.pdf20 Jan 2023
Upload all Clear and legible sanctioned drawings Floor plans, sectional drawings and elevations.File: PLAN + SECTION.pdf20 Jan 2023
parking area is allotted to the individual flatsFile: PARKING ALLOTMENT.pdf20 Jan 2023
KSPCB CFEFile: KSPCB CFE.pdf20 Jan 2023
Single plot layout Order.File: SINGLE LAYOUT MAP.pdf20 Jan 2023
certified Carpet area calculationFile: CERTIFIED CARPET AREA CALCULATION.pdf20 Jan 2023
CDP map showing the proposed site.File: CDP 465.jpeg20 Jan 2023
village map showing the proposed siteFile: village map.pdf20 Jan 2023
latitude and longitude detailFile: PROJECT LOCATION.pdf20 Jan 2023
brief estimated cost of construction civil works(Summary of civil works) certified by the Engineer.File: FORM 3 ENGINEER CERTIFICATE.pdf20 Jan 2023
project schedule dates till the proposed completion date as mention on the project detail pFile: Project Schedule Details.pdf20 Jan 2023
project name and project address and upload the signed copy of the project specification.File: PROJECT SPECIFICATIONS.pdf20 Jan 2023
upload the STP demarcation plan along with the KSPCB NOC (NOC PENDING)File: STP LOCATION AND DETAIL CAD PDF.pdf20 Jan 2023
upload the STP demarcation plan along with the KSPCB NOC (NOC PENDING)File: STP LOCATION AND DETAIL SIGNED (CAD PDF SCANNED COPY).pdf20 Jan 2023
Proforma of Allotment letterFile: DRAFT ALLOTMENT LETTER.pdf20 Jan 2023
Allotment LetterFile: Allotment Letter (Booking Form).pdf16 Dec 2022
APPROVED BUILDING DRAWINGSFile: APPROVED BUILDING DRAWINGS.pdf16 Dec 2022
BUILDING LICENSEFile: BUILDING LICENSE.pdf16 Dec 2022
CMC FEE RECEIPTFile: CMC FEE RECEIPT.pdf16 Dec 2022
Guidance value of the property by the Sub RegistrarFile: Guidance value of the property by the Sub Registrar.pdf16 Dec 2022
LEGAL OPINION FROM ADVOCATEFile: LEGAL OPINION FROM ADVOCATE.pdf16 Dec 2022
MAR FORM 26File: MAR FORM 26.pdf16 Dec 2022
MR OR FORM 3File: MR OR FORM 3.pdf16 Dec 2022
NA COPYFile: N A CONVERSATION ORDER COPY.pdf16 Dec 2022
SALE DEED FROM RAJU BHURAT TO PRAVEEN KUMAR TALEDAFile: SALE DEED FROM RAJU BHURAT TO PRAVEEN KUMAR TALEDA.pdf16 Dec 2022
SINGLE LAYOUT MAPFile: SINGLE LAYOUT MAP.pdf16 Dec 2022
RTC, survey 465C1A-
Mutation, survey 465C1A-
Encumbrance Certificate, survey 465C1A-
Conversion/Alienation Order, survey 465C1A-
Sale/Title/Gift Deed, survey 465C1A-
Khatha, survey 465C1A-
RTC, survey 465B1B2-
Mutation, survey 465B1B2-
Encumbrance Certificate, survey 465B1B2-
Conversion/Alienation Order, survey 465B1B2-
Sale/Title/Gift Deed, survey 465B1B2-
Khatha, survey 465B1B2-
Registration CertificateFile: REGISTRATION OF FIRM.PDF-
Partnership DeedFile: PARTNERSHIP DEED.PDF-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM 1 AXIS INC_compressed.pdf-
Certificate issued by Architect Form 2File: Form 2.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Axis Inc Rera Bangalore.pdf-
Certificate from Chartered AccountFile: FORM 1 AXIS INC_compressed.pdf-
Balance Sheet 2021 - 2022File: NA - Balance Sheet.pdf-
Balance Sheet 2020 - 2021File: NA - Balance Sheet.pdf-
Balance Sheet 2019 - 2020File: NA - Balance Sheet.pdf-
Audited Profit and Loss Statement 2021 - 2022File: NA- PNL.pdf-
Audited Profit and Loss Statement 2020 - 2021File: NA- PNL.pdf-
Audited Profit and Loss Statement 2019 - 2020File: NA- PNL.pdf-
Director's Report 2021 - 2022File: NA - Director Report.pdf-
Director's Report 2020 - 2021File: NA - Director Report.pdf-
Director's Report 2019 - 2020File: NA - Director Report.pdf-
Cash Flow Statement 2021 - 2022File: NA - Cash Flow Statement.pdf-
Cash Flow Statement 2020 - 2021File: NA - Cash Flow Statement.pdf-
Auditor's Report 2021 - 2022File: NA - Auditor's Report.pdf-
Auditor's Report 2020 - 2021File: NA - Auditor's Report.pdf-
Auditor's Report 2019 - 2020File: NA - Auditor's Report.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: NA - Income Tax Return Acknowledgement.pdf-

How this compares with Ballari

2%of Ballari projects moved their completion datethis one has not
0%of Ballari registrations are shown as withdrawn or revokedthis one is not

Computed across the 190+ Ballari projects on ReraGenie, from their own filings.

Keep Axis Park West on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ballari190+ in Ballari

Builder: AXIS INC

AXIS INC has 1 registration on RERA Karnataka, including Axis Park West. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Ballari district page.

Frequently asked questions

What are my rights if Axis Park West is delayed beyond 31 Jul 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Axis Park West?

The registered promoter entity is AXIS INC, a partnership firm as per the filing. Its GSTIN 29ABSFA9876F1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Axis Park West?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Axis Park West?

The professionals named in the filing: Architect: SANGAMESH CHANAMALLAPPA HAVARAGI; Engineer: W LALITHA PRASAD; Chartered Accountant: VISHAL JAYESHKUMAR JALALPORWALA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Axis Park West?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Axis Park West. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Axis Park West to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.