ReraGenieLog inGet a buyer report

Home / Browse projects / Ballari, Karnataka / SERENE TOWERS

Registration approved No litigation declared Residential/Group Housing project

SERENE TOWERS

By G LAKSHMI REKHA

RG-KA-37638 · RERA PRM/KA/RERA/1248/469/PR/281124/007253 · Last updated on RERA Karnataka portal: 18 Oct 2024

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 73 documents Report an error

SERENE TOWERS is a Residential/Group Housing project by G LAKSHMI REKHA in Ballari, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1248/469/PR/281124/007253 on 28 Nov 2024. Possession is promised by 31 Dec 2027.

At a glance

Project

  • NameSERENE TOWERS
  • TypeResidential/Group Housing
  • Location
    • Ballari
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1248/469/PR/281124/007253
  • ReraGenie IDRG-KA-37638

Builder

  • NameG LAKSHMI REKHA
  • Entity typeProprietorship
  • Authorized Signatory1

Key dates

this monthRegisteredNov 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Nov 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SERENE TOWERS---84084

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 18 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 18 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
G LAKSHMI REKHA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 22.54 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 22.05 cr-
On-site expenditure-Site OverheadRs 20.00 lakh-
On-site expenditure-Salaries of workersRs 15.00 lakh-
On-site expenditure-Consultants FeesRs 10.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 4.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARVIND G
EngineerRAM MOHAN DESAI
Chartered AccountantSRINIVAS REDDY GANAPAL

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed73

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1248/469/PR/281124/007253 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
INCOME TAX RETURNFile: ITR.jpeg18 Oct 2024
BALANCE SHEET 2022File: 2022.pdf18 Oct 2024
BALANCE SHEET 2023File: 2023.pdf18 Oct 2024
BALANCE SHEET 2024File: 2024.pdf18 Oct 2024
CHARTERED ACCOUNTANT FORM 1File: Chartered accountant form 1.pdf18 Oct 2024
SOURCES OF FUNDFile: sources of fund.pdf18 Oct 2024
AREA DETAILS AND CARPET AREA DETAILS CERTIFIED BY ENGINEERFile: Area details and carpet details.pdf16 Sep 2024
CHARTERED ACCOUNTANT CERTIFICATE FORM-1File: Chartered accountant form 1.pdf16 Sep 2024
FINANCIAL STATEMENTS CLARIFICATIONFile: Financial statements clarification.jpeg16 Sep 2024
FIRE NOC CLARIFICATIONFile: Fire NOC clarification.pdf16 Sep 2024
KATHA EXTRACT IN THE NAME OF CURRENT OWNERFile: Khata.pdf16 Sep 2024
SINGLE PLOT LAYOUT ORDER AND APPROVALFile: single ley out plan and approvel letter.pdf16 Sep 2024
SOURCES OF FUNDFile: sources of fund.pdf16 Sep 2024
STP CLARIFICATIONFile: STP Drawing SERENE.pdf16 Sep 2024
WATER SOURCE CLARIFICATIONFile: water clarification.pdf16 Sep 2024
ZONAL REGULATION COPYFile: ZR COPY.pdf16 Sep 2024
PROJECT SPECIFICATIONFile: specification.pdf16 Sep 2024
FINANCIAL STATEMENT CLARIFICATIONFile: Financial statements clarification.jpeg19 Aug 2024
SOURCES OF FUNDFile: sources of fund.pdf19 Aug 2024
CA CERTIFICATE FORM-1File: Chartered accountant form 1.pdf19 Aug 2024
SINGLE LAYOUT PLANFile: single ley out plan and approvel letter.pdf19 Aug 2024
SINGLE LAYOUT PLAN APPROVALFile: single ley out plan and approvel letter.pdf19 Aug 2024
COMMON AREA DETAILSFile: Area details and carpet details.pdf19 Aug 2024
AREA DETAILS AND FLAT DETAILSFile: flat details.pdf19 Aug 2024
CHARTERED ACCOUNTANT MEMBERSHIP DETAILSFile: CA membership.pdf19 Aug 2024
ENGINEER CERTIFICATEFile: Form -6.pdf19 Aug 2024
BRIEF PROJECT ESTIMATED COST CERTIFIED BY ENGINEERFile: ESTIMATION SUMMARY SHEET.pdf19 Aug 2024
STRUCTUAL SAFETYFile: structural safety.pdf19 Aug 2024
WATER CLARIFICATIONFile: water clarification.pdf19 Aug 2024
SECTION 3 NOTARIZED AFFIDAVITFile: Section 3 Notarized affidavit.pdf19 Aug 2024
KARNATAKA STATE POLLUTION CONTROL BOARDFile: Karnataka state pollution board.pdf19 Aug 2024
FIRE NOC CLARIFICATIONFile: Fire NOC clarification.pdf19 Aug 2024
LAND CALCULATIONFile: land calculation.pdf19 Aug 2024
ZONAL REGULATION COPYFile: Zonal regulation copy.pdf19 Aug 2024
KHATHAFile: khatha.pdf19 Aug 2024
STP DRAWINGFile: stp.pdf19 Aug 2024
RTC, survey 639/*/A3a7-
Mutation, survey 639/*/A3a7-
Encumbrance Certificate, survey 639/*/A3a7-
Conversion/Alienation Order, survey 639/*/A3a7-
Sale/Title/Gift Deed, survey 639/*/A3a7-
Khatha, survey 639/*/A3a7-
Registration CertificateFile: Trading licence.jpeg-
Certificate issued by Architect Form 2File: architecte certificate form 2.pdf-
Certificate issued by Engineer Form 3File: Form 3 engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation affidavit.pdf-
Certificate from Chartered AccountFile: Chartered accountant form 1.pdf-
Commencement certificate 1-
electric NOC-
water NOC Letter-
Approval Plan-
approved layout plan and letter-
Approval Plan-
Approval Plan-
SPECIFICATIONS-
Legal search report-
Agreement of Sale Proforma(4)-
MODEL FORM OF ALLOTMENT LETTER NEW-
Form B-
section 3 violation affidavit-
electric NOC-
water NOC Letter-
Karnataka state pollution board-
Relinquished order-
CDP MAP-
guidance value certificate-
Area details and carpet details-
flat details-
Form -6-
land calculation-

How this compares with Ballari

2%of Ballari projects moved their completion datethis one has not
0%of Ballari registrations are shown as withdrawn or revokedthis one is not

Computed across the 190+ Ballari projects on ReraGenie, from their own filings.

Keep SERENE TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ballari190+ in Ballari

Builder: G LAKSHMI REKHA

G LAKSHMI REKHA has 1 registration on RERA Karnataka, including SERENE TOWERS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Ballari district page.

Frequently asked questions

What are my rights if SERENE TOWERS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SERENE TOWERS?

The registered promoter entity is G LAKSHMI REKHA, a proprietorship as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SERENE TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SERENE TOWERS?

The professionals named in the filing: Architect: ARVIND G; Engineer: RAM MOHAN DESAI; Chartered Accountant: SRINIVAS REDDY GANAPAL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SERENE TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SERENE TOWERS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SERENE TOWERS to a free account