Registration approved No litigation declared Residential/Group Housing project

SEASONS AVENUE

By ASIT MAVJIBHAI LAKUM

RG-KA-48838 · RERA PRM/KA/RERA/1251/309/PR/180120/001585 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 78 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2028Possession promisedmoved 78 months from the original
1 of 15Construction stages donefurthest along: Foundation footing work, 85%
66 of 84Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 75 documents Report an error

SEASONS AVENUE is a Residential/Group Housing project by ASIT MAVJIBHAI LAKUM in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180120/001585 on 20 Jan 2018. Possession is promised by 31 Dec 2028. The completion date has moved by 78 months from the original filing. 18 of the 84 units on this registration are recorded sold or booked, and 1 of 15 construction stages are filed complete.

At a glance

Project

  • NameSEASONS AVENUE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/180120/001585
  • ReraGenie IDRG-KA-48838

Builder

  • NameASIT MAVJIBHAI LAKUM
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2018First promiseJun 2022Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2018
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed75 files

Current status

21%18 of 84 units booked
12.8%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Seasons Avenue---84084

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 15 construction stages are filed complete. The stage furthest along is Foundation footing work, at 85%.

Building: 64% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work85%
Retaining wall (All types)Not applicable
Plinth level Beam85%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)85%
RCC or MS Framed structure66%
Masonry construction: Bricks, Concrete blocks etc66%
Plastering inside , outside & Ceiling66%
Joinery: Doors, Windows, Ventilators etc66%
Basic work of Water supply, Sanitary and Electrification66%
Dadoing, Skirting, Flooring, Tiles work (All types)66%
Railing and Grill fixing66%
Electrification, Water supply and Sanitary Finishing40%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting40%
Elevation work30%
Internal and External work including landscapes as per santioned drawings30%

Progress on shared amenities41

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes25%
Internal Roads & FootpathsYes25%
Sewage and Drainage SystemYes25%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes65%
LiftsYes50%
Staircases and Lift lobbies, corridor,lobbies, corridorYes60%
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes40%
BasementNoNot applicable
TerraceYes50%
Outer WallYes50%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,237 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.62 cr
Cost incurredRs 1.49 cr
Spent of the estimate12.81%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 7.40 crRs 1.49 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.10 cr-
On-site expenditure-Salaries of workersRs 1.00 cr-
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 96.00 lakh-
On-site expenditure-Site OverheadRs 70.69 lakh-
On-site expenditure-Consultants FeesRs 20.00 lakh-
Payment of taxesRs 12.58 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 5.00 lakh-
Payment of chargesRs 3.00 lakh-
Payment of feesRs 2.50 lakh-
Payment of cessRs 1.00 lakh-
Payment of PremiumsRs 1.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKASIM MOHAMMAD IQBAL
EngineerSOHIL M MAKWANA

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2022 → Mar 2023

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/230922/001585Mar 2023 → Mar 2024

Reason as filed by the promoterFinancial crunch

ExtensionMar 2024 → Dec 2028

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed75

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180120/001585 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: 03 - Form 4 CA Certificate - Q34.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: 01 - Form -5 Architect's Certificate.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: 02 - FORM 6 ENGINEER CERTIFICATE.pdf14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: 03 - FORM 4 CA CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: 01 - Form -5 Architect's Certificate .pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: 02 - FORM 6 ENGINEER CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: 03 - FORM 4 CA CERTIFICATE.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: 01 - Form -5 Architect's Certificate .pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: 02 - FORM 6 ENGINEER CERTIFICATE.pdf13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: 03 - Form - 4 CA Certificates - Seasons Avenue - Q30.pdf6 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: 01 - Form -5 Architect's Certificate .pdf6 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: 02 - FORM 6 ENGINEER CERTIFICATE.pdf6 Jan 2026
Q3 2025-26 Airport Authority of India6 Jan 2026
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: 03 - Form-Ex1 Architect Certificate For Status of Work As On Date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: 04 - Form-Ex5 Engineers Certifictae for Pending work as on date.pdf-
CA Certificate for Funds UtilizationFile: 05 - Form-Ex3 Chartered Accountant Certificate For Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: 07 - Form-Ex2 Architect Certificate For Pending Work As On Date.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: 08 - Form-Ex6 Engineers Certifictae for Pending work as on date.pdf-
CA Certificate for Funds required for Project CompletionFile: 09 - Form-Ex4 Chartered Accountant Certificate For Fund Required_compressed.pdf-
AffidavitFile: 10 - Form - Ex7 - Affidavit_compressed.pdf-
Latest Encumbrance CertificateFile: 11 - Encumbrance Certificate.pdf-
Consent letter from 2/3rd of AllotteesFile: 12 - 2-3 Allottee Consent Affidavits.pdf-
Details Of Sold/ Un-sold UnitsFile: 13 - SoldUnsoldDetails.xlsx-
Document 1File: 14 - BESCOM NOC.jpg-
Document 2File: 15 -BSNL NOC.jpg-
Document 3File: 16 - karnataka state pollution board.pdf-
Document 4File: 17 - Airport Authority of India.pdf-
Document 5File: 18 - Flat No G-15.pdf-
Document 6File: 19 - Flat No G-16.pdf-
Document 7File: 20 - Flat No G-17.pdf-
Document 8File: 21 - Flat No S15.pdf-
Document 9File: 22 - FORM B - DECLARATION.pdf-
Document 10File: 23 - DRAFT Agreement To Sale.pdf-
Document 11File: 24 - SEASONS AVENUE DRAFT SALE DEED.pdf-
C_CC-
Site Elevation Section Plan-
Floor Plan-
N_sale deed proforma-
O_Proforma _agreement of sale-
F_land documents-
Floor Plan-
Site Elevation Section Plan-
I_Performa of allotment letter-
K_all NOC-
L_project specifications-
EC-
Katha-
JDA-
Conversion order-
K_all NOC-
Balance Sheet 2015 - 2016File: balance sheet 2016.pdf-
Balance Sheet 2014 - 2015File: balance sheet 2015.pdf-
Balance Sheet 2013 - 2014File: balance sheet 2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: audit report 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: audit report 2014-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: audit report 2013-14.pdf-
Director's Report 2015 - 2016File: balance sheet 2016.pdf-
Director's Report 2014 - 2015File: balance sheet 2015.pdf-
Director's Report 2013 - 2014File: balance sheet 2014.pdf-
Cash Flow Statement 2015 - 2016File: IT returns 2016-17.pdf-
Cash Flow Statement 2014 - 2015File: IT returns 2015-16.pdf-
Auditor's Report 2015 - 2016File: audit report 2015-16.pdf-
Auditor's Report 2014 - 2015File: audit report 2014-15.pdf-
Auditor's Report 2013 - 2014File: audit report 2013-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT returns 2016-17.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT returns 2015-16.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: IT Returns 2014-15.pdf-
M_Form-B-
Prospectus/BrochureFile: 0001.jpg-
Advertisement Copy 1File: 0001.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180120_001585.xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
NIRMAL RESIDENCY, KADATHANMALE, HESARGHATTA HOBLI, BANGALORE-Completed-No date filed

How this compares with Bengaluru Urban

21%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 78 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SEASONS AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: ASIT MAVJIBHAI LAKUM

ASIT MAVJIBHAI LAKUM has 1 registration on RERA Karnataka, including SEASONS AVENUE. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SEASONS AVENUE is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SEASONS AVENUE?

The registered promoter entity is ASIT MAVJIBHAI LAKUM. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SEASONS AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SEASONS AVENUE?

The professionals named in the filing: Architect: KASIM MOHAMMAD IQBAL; Engineer: SOHIL M MAKWANA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SEASONS AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SEASONS AVENUE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SEASONS AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.