Home / Browse projects / Bengaluru Urban, Karnataka / SDMV ELITE

Registration approved No litigation declared Residential/Group Housing project

SDMV ELITE

By M/s SDMV INFRA

RG-KA-88637 · RERA PRM/KA/RERA/1251/308/PR/180723/006073 · Last updated on RERA Karnataka portal: 21 Feb 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
17 of 17Construction stages doneevery applicable stage filed complete
47 of 168Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 243 documents Report an error

SDMV ELITE is a Residential/Group Housing project by M/s SDMV INFRA in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180723/006073 on 18 Jul 2023. Possession is promised by 31 Dec 2026. 121 of the 168 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.

At a glance

Project

  • NameSDMV ELITE
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/180723/006073
  • ReraGenie IDRG-KA-88637

Builder

  • NameM/s SDMV INFRA
  • Entity typePartnership Firm
  • GSTIN29AEUFS2431R1Z0
  • Authorized SignatoryMr.Oleti Subash

Key dates

this monthRegisteredJul 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Jul 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed243 files

Current status

72%121 of 168 units booked
159.5%Of the estimated cost spent so far

Figures as on 21 Feb 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SDMV ELITE---1680168

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 21 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 21 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes100%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership7

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners7
LandownerVillageDistrict
M/S SDMV INFRA--
V.Chandrappa @ Ramachandra--
Chinnaswamy--
M/S SDMV INFRA--
Venkatesh and others--
Smt.Basamma--
M/S VMAKS BUILDERS PRIVATED LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 42.00 cr
Cost incurredRs 66.97 cr
Spent of the estimate159.46%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 42.00 crRs 66.97 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhanumathy G
EngineerSrinivasa Rao Bolimunta
Chartered AccountantSobhanadri V

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed243

As listed on the registration, under the names the promoter filed them with; the newest 80 of 243 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180723/006073 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Q3(FY_2025-26).pdf21 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: SDMV INFRA - FORM-5C(Q3-2025-26).pdf21 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: SDMV INFRA - FORM-6A(Q3-2025-26).pdf21 Feb 2026
Q3 2025-26 Water supply and sewage board21 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)21 Feb 2026
Q3 2025-26 KPTCL- BESCOM21 Feb 2026
Accounts SDMV Infra Current Year AllFile: SDMV - Signed Financials 2022-23.pdf3 Jul 2023
Sy.no.15/8 06 Guntas ConversionFile: Sy no 15-8 06 Guntas Conversion.pdf3 Jul 2023
Sy.no.15/8 06 Guntas Ec Sy.no.15File: Sy no 15-8 06 Guntas EC Sy No 15.pdf3 Jul 2023
Sy.no.15/8 06 Guntas EcFile: Sy no 15-8 06 Guntas EC.pdf3 Jul 2023
Sy.no.15/8 06 Guntas KathaFile: Sy no 15-8 06 Guntas Katha.pdf3 Jul 2023
Sy.no.15/8 06 Guntas MRFile: Sy no 15-8 06 Guntas MR.pdf3 Jul 2023
Sy.no.15/8 06 Guntas RTCFile: Sy no 15-8 06 Guntas RTC.pdf3 Jul 2023
Sy.no.15/8 06 Guntas Sale Deed in Favour of SDMV InfraFile: Sy no 15-8 06 Guntas SaleDeed In favour of SDMV Infra.pdf3 Jul 2023
Sy.no.15/8 06 Guntas Sale Deed in favour of VMAKS-1File: Sy no 15-8 06 Guntas SaleDeed In favour of VMAX-1.pdf3 Jul 2023
Sy.no.15/8 06 Guntas Sale Deed in favour of VMAKS-2File: Sy no 15-8 06 Guntas SaleDeed In favour of VMAX-2.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Conversation 85-16-17File: Sy no 18-4 06 Guntas Conversation 85-16-17.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Conversation 86-16-17File: Sy no 18-4 06 Guntas Conversation 86-16-17.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Conversation 87-2016-17File: Sy no 18-4 06 Guntas Conversation 87-2016-17.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas EC Sy.No 18File: Sy no 18-4 06 Guntas EC Sy No 18.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Latest RTCFile: Sy no 18-4 06 Guntas Latest RTC.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Prakash Babu GPA -1File: Sy no 18-4 06 Guntas Prakash Babu GPA -1.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Prakash Babu GPA -2File: Sy no 18-4 06 Guntas Prakash Babu GPA -2.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Prakash Babu GPA -3File: Sy no 18-4 06 Guntas Prakash Babu GPA -3.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas Sale Deed in favour of SDMV InfraFile: Sy no 18-4 06 Guntas Sale Deed in favour of SDMV Infra.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas SD-5334 in favour of VMAXFile: Sy no 18-4 06 Guntas SD-5334 in favour of VMAX.pdf3 Jul 2023
Sy.no. 18-4 06 Guntas SDMV KathaFile: Sy no 18-4 06 Guntas SDMV Katha.pdf3 Jul 2023
Sy.no.15-9 15 Guntas ConversationFile: Sy no 15-9 15 Guntas Conversation.pdf3 Jul 2023
Sy.no.15-9 15 Guntas EC Sy.No 15File: Sy no 15-9 15 Guntas EC Sy No 15.pdf3 Jul 2023
Sy.no.15-9 15 Guntas JDA Chandrappa in favour of SDMV InfraFile: Sy no 15-9 15 Guntas JDA Chandrappa in favour of SDMV Infra.pdf3 Jul 2023
Sy.no.15-9 15 Guntas MR FOR 15 GUNTASFile: Sy no 15-9 15 Guntas MR FOR 15 GUNTAS.pdf3 Jul 2023
Sy.no.15-9 15 Guntas RTCFile: Sy no 15-9 15 Guntas RTC.pdf3 Jul 2023
Sy.no.15-9 15 Guntas SDMV Elite KathaFile: Sy no 15-9 15 Guntas SDMV Elite Katha.pdf3 Jul 2023
Sy.no.15-9 15 Guntas TITLE DEEDFile: Sy no 15-9 15 Guntas TITLE DEED.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas Conversation 208-2015-16File: Sy no 18-1 3 1-4 Guntas Conversation 208-2015-16.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas ConversionFile: Sy no 18-1 3 1-4 Guntas Conversion.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas EC Sy.No 18File: Sy no 18-1 3 1-4 Guntas EC Sy No 18.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas MRFile: Sy no 18-1 3 1-4 Guntas MR.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas RTCFile: Sy no 18-1 3 1-4 Guntas RTC.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas Sale Deed 5053 in Favour of VamxFile: Sy no 18-1 3 1-4 Guntas Sale Deed 5053 in Favour of Vamx.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas Sale Deed 5334 in Favour of VamxFile: Sy no 18-1 3 1-4 Guntas Sale Deed 5334 in Favour of Vamx.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas Sale Deed in favour of SDMV InfraFile: Sy no 18-1 3 1-4 Guntas Sale Deed in favour of SDMV Infra.pdf3 Jul 2023
Sy.no.18-1 3 1-4 Guntas SDMV Elite KathaFile: Sy no 18-1 3 1-4 Guntas SDMV Elite Katha.pdf3 Jul 2023
Sy.no.18-4 09 Guntas RTCFile: Sy no 18-4 09 Guntas RTC.pdf3 Jul 2023
Sy.no.18-4 09 Guntas ConversationFile: Sy no 18-4 09 Guntas Conversation.pdf3 Jul 2023
Sy.no.18-4 09 Guntas EC Sy.No 18File: Sy no 18-4 09 Guntas EC Sy No 18.pdf3 Jul 2023
Sy.no.18-4 09 Guntas ECFile: Sy no 18-4 09 Guntas EC.pdf3 Jul 2023
Sy.no.18-4 09 Guntas JD in favour of SDMV InfraFile: Sy no 18-4 09 Guntas JD in favour of SDMV Infra.pdf3 Jul 2023
Sy.no.18-4 09 Guntas MRFile: Sy no 18-4 09 Guntas MR.pdf3 Jul 2023
Sy.no.18-4 09 Guntas SDMV Elite KathaFile: Sy no 18-4 09 Guntas SDMV Elite Katha.pdf3 Jul 2023
Sy.no.18-4 09 Guntas Title DeedFile: Sy no 18-4 09 Guntas Title Deed.pdf3 Jul 2023
Sy.no.18-4 09 Guntas Title Deed-1File: Sy no 18-4 09 Guntas Title Deed-1.pdf3 Jul 2023
Sy.no.18-4 09 Guntas Title Deed-2File: Sy no 18-4 09 Guntas Title Deed-2.pdf3 Jul 2023
Sy.no.18-4 15 Guntas Conversation 202-2006-07File: Sy no 18-4 15 Guntas Conversation 202-2006-07.pdf3 Jul 2023
Sy.no.18-4 15 Guntas EC Sy.No 18File: Sy no 18-4 15 Guntas EC Sy No 18.pdf3 Jul 2023
Sy.no.18-4 15 Guntas JDA Venkatesh in favour of SDMV InfraFile: Sy no 18-4 15 Guntas JDA Venkatesh in favour of SDMV Infra.pdf3 Jul 2023
Sy.no.18-4 15 Guntas RTCFile: Sy no 18-4 15 Guntas RTC.pdf3 Jul 2023
Sy.no.18-4 15 Guntas SDMV Elite KathaFile: Sy no 18-4 15 Guntas SDMV Elite Katha.pdf3 Jul 2023
Sy.no.18-4 15 Guntas Title Deed -1File: Sy no 18-4 15 Guntas Title Deed -1.pdf3 Jul 2023
Sy.no.18-4 15 Guntas Title Deed -2File: Sy no 18-4 15 Guntas Title Deed -2.pdf3 Jul 2023
Sy.no.18-4 15 Guntas Title Deed -3File: Sy no 18-4 15 Guntas Title Deed -3.pdf3 Jul 2023
Sy.no.18-8 01 Gunta ConversationFile: Sy no 18-8 01 Gunta Conversation.pdf3 Jul 2023
Sy.no.18-8 01 Gunta EC Sy.No 18File: Sy no 18-8 01 Gunta EC Sy No 18.pdf3 Jul 2023
Sy.no.18-8 01 Gunta RTCFile: Sy no 18-8 01 Gunta RTC.pdf3 Jul 2023
Sy.no.18-8 01 Gunta Sale 5334 Deed in favour of VMAXFile: Sy no 18-8 01 Gunta Sale 5334 Deed in favour of VMAX.pdf3 Jul 2023
Sy.no.18-8 01 Gunta Sale Deed in favour of SDMV InfraFile: Sy no 18-8 01 Gunta Sale Deed in favour of SDMV Infra.pdf3 Jul 2023
Sy.no.18-8 01 Gunta SDMV Elite KathaFile: Sy no 18-8 01 Gunta SDMV Elite Katha.pdf3 Jul 2023
Sy.no.18-9 04 Guntas Conversion Sy.no.18_9 measuring 2 GuntasFile: Sy no 18-9 04 Guntas Conversion Sy no 18-9 measuring 2 Guntas.pdf3 Jul 2023
Sy.no.18-9 04 Guntas Conversion-sy.no.18_1 and 18_9-pages-1-7File: Sy no 18-9 04 Guntas Conversion-sy no 18-1 and 18-9-pages-1-7.pdf3 Jul 2023
Sy.no.18-9 04 Guntas EC Sy.No 18File: Sy no 18-9 04 Guntas EC Sy No 18.pdf3 Jul 2023
Sy.no.18-9 04 Guntas RTCFile: Sy no 18-9 04 Guntas RTC.pdf3 Jul 2023
Sy.no.18-9 04 Guntas Sale Deed 4403 in favour of VMAXFile: Sy no 18-9 04 Guntas Sale Deed 4403 in favour of VMAX.pdf3 Jul 2023
Sy.no.18-9 04 Guntas Sale Deed 5053 in favour of VMAXFile: Sy no 18-9 04 Guntas Sale Deed 5053 in favour of VMAX.pdf3 Jul 2023
Sy.no.18-9 04 Guntas SDMV Elite KathaFile: Sy no 18-9 04 Guntas SDMV Elite Katha.pdf3 Jul 2023
Sy.no.18-9 04 Guntas SDMV Sale DeedFile: Sy no 18-9 04 Guntas SDMV Sale Deed.pdf3 Jul 2023
Sy.no.18-9 13.5 Guntas Conversion Sy.no.18_9File: Sy no 18-9 13 5 Guntas Conversion Sy no 18_9.pdf3 Jul 2023
Sy.no.18-9 13.5 Guntas EC Sy.No 18File: Sy no 18-9 13 5 Guntas EC Sy No 18.pdf3 Jul 2023
Sy.no.18-9 13.5 Guntas JDA Gopal Ragupathy in favour of SDMV InfraFile: Sy no 18-9 13 5 Guntas JDA Gopal Ragupathy in favour of SDMV Infra.pdf3 Jul 2023
Sy.no.18-9 13.5 Guntas RTCFile: Sy no 18-9 13 5 Guntas RTC.pdf3 Jul 2023
Sy.no.18-9 13.5 Guntas SDMV Elite KathaFile: Sy no 18-9 13 5 Guntas SDMV Elite Katha.pdf3 Jul 2023

How this compares with Bengaluru Urban

72%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SDMV ELITE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: M/s SDMV INFRA

M/s SDMV INFRA has 1 registration on RERA Karnataka, including SDMV ELITE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SDMV ELITE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SDMV ELITE?

The registered promoter entity is M/s SDMV INFRA, a partnership firm as per the filing. Its GSTIN 29AEUFS2431R1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SDMV ELITE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SDMV ELITE?

The professionals named in the filing: Architect: Bhanumathy G; Engineer: Srinivasa Rao Bolimunta; Chartered Accountant: Sobhanadri V. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SDMV ELITE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SDMV ELITE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SDMV ELITE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.