Home / Browse projects / Bengaluru Urban, Karnataka / SAPTHAGIRI SANDALWOODS

Registration approved No litigation declared Residential/Group Housing project

SAPTHAGIRI SANDALWOODS

By SAPTHAGIRI SHELTERS

RG-KA-68643 · RERA PRM/KA/RERA/1251/446/PR/090523/005918 · Last updated on RERA Karnataka portal: 28 Apr 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Apr 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 126 documents Report an error

SAPTHAGIRI SANDALWOODS is a Residential/Group Housing project by SAPTHAGIRI SHELTERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/090523/005918 on 9 May 2023. Possession is promised by 30 Apr 2025.

At a glance

Project

  • NameSAPTHAGIRI SANDALWOODS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/090523/005918
  • ReraGenie IDRG-KA-68643

Builder

  • NameSAPTHAGIRI SHELTERS
  • Entity typePartnership Firm
  • GSTIN29AEBFS4817C1Z4
  • Authorized SignatoryM.SUBRAMANYAM NAIDU
  • Other registrations2 more →

Key dates

this monthRegisteredMay 2023PromisedApr 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 May 2023
  • Promised completion30 Apr 2025
  • Revised completionNone
  • Buildings6 building records
  • Documents filed126 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Block---40040
B Block---40040
C Block---40040
D Block---40040
E Block---44044
F Block---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 28 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners4
LandownerVillageDistrict
K.ETHIRAJULU NAIDU, RAJESH BANDI AND BANDI PAVAN KUMAR--
RAJESH BANDI--
BANDI PAVAN KUMAR--
M/s. SAPTHAGIRI SHELTERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 75.60 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 75.60 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVijay Associates
EngineerC G ASSOCIATES
Chartered AccountantGALIGUTTA HARSHAVARDHAN REDYY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed126

As listed on the registration, under the names the promoter filed them with; the newest 80 of 126 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/090523/005918 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architects certificate with valid COA numberFile: Architech certificate.pdf28 Apr 2023
KSPCB CFE along with fee receiptFile: KPSC Fee paid receipt.pdf28 Apr 2023
KSPCB CFEFile: PCB NOC.pdf28 Apr 2023
Single plot layout Order and plan clarificationFile: Single plot order clarification.pdf28 Apr 2023
Katha 87-1 and 87-2 BBMPFile: 87-1 and 87-2 BBMP katha.pdf13 Apr 2023
Allotment letterFile: Allotment letter new.pdf13 Apr 2023
AOS as per RERAFile: AOS as per RERA.pdf13 Apr 2023
Balance sheet and profit and loss account and sechdules 19-20File: Balance sheet - p&l and sechdules with UDIN 19-20.pdf13 Apr 2023
Balance sheet and profit and loss account and sechdules 20-21File: Balance sheet - p&l and sechdules with UDIN 20-21.pdf13 Apr 2023
Balance sheet and profit and loss account and sechdules 21-22File: Balance sheet - p&l and sechdules with UDIN 21-22.pdf13 Apr 2023
Bank letterFile: Bank letter.pdf13 Apr 2023
Bescom fee paid receiptFile: BESCOM Fee paid receipt.jpeg13 Apr 2023
brochure clarificationFile: Brochure clarification.pdf13 Apr 2023
building licesneFile: BUILDING LICENCE.pdf13 Apr 2023
BWSSB NOCFile: BWSSB NOC.pdf13 Apr 2023
CA certificateFile: CA certificate.pdf13 Apr 2023
CDP MapFile: CDP MAP 1.pdf13 Apr 2023
CDM MAPFile: CDP Map.pdf13 Apr 2023
Comman area clarification letterFile: Comman Area clarification letter.pdf13 Apr 2023
katha certificateFile: katha certificate all.pdf13 Apr 2023
loan letterFile: Loan letter.jpeg13 Apr 2023
project estimation by engineerFile: Project estimation.pdf13 Apr 2023
reliquishment deedFile: Reliquishment deed clarification.pdf13 Apr 2023
section 3(1) affidavitFile: Section 3(1) Affidavit.pdf13 Apr 2023
source of fund detailsFile: Source of fund details.pdf13 Apr 2023
specificationFile: Specification.pdf13 Apr 2023
structural stability certificate by engineerFile: Structural stability certificate.pdf13 Apr 2023
village mapFile: Village Map.pdf13 Apr 2023
MR all sy.noFile: MR All_compressed.pdf13 Apr 2023
Conversion order Sy.No.87File: Sy no 78 conversation order_compressed.pdf13 Apr 2023
Conversion order Sy.No.87-2 and 87BFile: Sy no 87-2 and 87-2B conversation order_compressed.pdf13 Apr 2023
Commencement certificateFile: CC.pdf13 Apr 2023
Form-7 uploadedFile: Form - 7 uploaded.pdf13 Apr 2023
sale deed 78File: Sale deed (title deed) 78.pdf13 Apr 2023
sale deedFile: Sale deed 78_compressed.pdf13 Apr 2023
sale deed 87-1 and 87-2File: Sale deed 87-1 and 87-2_compressed.pdf13 Apr 2023
sale deed 87-1File: Sale Deed 87-1.pdf13 Apr 2023
architech certificateFile: Architech Certificate.pdf13 Apr 2023
KspcbFile: Sapthagiri KSPCB.pdf13 Apr 2023
RTC, survey 87/1-
Mutation, survey 87/1-
Encumbrance Certificate, survey 87/1-
Conversion/Alienation Order, survey 87/1-
Sale/Title/Gift Deed, survey 87/1-
JDA, survey 87/1-
Khatha, survey 87/1-
RTC, survey 87/2-
Mutation, survey 87/2-
Encumbrance Certificate, survey 87/2-
Conversion/Alienation Order, survey 87/2-
Sale/Title/Gift Deed, survey 87/2-
JDA, survey 87/2-
Khatha, survey 87/2-
RTC, survey 78-
Mutation, survey 78-
Encumbrance Certificate, survey 78-
Conversion/Alienation Order, survey 78-
Sale/Title/Gift Deed, survey 78-
Khatha, survey 78-
Registration CertificateFile: registration certificate.pdf-
Partnership DeedFile: registration certificate and partnership deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA certificate_compressed.pdf-
Certificate issued by Architect Form 2File: Architech Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: CA certificate.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet 21-22.pdf-
Balance Sheet 2019 - 2020File: balance sheet 2019-20.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P&L 21-22.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit and loss account 2019-20.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 21-22.pdf-
CC-
BESCOM NOC-
BWSSB NOC_compressed-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SAPTHAGIRI SANDALWOODS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SAPTHAGIRI SHELTERS

SAPTHAGIRI SHELTERS has 3 registrations on RERA Karnataka, including SAPTHAGIRI SKY GARDEN and SAPTHAGIRI SANDALWOODS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SAPTHAGIRI SANDALWOODS is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAPTHAGIRI SANDALWOODS?

The registered promoter entity is SAPTHAGIRI SHELTERS, a partnership firm as per the filing. Its GSTIN 29AEBFS4817C1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAPTHAGIRI SANDALWOODS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAPTHAGIRI SANDALWOODS?

The professionals named in the filing: Architect: Vijay Associates; Engineer: C G ASSOCIATES; Chartered Accountant: GALIGUTTA HARSHAVARDHAN REDYY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAPTHAGIRI SANDALWOODS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAPTHAGIRI SANDALWOODS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAPTHAGIRI SANDALWOODS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.