ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SANKALP SQUARE

Registration approved Residential/Group Housing project

SANKALP SQUARE

By SANKALP CONSTRUCTIONS PRIVATE LIMITED

RG-KA-78114 · RERA PRM/KA/RERA/1251/472/PR/190614/002612

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2025Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 45 documents Report an error

SANKALP SQUARE is a Residential/Group Housing project by SANKALP CONSTRUCTIONS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/190614/002612 on 14 Jun 2019. Possession is promised by 30 Mar 2025. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameSANKALP SQUARE
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/190614/002612
  • ReraGenie IDRG-KA-78114

Builder

  • NameSANKALP CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • Authorized SignatoryV K JAGADISH BABU
  • OthersT V SANTHANAGOPALAN
  • Other registrations13 more →
  • Declared earlier projects19 →

Key dates

this monthRegisteredJun 2019First promiseJun 2024Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Jun 2019
  • Promised completion30 Mar 2025
  • Revised completionRevised to 30 Mar 2025 (originally 30 Jun 2024)
  • Buildings13 building records
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMBER---16016
CORAL---16016
DIAMOND---16016
EMERALD---16016
IVORY---16016
ONYX---16016
OPAL---16016
PEARL---16016
RUBY---16016
SAPPHIRE---16016
TOPAZ---16016
JADE---16016
JASPER---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,152 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 72.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVERNEKAR ASSOCIATES PRIVATE LIMITED
EngineerNADIG CONSULTING

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2024 → Mar 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/190614/002612 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation Certificate.pdf-
Form of sanction-
Approved ploting Plan-
ilovepdf_merged (2)-
Final Sale Deed-
Final Agreement for Sale-
Sale Deed-
Floor Plans-
Approved Layout Plan-
Pro-Forma of Allotment Letter-
Specifications-
11 EC Merged final_compressed-
2 affidavit-
1 affidavit cum declaration-
5 Khatha & Extract-
JDA-
BESCOM NOC_compressed-
BWSSB NOC_compressed-
ULC Order 31-07-1980-
Existing Layout plan-
Existing Section plan Speci-
ULC Order-
Balance Sheet 2017 - 2018File: 1 Balance Sheet 17-18-min.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet 16-17.pdf-
Balance Sheet 2015 - 2016File: 1 Balance sheet 2016.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 2 Profit & Loss Ac-min.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L 16-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 2 Profit and Loss 2016.pdf-
Director's Report 2017 - 2018File: 3 Directors Report-min.pdf-
Director's Report 2016 - 2017File: P&L 16-17.pdf-
Director's Report 2015 - 2016File: 3 Directors report 2016.pdf-
Cash Flow Statement 2017 - 2018File: 5 Cash flow statement.pdf-
Cash Flow Statement 2016 - 2017File: Cash flow statement.pdf-
Auditor's Report 2017 - 2018File: 4 Auditors Report-min.pdf-
Auditor's Report 2016 - 2017File: Auditors Report.pdf-
Auditor's Report 2015 - 2016File: 4 Auditor Report 2016.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: 6 ITR V.PDF-
Income Tax Return Acknowledgement 2016 - 2017File: ITR V.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 6 ITR-V 2016-17.pdf-
3 form B-
Tower Excel SheetFile: PRM_KA_RERA_1251_472_PR_190614_002612.xlsx-
Loan raised documentFile: SANKALP HDFC-NDC-31122024.pdf-
Occupancy CertificateFile: SS OC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: SSQ Affidavit for Completion of the Project.pdf-
Occupation CertificateFile: SS OC.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SANKALP SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSANKALP SQUAREOther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: SANKALP CONSTRUCTIONS PRIVATE LIMITED

SANKALP CONSTRUCTIONS PRIVATE LIMITED has 14 registrations on RERA Karnataka, including SANKALP WINDSOR HOUSE and SANKALP SQUARE. Its filings declare 19 earlier projects, 8 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SANKALP SQUARE is delayed beyond 30 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SANKALP SQUARE?

The registered promoter entity is SANKALP CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SANKALP SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SANKALP SQUARE?

The professionals named in the filing: Architect: VERNEKAR ASSOCIATES PRIVATE LIMITED; Engineer: NADIG CONSULTING. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SANKALP SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANKALP SQUARE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANKALP SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.