Home / Browse projects / Bengaluru Urban, Karnataka / Sanjeevini II
Sanjeevini II
By MBSR Infrastructure Pvt. Ltd.
RG-KA-72822 · RERA PRM/KA/RERA/1251/310/PR/210524/006925 · Last updated on RERA Karnataka portal: 7 Aug 2025
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
Sanjeevini II is a Plotted Development project by MBSR Infrastructure Pvt. Ltd. in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210524/006925 on 21 May 2024. Possession is promised by 10 Jun 2025. The completion date has moved by 6 months from the original filing.
At a glance
Project
- NameSanjeevini II
- TypePlotted Development
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/210524/006925
- ReraGenie IDRG-KA-72822
Builder
- NameMBSR Infrastructure Pvt. Ltd.
- Entity typeCompany
- GSTIN29AALCM9054C1Z7
- Authorized SignatorySathya Ranjan Shetty
- MdSathya Ranjan Shetty
- DirectorsSathya Ranjan Shetty, Supriya
- Project HeadSathya Ranjan Shetty
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 May 2024
- Promised completion10 Jun 2025
- Revised completionRevised to 10 Jun 2025 (originally 2 Dec 2024)
- BuildingsNot stated in filing
- Documents filed161 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| K Shiva Shankar | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 1.18 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | RAGHAVENDRA T V |
| Chartered Accountant | Rajagopal S Joshi |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in Approvals
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed161
As listed on the registration, under the names the promoter filed them with; the newest 80 of 161 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210524/006925 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| About Annual Audit ReportFile: Screen shot Audit report.jpg | 7 Aug 2025 |
| Aduit ReportFile: MBSR_Audit Report_202324_ReRa.pdf | 12 Jul 2025 |
| Audited FinancialsFile: Financials_MBSR_2023-24_ReRa.pdf | 12 Jul 2025 |
| Engieering Query on Zeropercent work pendingFile: ReRa_Engineering Clarification.pdf | 12 Jul 2025 |
| Reason for late completionFile: Reason for Late Completion of Project.pdf | 12 Jul 2025 |
| Promoter Approved and Renewal approval orderFile: Renewal Order & Renewal Plan.pdf | 12 Jul 2025 |
| Query Regarding Form B AffidavitFile: About Affidavit B.pdf | 12 Jul 2025 |
| RERA COLLECTION ACCOUNTFile: RERA collection account.pdf | 13 May 2024 |
| RERA DESIGNATED ACCOUNTFile: Rera designated account.pdf | 13 May 2024 |
| RERA DEVELOPER ACCOUNTFile: Rera developer account.pdf | 13 May 2024 |
| BANK AFFIDAVITFile: Bank affidavit.pdf | 13 May 2024 |
| FINANCIAL STATEMENT OF 2022-23File: Financial statement 2022 23.pdf | 13 May 2024 |
| FINANCIAL STATEMENT OF 2021-22File: Financial statement 2021 22.pdf | 13 May 2024 |
| BALANCE SHEET OF 2020-21File: Balance Sheet FY 2020 21.pdf | 13 May 2024 |
| PROFIT AND LOSS ACCOUNT FOR 2020-21File: Profit and Loss FY 2020 21.pdf | 13 May 2024 |
| CA CERTIFICATE FORM 1File: CA Certificate Form 1.pdf | 13 May 2024 |
| APPROVED LAYOUT PLANFile: Aproved plan Sy no 70.jpg | 13 May 2024 |
| GST CERTIFICATEFile: GST certificate.pdf | 13 May 2024 |
| SOURCES OF FUNDFile: Fund supporting doc sy no 70.pdf | 13 May 2024 |
| CURRENT YEAR RTCFile: RTC new Sy no 70.pdf | 13 May 2024 |
| CONNECTED MRFile: MR new sy no 70.pdf | 13 May 2024 |
| GUNTA B KARAB AFFIDAVITFile: Karab affidavit sy no 70.pdf | 13 May 2024 |
| JDA AFFIDAVIITFile: JDA affidavit.pdf | 13 May 2024 |
| SECTION 3 NOTARIZED AFFIDAVITFile: Affidavit 3 violation.pdf | 13 May 2024 |
| NOTARIZED FORM -B AFFIDAVITFile: Affidavit cum declaration form B.pdf | 13 May 2024 |
| ADVOCATE SEARCH REPORTFile: Advocate search report sy no 70.pdf | 13 May 2024 |
| SALE DEED 1File: sale deed 1.pdf | 13 May 2024 |
| SALE DEEDFile: Sale deed.pdf | 13 May 2024 |
| ALLOTMENT OF SALEFile: Allotment of sale.pdf | 13 May 2024 |
| PROFORMA OF AGREEMENT OF SALEFile: Proforma of agreement of sale.pdf | 13 May 2024 |
| RELINQUISHMENT DEEDFile: Relinquishment Deed 2 sy no 70.pdf | 13 May 2024 |
| CDP MAPFile: BYLALU CDP MAP.pdf | 13 May 2024 |
| VILLAGE MAPFile: BYLALU VILLAGE MAP.pdf | 13 May 2024 |
| LAYOUT PLAN APPROVAL WORK ORDERFile: Sy no 70 Work order.pdf | 13 May 2024 |
| STP PLANFile: stp plan by eng.pdf | 13 May 2024 |
| PROJECT SPECIFICATIONFile: specifications details of plots Sanjeevini 2.pdf | 13 May 2024 |
| ENGINEER CERTIFICATE FORM 3File: Engineer cirtificate.pdf | 13 May 2024 |
| ENGINEER KYCFile: Engineer KYC.pdf | 13 May 2024 |
| ENGINEER LICENSEFile: ENGINEER LICENSE.pdf | 13 May 2024 |
| ESTIMATED COST OF CONSTRUTIONFile: Estimated developement cost.pdf | 13 May 2024 |
| DEMARCATION PLANFile: Demarcation Plan.pdf | 13 May 2024 |
| ECFile: EC.pdf | 13 May 2024 |
| NON LITIGATION AFFIDAVITFile: Non litigation affidavit sy no 70.pdf | 13 May 2024 |
| DECLARATION OF PROJECT ARCHITECT CERTIFICATEFile: Declaration on Project Architect.pdf | 13 May 2024 |
| DECLARATION OF HORTICULTURE NOCFile: Declaration on Horticulture NOC.pdf | 13 May 2024 |
| CLARIFICATION OF CHANGE OF LAND USEFile: Declaration on CLU sy no 70.pdf | 13 May 2024 |
| CONVERSION ORDER COPYFile: conversation sy no 70.pdf | 13 May 2024 |
| WATER NOCFile: Panchayat water NOC sy no 70.pdf | 13 May 2024 |
| ELECTRICITY NOCFile: BESCOM NOC with Receipt.pdf | 13 May 2024 |
| LAND VALUE CALCULATIONFile: Land value Calculation sheet.pdf | 13 May 2024 |
| WATER SOURCES FROM LOCAL BODYFile: Panchayat water NOC sy no 70.pdf | 13 May 2024 |
| ENGINEER CERTIFICATE FORM 6File: Engineer Certificate Form 6.pdf | 13 May 2024 |
| ENGINEER REGISTRATION CERTIFICATE WITH SELF ATTESTEDFile: Engineer certificate of Registration Self attested.pdf | 13 May 2024 |
| PLOT WISE DIMENSION DETAILS WITH ATTESTED BY ENGINEERFile: Plot wise dimensions and details of sy no 70.pdf | 13 May 2024 |
| RTC, survey 70 | - |
| Mutation, survey 70 | - |
| Encumbrance Certificate, survey 70 | - |
| Conversion/Alienation Order, survey 70 | - |
| JDA, survey 70 | - |
| Khatha, survey 70 | - |
| Registration CertificateFile: Cirtificate of Incorporation.pdf | - |
| Memorandum of Association | - |
| Article of Association | - |
| Organization StructureFile: Organisation struct.pdf | - |
| Certificate issued by CA Form 1File: CA Certificate Form 1.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Certificate Form 6.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: Non litigation affidavit sy no 70.pdf | - |
| Certificate from Chartered AccountFile: CA Certificate Form 1.pdf | - |
| Certificate issued by ArchitectFile: Declaration on Project Architect.pdf | - |
| Balance Sheet 2022 - 2023File: willAS pdf (1).pdf | - |
| Balance Sheet 2021 - 2022File: willAS pdf (1).pdf | - |
| Balance Sheet 2020 - 2021File: willAS pdf (1).pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: willAS pdf (1).pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: willAS pdf (1).pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: willAS pdf (1).pdf | - |
| Director's Report 2022 - 2023File: willAS pdf (1).pdf | - |
| Director's Report 2021 - 2022File: willAS pdf (1).pdf | - |
| Director's Report 2020 - 2021File: willAS pdf (1).pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Sanjeevini II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: MBSR Infrastructure Pvt. Ltd.
MBSR Infrastructure pvt ltd has 2 registrations on RERA Karnataka, including SANJEEVINI and Sanjeevini II. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Sanjeevini II is delayed beyond 10 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Sanjeevini II?
The registered promoter entity is MBSR Infrastructure Pvt. Ltd., a company as per the filing. Its GSTIN 29AALCM9054C1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Sanjeevini II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Sanjeevini II?
The professionals named in the filing: Engineer: RAGHAVENDRA T V; Chartered Accountant: Rajagopal S Joshi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sanjeevini II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback