SANJEEVINI

By MBSR Infrastructure pvt ltd

RG-KA-01787 · RERA PRM/KA/RERA/1251/310/PR/190919/002892

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2021Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 72 documents Report an error

SANJEEVINI is a Plotted Development project by MBSR Infrastructure pvt ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190919/002892 on 19 Sep 2019. Possession is promised by 12 Dec 2021. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameSANJEEVINI
  • TypePlotted Development
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/190919/002892
  • ReraGenie IDRG-KA-01787

Builder

  • NameMBSR Infrastructure pvt ltd
  • Entity typeCompany
  • CINU45500KA2018PTC113888
  • Authorized SignatorySathya Ranjan Shetty
  • DirectorSupriya Shetty
  • Other registrations1 more →

Key dates

this monthRegisteredSep 2019First promiseMar 2021Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Sep 2019
  • Promised completion12 Dec 2021
  • Revised completionRevised to 12 Dec 2021 (originally 12 Mar 2021)
  • BuildingsNot stated in filing
  • Documents filed72 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,331 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1.05 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2021 → Dec 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed72

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190919/002892 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: CERTIFICATE OF INCORPORATION.pdf-
Commencement-
sanjeevini new plan-
Sanjeevini plan-
not aplicable-
not aplicable-
saledeed and rtc-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
EC 12years-
form b-
not aplicable-
Katha-
not aplicable-
FLOW OF TITLE-
CONVERSION ORDER-
not aplicable-
not aplicable-
not aplicable-
certificate-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
Unnamed document-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
not aplicable-
Sanjeevini plan-
not aplicable-
not aplicable-
FLOW OF TITLE-
Balance Sheet 2017 - 2018File: Balance Sheet.pdf-
Balance Sheet 2016 - 2017File: not aplicable.jpeg-
Balance Sheet 2015 - 2016File: not aplicable.jpeg-
Audited Profit and Loss Statement 2017 - 2018File: Audit Profit And Loss.pdf-
Audited Profit and Loss Statement 2016 - 2017File: not aplicable.jpeg-
Audited Profit and Loss Statement 2015 - 2016File: not aplicable.jpeg-
Director's Report 2017 - 2018File: not aplicable.jpeg-
Director's Report 2016 - 2017File: not aplicable.jpeg-
Director's Report 2015 - 2016File: not aplicable.jpeg-
Cash Flow Statement 2017 - 2018File: not aplicable.jpeg-
Cash Flow Statement 2016 - 2017File: not aplicable.jpeg-
Auditor's Report 2017 - 2018File: Auditor report.pdf-
Auditor's Report 2016 - 2017File: not aplicable.jpeg-
Auditor's Report 2015 - 2016File: not aplicable.jpeg-
Income Tax Return Acknowledgement 2017 - 2018File: not aplicable.jpeg-
Income Tax Return Acknowledgement 2016 - 2017File: not aplicable.jpeg-
Income Tax Return Acknowledgement 2015 - 2016File: not aplicable.jpeg-
AFFIDAVIT-
Prospectus/BrochureFile: MBSR Broucher.jpg-
Advertisement Copy 1File: MBSR Broucher.jpg-
Advertisement Copy 2File: Broucher backside.jpg-
Plot Excel SheetFile: PRM_KA_RERA_1251_310_PR_190919_002892 (1).xlsx-
Final plan technical sanction LetterFile: oc.pdf-
Final layout plan sanctionedFile: Plan.pdf-
Completion CertificateFile: oc.pdf-
Site release order Copies(1st,2nd phase and final release order)File: oc.pdf-
Chartered Accountant Certificate (Form-4)File: CA Certicate.pdf-
Engineer's Certificate (Form-6)File: oc.pdf-
Affidavit from Promoter for completing project as per advertisement published in brochure and as per project sFile: oc.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SANJEEVINI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: MBSR Infrastructure pvt ltd

MBSR Infrastructure pvt ltd has 2 registrations on RERA Karnataka, including SANJEEVINI and Sanjeevini II. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SANJEEVINI is delayed beyond 12 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SANJEEVINI?

The registered promoter entity is MBSR Infrastructure pvt ltd, a company as per the filing. Its CIN U45500KA2018PTC113888 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SANJEEVINI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in SANJEEVINI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANJEEVINI. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANJEEVINI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.