Home / Browse projects / Bengaluru Urban, Karnataka / SAMRUDDHI
SAMRUDDHI
RG-KA-29499 · RERA PRM/KA/RERA/1251/310/PR/020926/008903 · Last updated on RERA Karnataka portal: 13 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SAMRUDDHI is a Residential/Group Housing project by SPW Estates LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/020926/008903 on 2 Sep 2026. Possession is promised by 30 Apr 2029. 0 of the 10 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.
At a glance
Project
- NameSAMRUDDHI
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/020926/008903
- ReraGenie IDRG-KA-29499
Builder
- NameSPW Estates LLP
- Entity typePartnership Firm
- LLPINABC-0045
- GSTIN29AEUFS0008L1ZJ
- Authorized SignatoryPriyanka Rathore
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on2 Sep 2026
- Promised completion30 Apr 2029
- Revised completionNone
- Buildings1 building record
- Documents filed94 files
Current status
Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | - | - | - | 10 | 0 | 10 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 21%.
Building: 1% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 21% |
| Foundation footing work | 0% |
| Upto Plinth Level | 0% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 0% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | Yes | 0% |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Kotta Enterprises Private Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 2.26 cr | Rs 25.60 lakh |
| On-site expenditure-Salaries of workers | Rs 71.90 lakh | - |
| On-site expenditure-Site Overhead | Rs 58.96 lakh | Rs 7.65 lakh |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 33.08 lakh | - |
| On-site expenditure-Consultants Fees | Rs 28.76 lakh | - |
| Payment of taxes | Rs 9.59 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Santosh B Shetty |
| Engineer | Sahana G |
| Chartered Accountant | Jyothi S Biradar |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed94
As listed on the registration, under the names the promoter filed them with; the newest 80 of 94 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/020926/008903 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Sep 26.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Sep 26.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU Sep 26.pdf | 13 Oct 2026 |
| Reply to queryFile: Reply to query.pdf | 25 Aug 2026 |
| Area StatementFile: 1 Area Statement.pdf | 25 Aug 2026 |
| Common Area and Amenities DetailsFile: 2 Common Area and Amenities Details.pdf | 25 Aug 2026 |
| STP Declaration and Corrigendum NotificationFile: 3 STP Declaration and Corrigendum Notification.pdf | 25 Aug 2026 |
| Reply to QueryFile: Reply to Query.pdf | 4 Aug 2026 |
| Form 1 CA CertificateFile: 1 Form 1 CA Certificate.pdf | 4 Aug 2026 |
| Bank AffidavitFile: 2 Bank Affidavit.pdf | 4 Aug 2026 |
| Bank Account Confirmation LetterFile: 2 Bank Account Confirmation Letter.pdf | 4 Aug 2026 |
| SPW Estates LLP-Balance Sheet FY 2022-23File: 3 SPW Estates LLP-Balance Sheet FY 2022-23.pdf | 4 Aug 2026 |
| SPW Estates LLP-Profit and Loss FY 2022-23File: 3 SPW Estates LLP-Profit and Loss FY 2022-23.pdf | 4 Aug 2026 |
| SPW Estates LLP-Balance Sheet FY 2023-24File: 3 SPW Estates LLP-Balance Sheet FY 2023-24.pdf | 4 Aug 2026 |
| SPW Estates LLP-Profit and Loss FY 2023-24File: 3 SPW Estates LLP-Profit and Loss FY 2023-24.pdf | 4 Aug 2026 |
| SPW Estates LLP-Balance Sheet FY 2024-25File: 3 SPW Estates LLP-Balance Sheet FY 2024-25.pdf | 4 Aug 2026 |
| SPW Estates LLP-Profit and Loss FY 2024-25File: 3 SPW Estates LLP-Profit and Loss FY 2024-25.pdf | 4 Aug 2026 |
| Source of FundFile: 4 Source of Fund.pdf | 4 Aug 2026 |
| Form 6 Engineer CertificateFile: 5 Form 6 Engineer Certificate.pdf | 4 Aug 2026 |
| Samruddhi-No Litigation AffidavitFile: 6 Samruddhi-No Litigation Affidavit.pdf | 4 Aug 2026 |
| & 9 Samruddhi Posession CertificateFile: 7 & 9 Samruddhi Posession Certificate.jpg | 4 Aug 2026 |
| & 9 Samruddhi Sale Deed - BDA Site Allotted to Raji MenonFile: 7 & 9 Samruddhi Sale Deed - BDA Site Allotted to Raji Menon.pdf | 4 Aug 2026 |
| Samruddhi-Sale Deed to Kotta Enterprises Private LimitedFile: 8 Samruddhi-Sale Deed to Kotta Enterprises Private Limited.pdf | 4 Aug 2026 |
| EC 01-04-2004 to 21-07-2026File: 10 EC 01-04-2004 to 21-07-2026.pdf | 4 Aug 2026 |
| Samruddhi-JDA AffidavitFile: 11 Samruddhi-JDA Affidavit.pdf | 4 Aug 2026 |
| Advocate Search ReportFile: 12 Advocate Search Report.pdf | 4 Aug 2026 |
| & 14 Single Plot layout Plan and order declarationFile: 13 & 14 Single Plot layout Plan and order declaration.pdf | 4 Aug 2026 |
| Declaration - ADLR Survey SketchFile: 15 Declaration - ADLR Survey Sketch.pdf | 4 Aug 2026 |
| Demarcated Google MapFile: 16 Demarcated Google Map.pdf | 4 Aug 2026 |
| Samruddhi Approved Building PlanFile: 17 Samruddhi Approved Building Plan.pdf | 4 Aug 2026 |
| Samruddhi-Commencement Certificate DeclarationFile: 18 Samruddhi-Commencement Certificate Declaration.pdf | 4 Aug 2026 |
| Village MapFile: 19 Village Map.jpg | 4 Aug 2026 |
| Change of Land use declarationFile: 20 Change of Land use declaration.pdf | 4 Aug 2026 |
| CDP-Demaracted 2031File: 20 CDP-Demaracted 2031.pdf | 4 Aug 2026 |
| Demarcated CDP Map 2015File: 20 Demarcated CDP Map 2015.pdf | 4 Aug 2026 |
| Form 6 Engineer CertificateFile: 27 Form 6 Engineer Certificate.pdf | 4 Aug 2026 |
| Samruddhi Structural Stability Certificate and Engineer LicenseFile: 28 Samruddhi Structural Stability Certificate and Engineer License.pdf | 4 Aug 2026 |
| Proforma of Agreement for SaleFile: 29 Proforma of Agreement for Sale.pdf | 4 Aug 2026 |
| Proforma of Allotment LetterFile: 30 Proforma of Allotment Letter.pdf | 4 Aug 2026 |
| Abstract Estimation and LicenseFile: 31 Abstract Estimation and License.pdf | 4 Aug 2026 |
| Land Cost Calculation Sheet & Guidance Value CertificateFile: 34 Land Cost Calculation Sheet & Guidance Value Certificate.pdf | 4 Aug 2026 |
| Samruddhi-Sale Deed to J C Uma ReddyFile: Samruddhi-Sale Deed to J C Uma Reddy.pdf | 4 Aug 2026 |
| Registration CertificateFile: SPW Estates LLP -LLP Incorporation Certificate.pdf | - |
| GST CertificateFile: SPW Estates LLP -GST Certificate.pdf | - |
| Partnership DeedFile: SPW Estates LLP -LLP Agreement.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: Form 5 Architect Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Form 6 Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Samruddhi-No Litigation Affidavit.pdf | - |
| Balance Sheet 2024 - 2025File: SPW Estates LLP-Balance Sheet FY 2024-25.pdf | - |
| Balance Sheet 2023 - 2024File: SPW Estates LLP-Balance Sheet FY 2023-24.pdf | - |
| Balance Sheet 2022 - 2023File: SPW Estates LLP-Balance Sheet FY 2022-23.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: SPW Estates LLP-Profit and Loss FY 2024-25.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: SPW Estates LLP-Profit and Loss FY 2023-24.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: SPW Estates LLP-Profit and Loss FY 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: SPW Estates LLP-ITR FY 2024-25.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: SPW Estates LLP-ITR FY 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: SPW Estates LLP-ITR FY 2022-23.pdf | - |
| Samruddhi Building License | - |
| Samruddhi Approved Building Plan | - |
| Samruddhi Approved Building Plan | - |
| Samruddhi Structural Stability Certificate and Engineer License | - |
| Samruddhi - Project Specifications | - |
| Samruddhi - Brochure Declaration | - |
| Samruddhi-Form B Affidavit | - |
| Samruddhi-Section 3(1) Affidavit | - |
| Samruddhi-JDA Affidavit | - |
| Samruddhi-Affidavit for BESCOM NOC | - |
| Samruddhi-Affidavit for BWSSB NOC | - |
| Samruddhi-Affidavit for KSPCB NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SAMRUDDHI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SPW Estates LLP
SPW Estates LLP has 1 registration on RERA Karnataka, including SAMRUDDHI. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SAMRUDDHI is delayed beyond 30 Apr 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SAMRUDDHI?
The registered promoter entity is SPW Estates LLP, a partnership firm as per the filing. Its LLPIN ABC-0045 and GSTIN 29AEUFS0008L1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SAMRUDDHI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SAMRUDDHI?
The professionals named in the filing: Architect: Santosh B Shetty; Engineer: Sahana G; Chartered Accountant: Jyothi S Biradar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAMRUDDHI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback