Home / Browse projects / Bengaluru Urban, Karnataka / SAMPOOJITHA HEIGHTS
SAMPOOJITHA HEIGHTS
RG-KA-64690 · RERA PRM/KA/RERA/1251/446/PR/270526/008687 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SAMPOOJITHA HEIGHTS is a Residential/Group Housing project by SAMPOOJITHA DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/270526/008687 on 27 May 2026. Possession is promised by 31 Dec 2029. 11 of the 100 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.
At a glance
Project
- NameSAMPOOJITHA HEIGHTS
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/270526/008687
- ReraGenie IDRG-KA-64690
Builder
- NameSAMPOOJITHA DEVELOPERS
- Entity typePartnership Firm
- GSTIN29AERFS5722G1ZI
- Authorized SignatoryMASARAPU MADHUSUDHAN RAO
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on27 May 2026
- Promised completion31 Dec 2029
- Revised completionNone
- Buildings1 building record
- Documents filed155 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING 1 | - | - | - | 100 | 0 | 100 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 70%.
Building: 37% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 70% |
| Masonry Construction | 60% |
| Plastering inside , outside & Ceiling | 40% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | 0% |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities36
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 40% |
| Sewage and Drainage System | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 5% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
Land and ownership7
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| K SRINIVAS | - | - |
| S. Ravindranath | - | - |
| K. Dhananjaya | - | - |
| K. Siddaramaiah | - | - |
| Saraswathamma | - | - |
| Prabhavathi K | - | - |
| Bhagya | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 43.74 cr | Rs 12.95 cr |
| On-site expenditure-Site Overhead | Rs 6.69 cr | Rs 1.03 cr |
| Payment of taxes | Rs 4.70 cr | Rs 15.86 lakh |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 3.02 cr | - |
| On-site expenditure-Consultants Fees | Rs 55.26 lakh | Rs 7.90 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHIVA KUMAR |
| Engineer | GANDHI S |
| Chartered Accountant | PRASAD BOGALA |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed155
As listed on the registration, under the names the promoter filed them with; the newest 80 of 155 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/270526/008687 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q2 2026-27.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: from 6.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| MR from 60/2 to 60/15File: MR from 60 2 to 60 15.pdf | 27 May 2026 |
| Title deed prabhavati 60/2File: prabhavathi release Deed.pdf | 27 May 2026 |
| Title deed bhagya 60/14File: Title deed bhagya 60 14.pdf | 27 May 2026 |
| EC upto dateFile: EC upto date.pdf | 27 May 2026 |
| Single Plot layout plan and Single Plot layout plan orderFile: Single Plot order.pdf | 22 May 2026 |
| survey sketchFile: Survey records.pdf | 22 May 2026 |
| commencement certificateFile: commencement certificate.pdf | 22 May 2026 |
| Demarcation of proposed land in Approved Master planFile: belthur cdp plan.pdf | 22 May 2026 |
| development detailsFile: Development details.pdf | 22 May 2026 |
| notarized affidavit in form-BFile: Form B.pdf | 22 May 2026 |
| notarized JD cum AffidavitFile: JD cum affadavit.pdf | 22 May 2026 |
| non-litigation AffidavitFile: Non-litigation.pdf | 22 May 2026 |
| CONNECTED MR FOR SY 60/2 BEFORE CONVERSIONFile: CONNECTED MR SAMPOOJITHA (1).pdf | 22 May 2026 |
| CONNECTED MR FOR SY 60/3 BEFORE CONVERSIONFile: MR for sy 60 3 After relese deed.pdf | 22 May 2026 |
| REALSE DEED IN FAVOUR OF LAND OWNERSFile: RELESE DEED IN FAVOUR OF LAND OWNER PARTION.pdf | 22 May 2026 |
| SALE DEED IN FAVOUR OF RAVIDRANTH FOR SY 60/6 AND 60/10File: SALE DEED BEFORE JD1.pdf | 22 May 2026 |
| JDA AND AMALGAMATION DEEDFile: JDA FINAL_merged.pdf | 22 May 2026 |
| OLD MR BEFORE PARTITIONFile: MR OLD 2000.pdf | 22 May 2026 |
| STABILTY CERTIFICATEFile: stabilty certificate .pdf | 22 May 2026 |
| Form 6File: FORM 6 .pdf | 22 May 2026 |
| LATEST EC, THERE NO TRANSACTION LATER THAT DATEFile: ECC111220258121493 2 (1).pdf | 22 May 2026 |
| Connect MR after partition for each land ownerFile: CONNECTED MR SAMPOOJITHA.pdf | 18 May 2026 |
| STABILITY CERTIFICATEFile: STABILITY CERTIFICATE (2).pdf | 18 May 2026 |
| STPFile: 60 KLD SBR Civil Drawing Model (2).pdf | 18 May 2026 |
| GUDIANCE VALUEFile: Guidance Value Certficate.pdf | 18 May 2026 |
| Allotment letterFile: allotment_letter[1].pdf | 18 May 2026 |
| AGREEMENT FOR SALEFile: AOS.pdf | 18 May 2026 |
| ECFile: EC - Belathuru.pdf | 18 May 2026 |
| JDA FOR 60/6 AND 60/10File: JDA 60 6 60 10.pdf | 18 May 2026 |
| Section 3(1) Notarized affidavitFile: Affidavit.pdf | 18 May 2026 |
| FORM 1 CA CERTIFICATEFile: Form 1 CA Certificate.pdf | 18 May 2026 |
| SOURCE OF FUNDSFile: sources of funds.pdf | 18 May 2026 |
| land Value CalculationFile: Land calculation.pdf | 18 May 2026 |
| Estimation CostFile: sampoojitha heights estimatted cost (1).pdf | 18 May 2026 |
| BrochureFile: Brochure.pdf | 18 May 2026 |
| NOC oF PollutionFile: Pollutiuon certificate.pdf | 18 May 2026 |
| Source of waterFile: source water and noc.pdf | 18 May 2026 |
| KTPC NOC LETTERFile: BDA.pdf | 18 May 2026 |
| sectional drawingsFile: PRJ77392425 1.pdf | 18 May 2026 |
| Site LocationFile: Site Location.jpeg | 18 May 2026 |
| Building licensesFile: BUILDING LICENCE.pdf | 18 May 2026 |
| ITR FY 2022-23 and 2023-24File: No ITR.pdf | 18 May 2026 |
| Financial Statements FY 2024-25File: sampoojitha developer Fy 2425.pdf | 18 May 2026 |
| Project SpecificationsFile: project sepcifications.pdf | 18 May 2026 |
| VILLAGE MAP WITH SITE DEMARCATIONFile: village map.pdf | 18 May 2026 |
| Village MapFile: village map (1) (2).pdf | 18 May 2026 |
| Amenities DetailsFile: Amenities Details.pdf | 18 May 2026 |
| Village PataFile: VILLAGE PATA .pdf | 18 May 2026 |
| akarbandhaFile: AKARBANDHA.pdf | 18 May 2026 |
| Common area DetailsFile: common area details.pdf | 18 May 2026 |
| CDP PlanFile: CDP PLAN BELTHURLATEST 1 (1) (1).pdf | 18 May 2026 |
| Legal OpinionFile: Legal opinion.pdf | 18 May 2026 |
| JD cum AffidavaitFile: Affi cum dec.pdf | 18 May 2026 |
| Engineer CertificateFile: gandhi licenses.pdf | 18 May 2026 |
| Form 3File: Form 3.pdf | 18 May 2026 |
| Allotment LetterFile: allotment letter.pdf | 14 Apr 2026 |
| AOSFile: Proformance letter.pdf | 14 Apr 2026 |
| Source of waterFile: source water and noc.pdf | 14 Apr 2026 |
| NOC OF PollutionFile: Pollutiuon certificate.pdf | 14 Apr 2026 |
| Stability CertificateFile: sampoojitha heights satbilty certificate.pdf | 14 Apr 2026 |
| Estimation CostFile: sampoojitha heights estimatted cost (1).pdf | 14 Apr 2026 |
| Land CostFile: Land cost calculation.pdf | 14 Apr 2026 |
| Site LocationFile: Site Location.jpeg | 14 Apr 2026 |
| ADLR SketechFile: Adlr Sektech.pdf | 14 Apr 2026 |
| cdr palnFile: cdp paln belthur (2).pdf | 14 Apr 2026 |
| sectional drawingsFile: PRJ_7739_24-25 (1).pdf | 14 Apr 2026 |
| KTPC NOC LETTERFile: BDA.pdf | 14 Apr 2026 |
| Source of fundsFile: sources of funds.pdf | 14 Apr 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SAMPOOJITHA HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SAMPOOJITHA DEVELOPERS
SAMPOOJITHA DEVELOPERS has 1 registration on RERA Karnataka, including SAMPOOJITHA HEIGHTS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SAMPOOJITHA HEIGHTS is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SAMPOOJITHA HEIGHTS?
The registered promoter entity is SAMPOOJITHA DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AERFS5722G1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SAMPOOJITHA HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SAMPOOJITHA HEIGHTS?
The professionals named in the filing: Architect: SHIVA KUMAR; Engineer: GANDHI S; Chartered Accountant: PRASAD BOGALA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAMPOOJITHA HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback