Home / Browse projects / Pune, Maharashtra / SAIRAJ

Registered No litigation declared Residential / Group Housing project

SAIRAJ

By LAXMIDEEP INFRASTRUCTURES

RG-MH-16537 · RERA P52100026844 · Last updated on MahaRERA portal: 20 Mar 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 46 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 46 months from the original
7 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 72%
34 of 36Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 136 documents Report an error

SAIRAJ is a Residential / Group Housing project by LAXMIDEEP INFRASTRUCTURES in Pune, Maharashtra, registered with MahaRERA as P52100026844 on 31 Oct 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 46 months from the original filing. 2 of the 36 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete.

At a glance

Project

  • NameSAIRAJ
  • TypeResidential / Group Housing
  • Location
    • MORDEWADI ROAD
    • MORDEWADI
    • Manchar (CT)
    • Ambegaon
    • Pune
    • 410503
  • Pincode410503
  • RERA no.P52100026844
  • ReraGenie IDRG-MH-16537

Builder

  • NameLAXMIDEEP INFRASTRUCTURES
  • Entity typePartnership
  • PartnersSANGITA SUNIL GAIKWAD, DIVYA DHARMENDRA SINGH

Key dates

this monthRegisteredOct 2020First promiseFeb 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Oct 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 28 Feb 2023)
  • Buildings2 building records
  • Documents filed136 files

Current status

6%2 of 36 units booked
44.1%Work done, per cost certificate

Figures as on 20 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAIRAJ ANA118321021
SAIRAJ BNA56315015

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 72%.

SAIRAJ A60%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks68%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.72%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SAIRAJ B34%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
SAIRAJ A11
SAIRAJ B11

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jan 2026
LandownerVillageDistrict
LAXMIDEEP INFRASTRUCTURESMundhawaPune

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI2260.32
Proposed, not sanctioned2,260 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 1, SECTOR 27A PRADHIKARAN NIGDI, PUNE 411044
Estimated costRs 4.00 cr
Cost incurredRs 1.77 cr
Work done44.14%
BuildingWingEstimatedIncurred
SAIRAJ ANARs 4.00 crRs 1.77 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNACHIKET PATIL
EngineerSANTOSH PATIL
Chartered AccountantSHRIKRISHNA VAIJANATH SURVASE
Chartered AccountantULHAS MANDHANE AND CO
PartnerRole in project
LAXMIDEEP INFRASTRUCTURES-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100016543Feb 2023 → Oct 2024

Reason as filed by the promoterWE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 28/02/2024

EXT52100027667Feb 2023 → Nov 2025

Reason as filed by the promoterWE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 31/11/2025.

EA21032620312Feb 2023 → Dec 2026

Reason as filed by the promoterWE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 31/12/2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed136

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 December 2020.pdf20 Mar 2026
Form 2File: Form 2 December 2020.pdf20 Mar 2026
Form 3File: Form 3 December 2020.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold And Unsold INVENTORY.pdf20 Mar 2026
Form 1File: Form 1 March 2021.pdf20 Mar 2026
Form 2File: Form 2 March 2021.pdf20 Mar 2026
Form 3File: Form 3 March 2021.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold And Unsold INVENTORY.pdf20 Mar 2026
Form 1File: Form 1 June 2021.pdf20 Mar 2026
Form 2File: Form 2 June 2021.pdf20 Mar 2026
Form 3File: Form 3 June 2021.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 September 2021.pdf20 Mar 2026
Form 2File: Form 2 September 2021.pdf20 Mar 2026
Form 3File: Form 3 September 2021.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 December 2021.pdf20 Mar 2026
Form 2File: Form 2 December 2021.pdf20 Mar 2026
Form 3File: Form 3 December 2021.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 March 2022.pdf20 Mar 2026
Form 2File: Form 2 March 2022.pdf20 Mar 2026
Form 3File: Form 3 March 2022.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 June 2022.pdf20 Mar 2026
Form 2File: Form 2 June 2022.pdf20 Mar 2026
Form 3File: Form 3 June 2022.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 September 2022_compressed.pdf20 Mar 2026
Form 2File: Form 2 September 2022.pdf20 Mar 2026
Form 3File: Form 3 September 2022.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 December 2022.pdf20 Mar 2026
Form 2File: Form 2 December 2022.pdf20 Mar 2026
Form 3File: Form 3 December 2022.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 March 2023_compressed.pdf20 Mar 2026
Form 2File: Form 2 March 2023.pdf20 Mar 2026
Form 3File: Form 3 March 2023.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 June 2023.pdf20 Mar 2026
Form 2File: Form 2 June 2023.pdf20 Mar 2026
Form 3File: Form 3 June 2023.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 September 2023.pdf20 Mar 2026
Form 2File: Form 2 September 2023.pdf20 Mar 2026
Form 3File: Form 3 September 2023.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 December 2023.pdf20 Mar 2026
Form 2File: Form 2 December 2023.pdf20 Mar 2026
Form 3File: Form 3 December 2023.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 March 2024.pdf20 Mar 2026
Form 2File: Form 2 March 2024.pdf20 Mar 2026
Form 3File: Form 3 March 2024.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 June 2024.pdf20 Mar 2026
Form 2File: Form 2 June 2024.pdf20 Mar 2026
Form 3File: Form 3 June 2024.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 September 2024.pdf20 Mar 2026
Form 2File: Form 2 September 2024.pdf20 Mar 2026
Form 3File: Form 3 September 2024.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 December 2024.pdf20 Mar 2026
Form 2File: Form 2 December 2024.pdf20 Mar 2026
Form 3File: Form 3 December 2024.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Upto Dec 24.pdf20 Mar 2026
Form 1File: Form 1 March 2025.pdf20 Mar 2026
Form 2File: Form 2 March 2025.pdf20 Mar 2026
Form 3File: Form 3 March 2025.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 June 2025.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 September 2025.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 December 2025_compressed.pdf20 Mar 2026

How this compares with Pune

6%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 46 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAIRAJ on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MORDEWADI13,700+ in Pune

Builder: LAXMIDEEP INFRASTRUCTURES

LAXMIDEEP INFRASTRUCTURES has 1 registration on MahaRERA, including SAIRAJ. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SAIRAJ is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAIRAJ?

The registered promoter entity is LAXMIDEEP INFRASTRUCTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAIRAJ?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAIRAJ?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAIRAJ?

The professionals named in the filing: Architect: NACHIKET PATIL; Engineer: SANTOSH PATIL; Chartered Accountant: SHRIKRISHNA VAIJANATH SURVASE; Chartered Accountant: ULHAS MANDHANE AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAIRAJ?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAIRAJ. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAIRAJ to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.