ReraGenieLog inGet a buyer report

Home / Browse projects / Bhandara, Maharashtra / Saibaba Complex

Completed No litigation declared Commercial project

Saibaba Complex

By KESHAV PREMLAL CHINDHALORE (HUF)

RG-MH-99983 · RERA P50600052219 · Last updated on MahaRERA portal: 29 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Bhandara registration emailed to you, free during the pilot beta.
May 2026Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Podiums (if any), 0%
16 of 33Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 105 documents Report an error

Saibaba Complex is a Commercial project by KESHAV PREMLAL CHINDHALORE (HUF) in Bhandara, Maharashtra, registered with MahaRERA as P50600052219 on 31 Jul 2023. The registration is recorded completed; possession was promised by 31 May 2026. 17 of the 33 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameSaibaba Complex
  • TypeCommercial
  • Location
    • Bhandara Raod
    • Tumsar
    • Tumsar (M Cl)
    • Bhandara
    • 441912
  • Pincode441912
  • RERA no.P50600052219
  • ReraGenie IDRG-MH-99983

Builder

  • NameKESHAV PREMLAL CHINDHALORE (HUF)
  • Entity typeOthers
  • OwnersSagar Chindhalore Chindhalore, Geeta Chindhalore Chindhalore
  • Authorizes SignatoryKeshav Chindhalore Chindhalore

Key dates

this monthRegisteredJul 2023PromisedMay 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Jul 2023
  • Promised completion31 May 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed105 files

Current status

52%17 of 33 units booked
95.1%Work done, per cost certificate

Figures as on 29 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Saibaba ComplexNA2233033

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Saibaba Complex: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Open Space5

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area666 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jan 2026

Approvals and building plan

Sanctioning authorityTumsar Municipal Council
Permissible FSI998.77
Proposed, not sanctioned999 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTumsar Bhandara
Estimated costRs 2.32 cr
Cost incurredRs 2.20 cr
Work done95.09%
BuildingWingEstimatedIncurred
Saibaba ComplexNARs 2.32 crRs 2.20 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajesh Bisney
EngineerRajesh Bisney
Chartered AccountantRishi Lashkare
Chartered AccountantRavindra Lashkare
PartnerRole in project
KESHAV PREMLAL CHINDHALORE (HUF)-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Dec 2023

Documents filed105

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A 2025-26.pdf29 May 2026
Withdrawal Update Form 1File: Form 1 Jan to Mar 2026.pdf23 Apr 2026
Withdrawal Update Form 2File: Form 2 Jan to Mar 2026.pdf23 Apr 2026
Withdrawal Update Form 3File: Form 3 Jan to Mar 2026.pdf23 Apr 2026
Form 5 (FY 2025-2026)File: Form 5 2025-26.pdf23 Apr 2026
Withdrawal Update Form 1File: Form 1 Apr to Jun 2025.pdf5 Feb 2026
Withdrawal Update Form 1File: Form 1 Apr to Jun 2025.pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2 Apr to Jun 2025.pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2 Apr to Jun 2025.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 Apr to Jun 2025(1).pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 Apr to Jun 2025(1).pdf5 Feb 2026
Withdrawal Update Form 1File: Form 1 Oct to Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Oct to Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 Oct to Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 July to Sep 2025.pdf15 Oct 2025
Withdrawal Update Form 2File: Form 2 July to Sep 2025.pdf15 Oct 2025
Withdrawal Update Form 3File: Form 3 July to Sep 2025.pdf15 Oct 2025
Withdrawal Update Form 1File: Form 1 Apr to Jun 2025.pdf20 Jul 2025
Withdrawal Update Form 2File: Form 2 Apr to Jun 2025.pdf20 Jul 2025
Withdrawal Update Form 3File: Form 3 Apr to Jun 2025(1).pdf20 Jul 2025
Form 5 (FY 2024-2025)File: Form 5 2024-25.pdf18 Jun 2025
Form 2A (FY 2023-2024)File: Form 2A 2023-24.pdf11 Jun 2025
Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf11 Jun 2025
Form 1File: Form 1 July to Sep 2023.pdf27 May 2025
Form 2File: Form 2 July to Sep 2023.pdf27 May 2025
Form 3File: Form 3 July to Sep 2023.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Q-July to Sep 2023.pdf27 May 2025
Form 1File: Form 1 Oct to Dec 2023.pdf27 May 2025
Form 2File: Form 2 Oct to Dec 2023.pdf27 May 2025
Form 3File: Form 3 Oct to Dec 2023.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Q-Oct to Dec 2023.pdf27 May 2025
Form 1File: Form 1 Jan to Mar 2024.pdf27 May 2025
Form 2File: Form 2 Jan to Mar 2024.pdf27 May 2025
Form 3File: Form 3 Jan to Mar 2024.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Q-Jan to Mar 2024.pdf27 May 2025
Form 1File: Form 1 Apr to Jun 2024.pdf27 May 2025
Form 2File: Form 2 Apr to Jun 2024.pdf27 May 2025
Form 3File: Form 3 Apr to Jun 2024.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Q-Apr to Jun 2024.pdf27 May 2025
Form 1File: Form 1 Oct to Dec 2024.pdf27 May 2025
Form 2File: Form 2 Oct to Dec 2024.pdf27 May 2025
Form 3File: Form 3 Oct to Dec 2024.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Q-Oct to Dec 2024.pdf27 May 2025
Form 1File: Form 1 Jan to Mar 2025.pdf27 May 2025
Form 2File: Form 2 Jan to Mar 2025.pdf27 May 2025
Form 3File: Form 3 Jan to Mar 2025.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Q-Jan to Mar 2025.pdf27 May 2025
Form 5 (FY 2023-2024)File: Form 5 2023-24.pdf27 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan to Mar 2025.pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jan to Mar 2025.pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jan to Mar 2025.pdf5 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan to Mar 2025.pdf5 May 2025
Disclosure of sold/ booked inventoryFile: Q-Jan to Mar 2025.pdf5 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct to Dec 2024.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Oct to Dec 2024.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct to Dec 2024.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: Q-Oct to Dec 2024.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 July to Sep 2024.pdf4 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 July to Sep 2024.pdf4 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 July to Sep 2024.pdf4 Nov 2024
Disclosure of sold/ booked inventoryFile: Q-July to Sep 2024.pdf4 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf4 Nov 2024
Form 1File: Form 1 Apr to Jun 2024.pdf26 Sep 2024
Form 2File: Form 2 Apr to Jun 2024.pdf26 Sep 2024
Form 3File: Form 3 Apr to Jun 2024.pdf26 Sep 2024
Disclosure of Sold and Booked InventoryFile: Apr to Jun 2024.pdf26 Sep 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct to Dec 2023.pdf7 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan to Mar 2024.pdf7 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Apr to Jun 2024.pdf7 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct to Dec 2023.pdf7 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan to Mar 2024.pdf7 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Apr to Jun 2024.pdf7 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Oct to Dec 2023.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Jan to Mar 2024.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Apr to Jun 2024.pdf7 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Oct to Dec 2023.pdf7 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jan to Mar 2024.pdf7 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Apr to Jun 2024.pdf7 Aug 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf1 Dec 2023

How this compares with Bhandara

52%of this project is bookeddistrict median 35%
22%of Bhandara projects moved their completion datethis one has not
44%of Bhandara registrations have lapsed or been cancelledthis one is completed

Computed across the 36 Bhandara projects on ReraGenie, from their own filings.

Keep Saibaba Complex on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tumsar36 in Bhandara

Builder: KESHAV PREMLAL CHINDHALORE (HUF)

KESHAV PREMLAL CHINDHALORE (HUF) has 1 registration on MahaRERA, including Saibaba Complex. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Bhandara district page.

Frequently asked questions

What are my rights if Saibaba Complex is delayed beyond 31 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Saibaba Complex?

The registered promoter entity is KESHAV PREMLAL CHINDHALORE (HUF), an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Saibaba Complex?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Saibaba Complex?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Saibaba Complex?

The professionals named in the filing: Architect: Rajesh Bisney; Engineer: Rajesh Bisney; Chartered Accountant: Rishi Lashkare; Chartered Accountant: Ravindra Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Saibaba Complex?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Saibaba Complex. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Saibaba Complex to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.