Sai Raghavendra's Tiara

By Sai Raghavendra Constructions and Developers

RG-KA-41172 · RERA PRM/KA/RERA/1251/446/PR/070324/006698 · Last updated on RERA Karnataka portal: 24 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jan 2026Possession promisedno revision filed
17 of 17Construction stages doneevery applicable stage filed complete
145 of 265Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 156 documents Report an error

Sai Raghavendra's Tiara is a Residential/Group Housing project by Sai Raghavendra Constructions and Developers in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/070324/006698 on 7 Mar 2024. Possession is promised by 24 Jan 2026. 120 of the 265 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSai Raghavendra's Tiara
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/070324/006698
  • ReraGenie IDRG-KA-41172

Builder

  • NameSai Raghavendra Constructions and Developers
  • Entity typePartnership Firm
  • GSTIN29ABHFS5999L1Z0
  • Authorized SignatoryManchikanti Janardhan

Key dates

this monthRegisteredMar 2024PromisedJan 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Mar 2024
  • Promised completion24 Jan 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed156 files

Current status

45%120 of 265 units booked
100.9%Of the estimated cost spent so far

Figures as on 24 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---1570157
Block B---1080108

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 24 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 24 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolNoNot applicable
GymYes100%
ParksYes100%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%
Common storage spacesNoNot applicable

Land and ownership18

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners18
LandownerVillageDistrict
P Y Vasudeva--
Vasanth--
M Narayanamurthy--
M Ramamurthy--
Murali M--
Jayaram--
Ramesh M--
Ramakrishna M--
P Y Vasudeva--
Vasanth--
M Narayanamurthy--
M Ramamurthy--
Murali M--
Ramesh M--
Jayaram--
Ramakrishna M--
Abdul Majeed Alias Mohsim--
Abdul Aziz Qader--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 116.74 cr
Cost incurredRs 117.76 cr
Spent of the estimate100.87%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 99.63 crRs 97.19 cr
Payment of taxesRs 10.57 crRs 6.90 cr
On-site expenditure-Site OverheadRs 3.73 crRs 10.87 cr
On-site expenditure-Salaries of workersRs 1.59 crRs 1.59 cr
On-site expenditure-Consultants FeesRs 76.21 lakhRs 76.21 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 45.90 lakhRs 45.90 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMD. Siddique Nawaz
EngineerMunish Sharma
Chartered AccountantNirmala Sreenivasulu

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01013/2026-Sai Raghavendra Constructions and Developers18/08/2026

Documents filed156

As listed on the registration, under the names the promoter filed them with; the newest 80 of 156 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/070324/006698 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_compressed.pdf24 Jan 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf24 Jan 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf24 Jan 2026
Q4 2025-26 Water supply and sewage board24 Jan 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)24 Jan 2026
Q4 2025-26 KPTCL- BESCOM24 Jan 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Sai Ragavendra Tiara_compressed.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5_compressed.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
TIARAFile: TIARA Name Clarification by Partners.pdf5 Mar 2024
SAI RAGHAVENDRAS BR ICON RERA CERTIFICATEFile: Sai raghavendra BR ICON RERA Certificate.pdf5 Mar 2024
ZONAL REGU BUFFER LAKE DETAILSFile: Zonal Regu Buffer Lake Details.pdf21 Feb 2024
ZONAL REGULATIONS - REVISED MASTER PLAN 2015File: Zoning_Regulations_RMP2015f Full Document.pdf21 Feb 2024
REMAINING FEE 4340 PAID RECEIPTFile: Remaining Fee 4340.pdf13 Feb 2024
ZR SHOWING LAKE IN LAKE BUFFERFile: Demarked project name in CDP.pdf13 Feb 2024
SEIAA NOCFile: MoEF SEIAA Self Signed Copy.pdf13 Feb 2024
SELF ATTESTED ENGINEER LICENCE CERTIFICATEFile: Self attested - Project Engineer Licence Certificate.pdf13 Feb 2024
ENGINEER CERTIFICATEFile: Form 3 engineers Certificate.pdf13 Feb 2024
CERTIFIED ESTIMATED COST OF CONSTRUCTIONFile: Estimated Cost of Construction Certified by Engineer.pdf13 Feb 2024
BESCOM NOC WITH RECEIPTFile: Self Attested copy of Bescom NOC.pdf13 Feb 2024
DEMARKED STP IN APPROVED DRAWING & STP DRAWINGFile: DEMARKED STP DESIGN AS PER KSPCB GUIDELINES.pdf13 Feb 2024
CERTIFIED GUIDANCE VALUEFile: Land Guidance Value marked.pdf13 Feb 2024
CERTIFICATE FROM REGISTERED ENGINEER INDICATING STRUCTURAL SAFETYFile: Certificate from Regd Engr indicating Structural Safety.pdf13 Feb 2024
Source of funds - all Partners Balance sheetsFile: Source of funds - all Partners Balance sheets.pdf26 Jan 2024
Financial Reports 20-21File: Financial Reports 20-21_compressed.pdf26 Jan 2024
Financial Reports 21-22File: Financial Reports 21-22_compressed.pdf26 Jan 2024
Financial Reports 22-23File: Financial Reports 22-23_compressed.pdf26 Jan 2024
RTC 23-24File: RTC 23-24.pdf26 Jan 2024
EC Till dateFile: EC till date.pdf26 Jan 2024
Inam deed Sy No 70/1 and 125/1File: Inam deed Sy No 70 & 125.pdf26 Jan 2024
Inam Deed Sy No 69/1File: Inam Deed Sy No 69.pdf26 Jan 2024
Sale Deed 70/1File: Sale Deed 70-1_compressed.pdf26 Jan 2024
Sale Deed 69/1File: Sale deed Nakalu 69-1.pdf26 Jan 2024
Notarised Non Litigation AffidavitFile: No Litigation Affidavit.pdf26 Jan 2024
Grant documentsFile: Grant Document.pdf26 Jan 2024
FORM B AffidavitFile: FORM B.pdf26 Jan 2024
JDA Affidavit cum DeclarationFile: JDA Affidavit.pdf26 Jan 2024
Unit wise Breakup DetailsFile: Unit wise Breakup Details.pdf26 Jan 2024
FAR Details with sanction planFile: FAR Details with sanction plan.pdf26 Jan 2024
Single Plot LayoutFile: Single Plot Layout.pdf26 Jan 2024
Single Plot Layout OrderFile: Single Plot Layout Order.pdf26 Jan 2024
Demarked project name in Village MapFile: Demarked project name in Village Map.pdf26 Jan 2024
Demarked project name in CDPFile: Demarked project name in CDP.pdf26 Jan 2024
Unit wise Breakup DetailsFile: Unit wise Breakup Details.pdf26 Jan 2024
Amenities and Common Area detailsFile: Amenities Common Areas.pdf26 Jan 2024
Engineers Certificate self attestedFile: Engineers Certificate self attested.pdf26 Jan 2024
Form 3 engineers CertificateFile: Form 3 engineers Certificate.pdf26 Jan 2024
Cost of ConstructionFile: Cost of Construction.pdf26 Jan 2024
Self attested Project SpecificationsFile: Specifications Final.pdf26 Jan 2024
Affidavit Notarised Sec(3)File: Affidavit Notarised Sec(3) Final.pdf26 Jan 2024
Agreement of saleFile: Agreement Of Sale - 260124.pdf26 Jan 2024
STP Demarked details in planFile: STP PLAN FOR RERA.jpg26 Jan 2024
Self attested guidance valueFile: Self attested guidance value.jpg26 Jan 2024
NOC KSPCBFile: PCB NOC Self Attested.pdf26 Jan 2024
NOC BWSSBFile: BWSSB NOC Self Attested.pdf26 Jan 2024
NOC BESCOMFile: Bescom NOC.pdf26 Jan 2024
BBMP LICENCEFile: Plan Sanction Licence.pdf26 Jan 2024
NOC MOEF SEIAAFile: MOEF SEIAA Self Signed.pdf26 Jan 2024
APPROVED SANCTIONED PLANSFile: Plan Sanction Drawings.pdf26 Jan 2024
Plan & ElevationsFile: Site Plan & Elevation.pdf26 Jan 2024
RTC, survey 69/1-
Mutation, survey 69/1-
Encumbrance Certificate, survey 69/1-
Conversion/Alienation Order, survey 69/1-
JDA, survey 69/1-
Khatha, survey 69/1-
RTC, survey 125/1-
Mutation, survey 125/1-
Encumbrance Certificate, survey 125/1-
Conversion/Alienation Order, survey 125/1-
JDA, survey 125/1-
Khatha, survey 125/1-
RTC, survey 70/1-
Mutation, survey 70/1-
Encumbrance Certificate, survey 70/1-
Conversion/Alienation Order, survey 70/1-
JDA, survey 70/1-

How this compares with Bengaluru Urban

45%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sai Raghavendra's Tiara on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Sai Raghavendra Constructions and Developers

Sai Raghavendra Constructions and Developers has 1 registration on RERA Karnataka, including Sai Raghavendra's Tiara. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sai Raghavendra's Tiara is delayed beyond 24 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sai Raghavendra's Tiara?

The registered promoter entity is Sai Raghavendra Constructions and Developers, a partnership firm as per the filing. Its GSTIN 29ABHFS5999L1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sai Raghavendra's Tiara?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sai Raghavendra's Tiara?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Sai Raghavendra's Tiara?

The professionals named in the filing: Architect: MD. Siddique Nawaz; Engineer: Munish Sharma; Chartered Accountant: Nirmala Sreenivasulu. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Raghavendra's Tiara?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Raghavendra's Tiara. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Raghavendra's Tiara to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.