ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SAI BALAJI ROYAL

Registration approved No litigation declared Residential/Group Housing project

SAI BALAJI ROYAL

By SAI BALAJI SHELTERS

RG-KA-64925 · RERA PRM/KA/RERA/1251/310/PR/070823/006118 · Last updated on RERA Karnataka portal: 3 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Sep 2025Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 97 documents Report an error

SAI BALAJI ROYAL is a Residential/Group Housing project by SAI BALAJI SHELTERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/070823/006118 on 7 Aug 2023. Possession is promised by 30 Sep 2025. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSAI BALAJI ROYAL
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/070823/006118
  • ReraGenie IDRG-KA-64925

Builder

  • NameSAI BALAJI SHELTERS
  • Entity typePartnership Firm
  • GSTIN29ADXFS4368P1ZN
  • Authorized SignatoryLOKESH Y M

Key dates

this monthRegisteredAug 2023First promiseSep 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Aug 2023
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Sep 2024)
  • Buildings1 building record
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---95095

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 3 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities42

As on 3 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
Jogging trackYes-
SPA roomYes-
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
KAVITHA J--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 29.84 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 21.50 cr-
On-site expenditure-Consultants FeesRs 3.65 cr-
Payment of taxesRs 2.58 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 2.10 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTNS CHAKRAVARTHI
EngineerD GURAPPA
Chartered AccountantASHISH KOPPA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/261105/006118Sep 2024 → Sep 2025

Reason as filed by the promoterAwaiting OC

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed97

As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/070823/006118 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Renewed Building plan & orderFile: Affidavit for renewal approved plan.pdf3 Oct 2026
Form BFile: Affidavit FORM b .pdf3 Oct 2026
Form BFile: Affidavit FORM b (1).pdf3 Oct 2026
ocFile: OCSBRcompressed.pdf3 Oct 2026
Provisional balance sheet Sai balaJi Shelters As on 31.03.2023File: Sai Balaji Royal Provisional balance sheet 31032023.pdf22 Jun 2023
Provisional balance sheet of Lokesh PartnerFile: Lokesh Y M Provisonal 31032023.pdf22 Jun 2023
Provisional balance sheet Anitha NK partnerFile: anitha K N provisional balance sheet 31032023.pdf22 Jun 2023
Provisional balance sheet Shivakumar PartnerFile: Shivaraj K N Provisonal balance sheet 31032023_0001.pdf22 Jun 2023
Source of completionFile: Source of completion_0001.pdf22 Jun 2023
DeclarationFile: Decalaration_0001.pdf22 Jun 2023
RTC of all propertiesFile: rtc LETTER_0001_compressed.pdf22 Jun 2023
Anitha K IT -2020-21File: Anitha IT 2020-21.pdf1 Jun 2023
Anitha K IT -2021-22File: Anitha IT 2021-22.pdf1 Jun 2023
Anitha K IT and balance sheet 2022-23File: Anitha IT and balance sheet 2022-23.pdf1 Jun 2023
Lokesh IT 2020-21File: Lokesh IT 2020-21.pdf1 Jun 2023
Lokesh IT 2021-22File: Lokesh IT 2021-22.pdf1 Jun 2023
Lokesh IT and Balance sheet 2022-23File: Lokesh IT and balance sheet 2022-23.pdf1 Jun 2023
sources of fund with supportingFile: rtc LETTER_0001_compressed.pdf1 Jun 2023
Agreement of SaleFile: AGREEMENT TO SELL sai balaji royal.pdf1 Jun 2023
BWSSB NOC demand and receiptFile: BWSSB receipt.pdf1 Jun 2023
Partners profit and loss account and balance sheet 2021-22File: sai Balaji shelters IT returns Ay 2021-22.pdf20 Apr 2023
Partners profit and loss account and balance sheet 2022-23File: sai Balaji shelters IT returns Ay 2022-23.pdf20 Apr 2023
IT Ack 2021-22File: IT Ack 2021-22.pdf20 Apr 2023
IT Ack 2022-23File: IT Ack 2022-23.pdf20 Apr 2023
Sources of fundsFile: Sources of fund_0001.pdf20 Apr 2023
chartered accountant certificate in prescribed format form -01File: CA certficate_0001.pdf20 Apr 2023
Need Title deed in the name of joint Land owner Kavitha and GowthamFile: PITION_0001_compressed.pdf20 Apr 2023
Gowtham passed away. Hence need death certificateFile: Death certficate Gautham.pdf20 Apr 2023
EC upto dateFile: EC upto date.pdf20 Apr 2023
brief estimated cost of construction for civil works certified by the EngineerFile: BOQ_0001.pdf20 Apr 2023
project specificationFile: specification_0001.pdf20 Apr 2023
Agreement for SaleFile: AGREEMENT TO SELL sai balaji royal.pdf20 Apr 2023
allotment letterFile: Proforma Allotment Letter.pdf20 Apr 2023
fee receipt paid towards power supply NOCFile: BESCOM NOC fees.jpeg20 Apr 2023
NOC issued by the concerned Water supply authorities along with the copy of fee receipt paid towardsFile: NOC Bwssb details.JPG20 Apr 2023
Registered Engineer indicating the structural safetyFile: structural stabbility certficate_0001.pdf20 Apr 2023
3(1) Notarized Affidavit.File: Affidavit_0001.pdf20 Apr 2023
STP design drawing and STP demarcation drawing as per the guidelines of KSPCB NOCFile: STP marked in plan-2.pdf20 Apr 2023
stp reportFile: STP Report.pdf20 Apr 2023
CDP mapFile: CDP.jpeg20 Apr 2023
commencement certificate noticeFile: Commencement certficate notice.pdf20 Apr 2023
SEIAA NOCFile: CFE.pdf20 Apr 2023
Sanction planFile: sanction plan 1.pdf20 Apr 2023
basement planFile: basement floor flan.pdf20 Apr 2023
ground floor planFile: Ground florr plan.pdf20 Apr 2023
terrace floorFile: Typical and terrace floor plaan.pdf20 Apr 2023
RTC, survey 56/2-
Mutation, survey 56/2-
Encumbrance Certificate, survey 56/2-
Conversion/Alienation Order, survey 56/2-
JDA, survey 56/2-
Khatha, survey 56/2-
Registration CertificateFile: PARTENRSHIP CERTFICATE.pdf-
Partnership DeedFile: partenrship agreement with reco.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 New CA.pdf-
Certificate issued by Architect Form 2File: Architect certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer certficate_compressed.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit land woner_0001.pdf-
Certificate from Chartered AccountFile: Form 1 New CA.pdf-
bescom APPROVAL_0001_compressed-
Sanction Plan-
Sanction plan-
LEGAL OPINION_0001_compressed-
JDA and sharing-
DC CONVERSION ORDER_0001_compressed (1)-
DC CONVERSION ORDER_0001_compressed (1)-
AMALGMATION DEED_0001-
sale agreement-
Allotment Letter-
Brochure-
Form B_0001_compressed-
promoter affidavit_0001_compressed-
JDA Affidavit_0001_compressed-
bescom APPROVAL_0001_compressed-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SAI BALAJI ROYAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SAI BALAJI SHELTERS

SAI BALAJI SHELTERS has 1 registration on RERA Karnataka, including SAI BALAJI ROYAL. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SAI BALAJI ROYAL is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAI BALAJI ROYAL?

The registered promoter entity is SAI BALAJI SHELTERS, a partnership firm as per the filing. Its GSTIN 29ADXFS4368P1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAI BALAJI ROYAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAI BALAJI ROYAL?

The professionals named in the filing: Architect: TNS CHAKRAVARTHI; Engineer: D GURAPPA; Chartered Accountant: ASHISH KOPPA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI BALAJI ROYAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI BALAJI ROYAL. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI BALAJI ROYAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.