Sahyadri Residency Phase I
RG-MH-89021 · RERA P51700013099 · Last updated on MahaRERA portal: 24 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sahyadri Residency Phase I is a Residential / Group Housing project by M/S NIRMAN DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700013099 on 14 Sep 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing. 12 of the 82 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete.
At a glance
Project
- NameSahyadri Residency Phase I
- TypeResidential / Group Housing
- Location
- Murbad
- Thane
- 421401
- Pincode421401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700013099
- ReraGenie IDRG-MH-89021
Builder
- NameM/S NIRMAN DEVELOPERS
- Entity typePartnership
- PartnersVINOD BALARAM KENE, MILIND SUDHAKAR DESHMUKH, NITIN BALARAM BHOIR, ASHISH BALARAM BHOIR
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Sep 2017
- Promised completion30 Dec 2023
- Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed145 files
Current status
Figures as on 24 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING 4 | NA | 6 | 6 | 38 | 2 | 40 |
| BUILDING 7/A | NA | 9 | 9 | 42 | 0 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 98%.
BUILDING 485%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
BUILDING 7/A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Satish Motiram Powale | Murbad | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Geo Associates |
| Architect | GULAMSABIR MOHAMMADHALIM CHAUDHARY |
| Engineer | Geo Associates |
| Chartered Accountant | RAHUL N GHARAT & CO |
| Chartered Accountant | Dilip Gosar |
| Partner | Role in project |
|---|---|
| M/S NIRMAN DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs you are aware, there was complete site closure from March 2020 till September 2020 due to Covid-19. Thereafter also we could not start the work in full swing due to a shortage of labor and a paucity of funds. Furthermore, there were also certain restrictions imposed by the State government to curb the covid-19 pandemic during the second wave of the pandemic which was unable to collect advances from customers due to financial difficulties faced by our prospective buyers who were looking to book or invest in our project. We are seeking extension for project Completion date which enable us to
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Sep 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Sep 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Sep 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Sep 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Apr 2024
Documents filed145
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 145 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Jun 23.pdf | 24 Jun 2026 |
| Form 2File: Form 2_Jun 23.pdf | 24 Jun 2026 |
| Form 3File: Form 3 jun 2023.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers June 2023.pdf | 24 Jun 2026 |
| Form 1File: sep 23.pdf | 24 Jun 2026 |
| Form 2File: Form2_Sep2023.pdf | 24 Jun 2026 |
| Form 3File: Form 3 sep 2023.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers September 2023.pdf | 24 Jun 2026 |
| Form 1File: Dec 23.pdf | 24 Jun 2026 |
| Form 2File: Form2_Dec2023.pdf | 24 Jun 2026 |
| Form 3File: Form 3 Dec 2023.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers december 2023.pdf | 24 Jun 2026 |
| Form 1File: June 18.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Jun 18.pdf | 23 Jun 2026 |
| Form 3File: Form 3 jun 2018.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers june 2018.pdf | 23 Jun 2026 |
| Form 1File: Sep 18.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Sep 18.pdf | 23 Jun 2026 |
| Form 3File: Form 3 Sep 2018.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers September 2018.pdf | 23 Jun 2026 |
| Form 1File: Dec 18.pdf | 23 Jun 2026 |
| Form 2File: Form 2Dec 18.pdf | 23 Jun 2026 |
| Form 3File: Form 3 Dec 2018.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers december 2018.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers March 2019.pdf | 23 Jun 2026 |
| Form 3File: Form 3 Mar 2019.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Mar 19.pdf | 23 Jun 2026 |
| Form 1File: Mar 19.pdf | 23 Jun 2026 |
| Form 1File: June 19.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Jun 19.pdf | 23 Jun 2026 |
| Form 3File: Form 3 jun 2019.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers June 2019.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers September 2019.pdf | 23 Jun 2026 |
| Form 3File: Form 3 Sep 2019.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Sep 19.pdf | 23 Jun 2026 |
| Form 1File: Sep 19.pdf | 23 Jun 2026 |
| Form 1File: Dec 19.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Dec 19.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers december 2019.pdf | 23 Jun 2026 |
| Form 3File: Dec_19.pdf | 23 Jun 2026 |
| Form 3File: Form 3 Mar 2020.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers March 2020.pdf | 23 Jun 2026 |
| Form 1File: Mar 20.pdf | 23 Jun 2026 |
| Form 2File: Form 2_MAR 20.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Jun 20.pdf | 23 Jun 2026 |
| Form 1File: June 20.pdf | 23 Jun 2026 |
| Form 3File: Form 3 June 2020.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers june 2020.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers September 2020.pdf | 23 Jun 2026 |
| Form 1File: Form 1 sep 20.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Sep 20.pdf | 23 Jun 2026 |
| Form 3File: Sep 20.pdf | 23 Jun 2026 |
| Form 3File: form3 Dec 20.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers december 2020.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Dec 20.pdf | 23 Jun 2026 |
| Form 1File: Dec 20.pdf | 23 Jun 2026 |
| Form 1File: Mar 21.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Mar_ 21.pdf | 23 Jun 2026 |
| Form 3File: Mar 21 form 3.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developer March 2021.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developers june 2021.pdf | 23 Jun 2026 |
| Form 3File: Form 3 june 21.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Jun 21.pdf | 23 Jun 2026 |
| Form 1File: June 21.pdf | 23 Jun 2026 |
| Form 1File: form 1 sep 21.pdf | 23 Jun 2026 |
| Form 3File: Sep 21.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Sep_ 21.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developer September 2021.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developer december 2021.pdf | 23 Jun 2026 |
| Form 3File: Dec_2021.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Dec 21.pdf | 23 Jun 2026 |
| Form 1File: Dec 21.pdf | 23 Jun 2026 |
| Form 1File: Mar 22.pdf | 23 Jun 2026 |
| Form 2File: Form 2_MAR 22_V2.pdf | 23 Jun 2026 |
| Form 3File: March 22.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developer March 2022.pdf | 23 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Nirman Developer june 2022.pdf | 23 Jun 2026 |
| Form 3File: Form 3 Jun 2022.pdf | 23 Jun 2026 |
| Form 2File: Form 2_Jun 22.pdf | 23 Jun 2026 |
| Form 1File: June 22.pdf | 23 Jun 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 145 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Sahyadri Residency Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Murbad7,600+ in Thane
Filed coordinates, straight-line distance. 18 registered projects within 2 km.
SUPARSHAVANATH REALITY
Rakesh Subhashchandra Shah
Techcons Basera
Techcons Constructional Engineering Co
Amber
Vajraa Developers
Sadguru Darshan
OM SADGURU REALTORS
Crystal Homes
Shreedham Construction Private Limited
Shree Darshan Heights
Shree Darshan Construction
See every Thane project, with the district possession charts
Builder: M/S NIRMAN DEVELOPERS
M/S NIRMAN DEVELOPERS has 1 registration on MahaRERA, including Sahyadri Residency Phase I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Sahyadri Residency Phase I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Sahyadri Residency Phase I is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sahyadri Residency Phase I?
The registered promoter entity is M/S NIRMAN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sahyadri Residency Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Sahyadri Residency Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sahyadri Residency Phase I?
The professionals named in the filing: Architect: Geo Associates; Architect: GULAMSABIR MOHAMMADHALIM CHAUDHARY; Engineer: Geo Associates; Chartered Accountant: RAHUL N GHARAT & CO; Chartered Accountant: Dilip Gosar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sahyadri Residency Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback