Home / Browse projects / Bengaluru Urban, Karnataka / S2 VIOLET

Registration approved No litigation declared Residential/Group Housing project

S2 VIOLET

By S2 DEVELOPERS

RG-KA-67626 · RERA PRM/KA/RERA/1251/446/PR/250523/005943 · Last updated on RERA Karnataka portal: 17 May 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 87 documents Report an error

S2 VIOLET is a Residential/Group Housing project by S2 DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/250523/005943 on 25 May 2023. Possession is promised by 31 Dec 2024.

At a glance

Project

  • NameS2 VIOLET
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/250523/005943
  • ReraGenie IDRG-KA-67626

Builder

  • NameS2 DEVELOPERS
  • Entity typeProprietorship Firm
  • GSTIN29BOHPS1404N1ZJ
  • Authorized SignatoryPERUMAL SHANKAR
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2023PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 May 2023
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed87 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
S2 VIOLET---64064

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 17 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 17 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners3
LandownerVillageDistrict
SAMUEL THOMAS--
THOMAS P KOSHY--
SHAFI ULLA KHAN SHAZIULLA KHAN--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.38 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 12.38 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVijay Associates E Roshini
EngineerPRAVEEN J
Chartered AccountantPRASANNA ADIGA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed87

As listed on the registration, under the names the promoter filed them with; the newest 80 of 87 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/250523/005943 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA Bank AccountFile: RERA Bank Account.pdf17 May 2023
Proprietorship Reg CertificateFile: Proprietorship Registration Certificate.pdf17 May 2023
Form -1 CA CertificateFile: Form 1 - CA Certificate.pdf17 May 2023
Complete ITR with CA UDIN for 2021-22File: BS and ITR 21-22 with CA UDIN.pdf17 May 2023
Complete ITR with CA UDIN 2022-23File: BS and ITR 22-23 with CA UDIN.pdf17 May 2023
Form - 2 Architect CertificateFile: Form - 2 Architect Certificate.pdf17 May 2023
Form - 3 Engineer CertificateFile: Form 3 - Engineer Certificate - S2.pdf17 May 2023
STP Demarcation PlanFile: STP Demarcation Plan.PDF17 May 2023
Conversion order and layout planFile: Conversion Order and Layout Plan.pdf17 May 2023
Complete Legal DocumentsFile: Complete Legal-1-61.pdf17 May 2023
Title DeedFile: Sale Deed.pdf17 May 2023
Specifications of the ProjectFile: Specifications of the PROJECT.pdf17 May 2023
CDP PlanFile: CDP PLAN Demarcation.pdf17 May 2023
BESCOM Noc Fees ReceiptFile: BESCOM NOC FEES PAID RECEIPT.pdf17 May 2023
BWSSB Noc Fees ReceiptFile: BWSSB FEES PAID RECEIPT.pdf17 May 2023
Structural Stability CertificateFile: Structural Stability Certificate.pdf17 May 2023
Sale Agreement ProformaFile: SALE AGREEMENT RERA FINAL.pdf17 May 2023
Sources of FundsFile: Source of Funds - S2.pdf17 May 2023
P SHANKAR - PANFile: P Shankar - Self attested PAN.pdf17 May 2023
ITR 2019-20File: ITR 2019-20.pdf17 May 2023
COMMON AREASFile: Common Areas.pdf17 May 2023
SINGLE PLOT AND RELINQUISHMENT DEEDFile: Single Plot and Relinquishment Deed.pdf17 May 2023
BBMP KHATA CERTIFICATE AND EXTRACTFile: BBMP Katha certificate and Extract.pdf20 Mar 2023
NO LITIGATION AFFIDAVITFile: No Litigation Affidavit.pdf20 Mar 2023
JOINT AFFIDAVIT CUM DECLARATIONFile: Joint Affidavit Cum Declaration.pdf20 Mar 2023
FORM BFile: Form B.pdf20 Mar 2023
3-1 AFFIDAVIT WITH ACK NUMBERFile: 3-1 Affidavit with Ack Number.pdf20 Mar 2023
ALLOTMENT LETTERFile: Allotment Letter.pdf20 Mar 2023
ADVOCATE SEARCH REPORTFile: Advocate Legal Opinion.pdf20 Mar 2023
EC TILL DATEFile: EC Till Date.pdf20 Mar 2023
CDP PLANFile: CDP PLAN.pdf20 Mar 2023
KSPCB NOCFile: KSPCB NOC.pdf20 Mar 2023
COMMENCEMENT CERTIFICATEFile: Commencement Certificate.pdf20 Mar 2023
BESCOM NOCFile: BESCOM NOC.pdf20 Mar 2023
BWSSB NOCFile: BWSSB NOC.pdf20 Mar 2023
Proprietorship CertificateFile: Proprietorship Registration Certificate.pdf20 Mar 2023
Registration CertificateFile: Registration Certificate.pdf-
Certificate issued by CA Form 1File: Form 1 - CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form - 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 - Engineer Certificate - S2.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 - CA Certificate.pdf-
Balance Sheet 2021 - 2022File: ITR AY 2021-22.pdf-
Balance Sheet 2020 - 2021File: ITR AY 2021-22.pdf-
Balance Sheet 2019 - 2020File: ITR AY 2021-22.pdf-
Audited Profit and Loss Statement 2021 - 2022File: ITR AY 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: ITR AY 2021-22.pdf-
Audited Profit and Loss Statement 2019 - 2020File: ITR AY 2021-22.pdf-
Director's Report 2021 - 2022File: ITR AY 2021-22.pdf-
Director's Report 2020 - 2021File: ITR AY 2021-22.pdf-
Director's Report 2019 - 2020File: ITR AY 2021-22.pdf-
Cash Flow Statement 2021 - 2022File: ITR AY 2021-22.pdf-
Cash Flow Statement 2020 - 2021File: ITR AY 2021-22.pdf-
Auditor's Report 2021 - 2022File: ITR AY 2021-22.pdf-
Auditor's Report 2020 - 2021File: ITR AY 2021-22.pdf-
Auditor's Report 2019 - 2020File: ITR AY 2021-22.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2021-22.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR AY 2021-22.pdf-
Building License-
BBMP Approved Plan-
BBMP Approved Plan-
BBMP Approved Plan-
BBMP Approved Plan-
BBMP Approved Plan-
BBMP Approved Plan-
BBMP Approved Plan-
JDA and GPA-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep S2 VIOLET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: S2 DEVELOPERS

S2 Developers has 2 registrations on RERA Karnataka, including BLUE MEADOWS and S2 VIOLET. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if S2 VIOLET is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of S2 VIOLET?

The registered promoter entity is S2 DEVELOPERS, a proprietorship firm as per the filing. Its GSTIN 29BOHPS1404N1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in S2 VIOLET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at S2 VIOLET?

The professionals named in the filing: Architect: Vijay Associates E Roshini; Engineer: PRAVEEN J; Chartered Accountant: PRASANNA ADIGA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in S2 VIOLET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About S2 VIOLET. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save S2 VIOLET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.