Home / Browse projects / Bengaluru Urban, Karnataka / S V Paradise

Registration approved Residential/Group Housing project

S V Paradise

By S V Builders

RG-KA-13638 · RERA PRM/KA/RERA/1251/310/PR/190809/002775

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Dec 2022Possession promisedmoved 9 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 45 documents Report an error

S V Paradise is a Residential/Group Housing project by S V Builders in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190809/002775 on 9 Aug 2019. Possession is promised by 14 Dec 2022. The completion date has moved by 9 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameS V Paradise
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/190809/002775
  • ReraGenie IDRG-KA-13638

Builder

  • NameS V Builders
  • Entity typePartnership Firm
  • Authorized SignatoryV Mallikarjuna Reddy
  • OthersV Mallikarjuna Reddy

Key dates

this monthRegisteredAug 2019First promiseMar 2022Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Aug 2019
  • Promised completion14 Dec 2022
  • Revised completionRevised to 14 Dec 2022 (originally 14 Mar 2022)
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
S V Paradise---20020

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area825 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV.SIVA KUMAR
EngineerSRINIVAS RAO BOLIMUNTA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2022 → Dec 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00415/2023-S V Builders03/04/2023

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190809/002775 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Registration certificate.jpg-
Site Drawing-
AGREEMENT FOR SALE CUM CONSTRUCTION-
AGREEMENT FOR SALE CUM CONSTRUCTION-
Conversion-sale deed-RTC-
Licenseplan-
Site Drawing-
Allotment letter-
SV Letter_compressed-
Specifications-
EC12years-
AFFIDAVIT-
Affidavit-
Khatha & Extract-
JDA Agreement-
Conversion-sale deed-
Conversion-
Site Drawing-
Specifications-
Betterment-
Balance Sheet 2017 - 2018File: BS.pdf-
Balance Sheet 2016 - 2017File: BS.pdf-
Balance Sheet 2015 - 2016File: BS.pdf-
Audited Profit and Loss Statement 2017 - 2018File: BS.pdf-
Audited Profit and Loss Statement 2016 - 2017File: BS.pdf-
Audited Profit and Loss Statement 2015 - 2016File: BS.pdf-
Director's Report 2017 - 2018File: BS.pdf-
Director's Report 2016 - 2017File: BS.pdf-
Director's Report 2015 - 2016File: BS.pdf-
Cash Flow Statement 2017 - 2018File: BS.pdf-
Cash Flow Statement 2016 - 2017File: BS.pdf-
Auditor's Report 2017 - 2018File: BS.pdf-
Auditor's Report 2016 - 2017File: BS.pdf-
Auditor's Report 2015 - 2016File: BS.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: BS.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: BS.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: BS.pdf-
Form B-
Prospectus/BrochureFile: S.V. Paradise BROUCHURE.pdf-
Advertisement Copy 1File: S.V. Paradise BROUCHURE.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_190809_002775 (2).xlsx-
Occupancy CertificateFile: OCCUPANCY CERTIFICATE.pdf-
Completion certificate issued by the competent authorityFile: OCCUPANCY CERTIFICATE.pdf-
Registered Agreement of SaleFile: Agrement.pdf-
Registered conveyance deed for an individual unitFile: saledeeds.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep S V Paradise on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmS V ParadiseOther 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: S V Builders

S V Builders has 1 registration on RERA Karnataka, including S V Paradise. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if S V Paradise is delayed beyond 14 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of S V Paradise?

The registered promoter entity is S V Builders, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in S V Paradise?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against S V Paradise?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at S V Paradise?

The professionals named in the filing: Architect: V.SIVA KUMAR; Engineer: SRINIVAS RAO BOLIMUNTA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in S V Paradise?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About S V Paradise. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save S V Paradise to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.