Home / Browse projects / Mumbai Suburban, Maharashtra / ROYAL STONE
ROYAL STONE
By VaibhavLaxmi Builders and Developers
RG-MH-30094 · RERA P51800029854 · Last updated on MahaRERA portal: 1 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 23 months past the filed date
- Completion date moved by 11 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ROYAL STONE is a Others project by VaibhavLaxmi Builders and Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029854 on 8 Jul 2021. Possession was promised by 30 Nov 2024 and is now 23 months past that date. The completion date has moved by 11 months from the original filing.
At a glance
Project
- NameROYAL STONE
- TypeOthers
- Location
- KANNAMWAR NAGAR 1
- VIKHROLI EAST
- Kurla
- Mumbai Suburban
- 400083
- Pincode400083
- RERA no.P51800029854
- ReraGenie IDRG-MH-30094
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Jul 2021
- Promised completion30 Nov 2024
- Revised completionRevised to 30 Nov 2024 (originally 31 Dec 2023)
- Buildings3 building records
- Documents filed67 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 24 | 0 | 0 | 0 | 0 |
| Wing B | NA | 24 | 0 | 0 | 0 | 0 |
| Wing C | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 1 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 40%.
Wing A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing C4%
| Activity | Progress |
|---|---|
| Excavation | 40% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed120
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 53 | 53 |
| Wing B | 53 | 53 |
| Wing C | 14 | 14 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RANGREKHA CHSL | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sachin Raje |
| Engineer | AJAY MAHALE |
| Chartered Accountant | NARENDRA KADAV |
| Partner | Role in project |
|---|---|
| VaibhavLaxmi Builders and Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThis project layout is a redevelopment project consisting of Mhada housing society called Rangrekha along with MHADA office buildings 5&6. As the office buildings belonged to MHADA, we as developer were required to handover 26 flats to MHADA in lieu of development rights of the plot. The 23 storey building consisting of A&B wings with rehab, sale and MHADA flats is built on plot physically belonging to Rangrekha CHS is fully ready. However, MHADA was unable to grant us physical possession of the plot belonging to them. On the office building plot MHADA had as a amenity provided a Hall which wa
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Jun 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed67
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Sep 2023.pdf | 1 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Dec 2023.pdf | 1 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory - March 24.pdf | 1 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory - June 2024.pdf | 1 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Sep 2024.pdf | 1 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Dec 2024.pdf | 1 Apr 2025 |
| Declaration in FORM BFile: Form B - Affidavit cum declaration.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 30th Sept 2021 Disclosure of Inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 31st Dec 2021 Disclosure of Inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 31st Mar 2022 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 31st June 2022 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 30th June 2023 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 30th Sep 2023 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 31st Dec 2023 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 31st Mar 2024 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 30th June 2024 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 30th Sep 2024 Disclosure of inventory.pdf | 13 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: 31st Dec 2024 Disclosure of inventory.pdf | 13 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal Stone Dec 24 (1)_compressed.pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal Stone Sep 24_compressed.pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal Stone June 24_compressed (1).pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024_compressed.pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal stone Dec 23(1).pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal stone Sep 2023_compressed.pdf | 11 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 June 23 (1)_compressed.pdf | 11 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June - Form 2.pdf | 11 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep - Form 2.pdf | 11 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec - Form 2.pdf | 11 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO-1 JUNE 2024.pdf | 8 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO- 1 SEPT 2024.pdf | 8 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1 - DEC 2024.pdf | 8 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO-1 MARCH 2024.pdf | 8 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Aditya Sangle.pdf | 8 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Anita Sangle.pdf | 8 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Ramdas Sangle.pdf | 8 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - amit pangam.pdf | 8 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality assurance certificate.pdf | 8 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Signed Form 5.pdf | 8 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-20-21.pdf | 21 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A - 2021-2022.pdf | 21 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 2022 Royal Stone_compressed (1).pdf | 21 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2022 Royal Stone_compressed.pdf | 21 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royalstone June'2022.pdf | 21 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 23 Royal Stone_compressed.pdf | 21 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ROYAL STONE MARCH 2023.pdf | 18 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed Form 5 (Royal Stone)FY-22-23.pdf | 15 Dec 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Full CC of wing A AND b.pdf | 14 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (1).pdf | 14 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form_2A.pdf | 12 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Royal Stone.pdf | 12 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royalstone June 22.pdf | 23 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed Form 5 FY 2021-22.pdf | 11 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrances Royal Stone.pdf | 20 Mar 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrances Royal Stone.pdf | 20 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Royal Stone.pdf | 20 Mar 2023 |
| Proforma of Allotment letterFile: Agreement to Sale-Building 17 and 19.pdf | 30 Jun 2021 |
| Copy of the legal title reportFile: Title Report Format A- VLBD.pdf | 29 Jun 2021 |
| PAN CardFile: vaibhavlaxmipan PAN card.pdf | 17 Jun 2021 |
| Declaration about Commencement CertificateFile: Declaration (2).pdf | 17 Jun 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf | 17 Jun 2021 |
| Layout approvalFile: 17-19 AMENDED PLAN (1).pdf | 15 Jun 2021 |
| Building plan approvalFile: 17-19 AMENDED PLAN (1).pdf | 15 Jun 2021 |
| Details of encumbrancesFile: Details of Encumbrance.pdf | 15 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: 17-19 AMENDED PLAN (1).pdf | 15 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 17-19 AMENDED PLAN (1).pdf | 15 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 8th June 2021.pdf | 15 Jun 2021 |
| Declaration in FORM BFile: Form B Developer.pdf | 15 Jun 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations, which the RERA portal never shows together
- All 67 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ROYAL STONE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VIKHROLI EAST6,700+ in Mumbai Suburban
Cons 1221 MIG T/S and 100 Shops S. No. 113 (pt
Mumbai Housing And Area Development Board
Om Siddhivinayak CHS and Gurukrupa CHS
Shreeji Developers
AKASSH AMAZONIA TOWER 1
HEER MEHTA LANDMARK DEVELOPERS PRIVATE LIM
Ajmera Solis
Shree Yogi Realcon Private Limited
CENTRAL PARK
V LAXMI NURSES DEVELOPERS LLP
Swastik Platinum
SUVASYA BUILDERS AND DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: VaibhavLaxmi Builders and Developers
VaibhavLaxmi Builders and Developers has 9 registrations on MahaRERA, including Green Vista and Stella Residency. Its filings disclose 8 earlier MahaRERA projects: declares 6 of 8 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that ROYAL STONE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ROYAL STONE is delayed beyond 30 Nov 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ROYAL STONE?
The registered promoter entity is VaibhavLaxmi Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ROYAL STONE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ROYAL STONE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ROYAL STONE?
The professionals named in the filing: Architect: Sachin Raje; Engineer: AJAY MAHALE; Chartered Accountant: NARENDRA KADAV. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ROYAL STONE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback