Registered No litigation declared Others projectMHADA redevelopment

ROYAL STONE

By VaibhavLaxmi Builders and Developers

RG-MH-30094 · RERA P51800029854 · Last updated on MahaRERA portal: 19 Aug 2026

Why this is marked a redevelopment: this filing shows 32 flats filed as rehab units, MahaRERA's column for homes returned to existing occupants or owners; MHADA as the sanctioning authority in Mumbai. MahaRERA has no redevelopment field, so this is ReraGenie's reading of the filing. Redevelopment across Mumbai Suburban.

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 48 months from the original
20 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 40%
71 of 190Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

ROYAL STONE is a Others project by VaibhavLaxmi Builders and Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029854 on 8 Jul 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 48 months from the original filing. 119 of the 190 units on this registration are recorded sold or booked, and 20 of 33 construction stages are filed complete.

At a glance

Project

  • NameROYAL STONE
  • TypeOthers
  • Location
    • KANNAMWAR NAGAR 1
    • VIKHROLI EAST
    • Kurla
    • Mumbai Suburban
    • 400083
  • Pincode400083
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800029854
  • ReraGenie IDRG-MH-30094

Builder

  • NameVaibhavLaxmi Builders and Developers
  • Entity typePartnership
  • GSTIN27AAGFV5861J1ZN
  • PartnersAnita Ramdas Sangle, Amit Ajit Pangam, Ramdas Maruti Sangle
  • Other registrations8 more →
  • Completed6 of 9
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredJul 2021First promiseDec 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Jul 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2023)
  • Buildings3 building records
  • Documents filed85 files

Current status

63%119 of 190 units booked

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA242486793
Wing BNA242486490
Wing CNA66077

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 40%.

Wing A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing C4%
ActivityProgress
Excavation40%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed120

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots120
Closed/Covered120
BuildingClosed/CoveredTotal
Wing A5353
Wing B5353
Wing C1414

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,821 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Aug 2026
LandownerVillageDistrict
RANGREKHA CHSLKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityBuilding Permission Cell, Greater Mumbai / MHADA
Permissible FSI11711.99
Proposed, not sanctioned9,712 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVikhroli

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSachin Raje
EngineerAJAY MAHALE
EngineerAtul Sawant
Chartered AccountantNARENDRA KADAV
Chartered AccountantKapure & Kapure
PartnerRole in project
VaibhavLaxmi Builders & Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018140Dec 2023 → Nov 2024

Reason as filed by the promoterThis project layout is a redevelopment project consisting of Mhada housing society called Rangrekha along with MHADA office buildings 5&6. As the office buildings belonged to MHADA, we as developer were required to handover 26 flats to MHADA in lieu of development rights of the plot. The 23 storey building consisting of A&B wings with rehab, sale and MHADA flats is built on plot physically belonging to Rangrekha CHS is fully ready. However, MHADA was unable to grant us physical possession of the plot belonging to them. On the office building plot MHADA had as a amenity provided a Hall which wa

EA25082622389Dec 2023 → Dec 2027

Reason as filed by the promoterIt may be noted that the A Wing and B Wing are fully complete and we have already received Part Occupancy Certificate from the Competent Authority that is MHADA as on 20th March 2024.The project is on the land CTS No. 356 Part admeasuring 1820.69 square Meters at Vikhroli. It is a redevelopment project of the buildings comprising Building No. 17, Building No. 19, Building No. 5 & Building No. 6. The land of the building is owned by the MHADA. Out of these 4 buildings, two buildings that is Building No. 5 & 6 are commercial buildings.The key reason for delay of the project is legal disputes reg

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM NO-1 MARCH 2024.pdf19 Aug 2026
Form 2File: MARCH 24.pdf19 Aug 2026
Form 3File: Form 3 March 24_compressed.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of inventory - March 24.pdf19 Aug 2026
Form 1File: FORM NO-1 JUNE 2024.pdf19 Aug 2026
Form 2File: Form - 2 - June 24_unlocked.pdf19 Aug 2026
Form 3File: Form 3 Royal Stone June 24_compressed.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of inventory - June 2024.pdf19 Aug 2026
Form 1File: FORM NO- 1 SEPT 2024.pdf19 Aug 2026
Form 2File: Form -2 - Sep 24_unlocked.pdf19 Aug 2026
Form 3File: Form 3 Royal Stone Sep 24_compressed.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of inventory - Sep 2024.pdf19 Aug 2026
Form 1File: FORM - 1 - DEC 2024.pdf19 Aug 2026
Form 2File: Form 2 - Dec 24_unlocked.pdf19 Aug 2026
Form 3File: Form 3 Royal Stone Dec 24_compressed.pdf19 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of inventory - Dec 2024.pdf19 Aug 2026
Form 2A (FY 2023-2024)File: Form 2A March 24.pdf19 Aug 2026
Form 5 (FY 2023-2024)File: Final Signed Form 5.pdf19 Aug 2026
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Sep 2023.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Dec 2023.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - March 24.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - June 2024.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Sep 2024.pdf1 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Dec 2024.pdf1 Apr 2025
Declaration in FORM BFile: Form B - Affidavit cum declaration.pdf28 Mar 2025
Disclosure of sold/ booked inventoryFile: 30th Sept 2021 Disclosure of Inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 31st Dec 2021 Disclosure of Inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 31st Mar 2022 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 31st June 2022 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 30th June 2023 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 30th Sep 2023 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 31st Dec 2023 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 31st Mar 2024 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 30th June 2024 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 30th Sep 2024 Disclosure of inventory.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: 31st Dec 2024 Disclosure of inventory.pdf13 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal Stone Dec 24 (1)_compressed.pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal Stone Sep 24_compressed.pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal Stone June 24_compressed (1).pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024_compressed.pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal stone Dec 23(1).pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royal stone Sep 2023_compressed.pdf11 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 June 23 (1)_compressed.pdf11 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June - Form 2.pdf11 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep - Form 2.pdf11 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec - Form 2.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO-1 JUNE 2024.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO- 1 SEPT 2024.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1 - DEC 2024.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO-1 MARCH 2024.pdf8 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Aditya Sangle.pdf8 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Anita Sangle.pdf8 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Ramdas Sangle.pdf8 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - amit pangam.pdf8 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality assurance certificate.pdf8 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Signed Form 5.pdf8 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-20-21.pdf21 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A - 2021-2022.pdf21 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 2022 Royal Stone_compressed (1).pdf21 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2022 Royal Stone_compressed.pdf21 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royalstone June'2022.pdf21 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 23 Royal Stone_compressed.pdf21 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ROYAL STONE MARCH 2023.pdf18 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed Form 5 (Royal Stone)FY-22-23.pdf15 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Full CC of wing A AND b.pdf14 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (1).pdf14 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form_2A.pdf12 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Royal Stone.pdf12 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Royalstone June 22.pdf23 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed Form 5 FY 2021-22.pdf11 Apr 2023
Details of encumbrances concerned to FinanceFile: Encumbrances Royal Stone.pdf20 Mar 2023
Details of encumbrances concerned to LegalFile: Encumbrances Royal Stone.pdf20 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Royal Stone.pdf20 Mar 2023
Proforma of Allotment letterFile: Agreement to Sale-Building 17 and 19.pdf30 Jun 2021
Copy of the legal title reportFile: Title Report Format A- VLBD.pdf29 Jun 2021
PAN CardFile: vaibhavlaxmipan PAN card.pdf17 Jun 2021
Declaration about Commencement CertificateFile: Declaration (2).pdf17 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf17 Jun 2021
Layout approvalFile: 17-19 AMENDED PLAN (1).pdf15 Jun 2021
Building plan approvalFile: 17-19 AMENDED PLAN (1).pdf15 Jun 2021

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered on promise2 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VICTORIA 54P51800025304VIKHROLI EAST, Mumbai Suburban145Apr 2020CompletedDec 2025Jun 2024
Templum HeightsP51800021056Vikhroli East, Mumbai Suburban-May 2019CompletedDec 2024Feb 2023
OlympusP51800022877Vikhroli East, Mumbai Suburban-Nov 2019CompletedDec 2024Oct 2022
Stella ResidencyP51800006691Vikhroli East, Mumbai Suburban-Aug 2017CompletedOct 2022Registered original: Apr 2021Feb 2022
Stella Sapphire A WingP51800007545Vikhroli East, Mumbai Suburban-Aug 2017CompletedDec 2019Nov 2019
Stella Sapphire B WIngP51800003333Kurla, Mumbai Suburban-Aug 2017CompletedDec 2018Late, Nov 2019
Green VistaP51800008487Vikhroli East, Mumbai Suburban-Aug 2017CompletedDec 2018Late, Sep 2019

How this compares with Mumbai Suburban

63%of this project is bookeddistrict median 29%
35%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
20%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,900+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROYAL STONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIKHROLI EAST6,900+ in Mumbai Suburban

Builder: VaibhavLaxmi Builders and Developers

VaibhavLaxmi Builders and Developers has 9 registrations on MahaRERA, including Green Vista and Stella Residency. Its filings disclose 8 earlier MahaRERA projects: declares 6 of 8 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ROYAL STONE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYAL STONE?

The registered promoter entity is VaibhavLaxmi Builders and Developers, a partnership as per the filing. Its GSTIN 27AAGFV5861J1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYAL STONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROYAL STONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYAL STONE?

The professionals named in the filing: Architect: Sachin Raje; Engineer: AJAY MAHALE; Engineer: Atul Sawant; Chartered Accountant: NARENDRA KADAV; Chartered Accountant: Kapure & Kapure. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYAL STONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYAL STONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYAL STONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.