Home / Browse projects / Thane, Maharashtra / Rohini

Completed No litigation declared Residential / Group Housing project

Rohini

By Thilayaparambil Kumaran Joshi

RG-MH-46902 · RERA P51700013602 · Last updated on MahaRERA portal: 29 Aug 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

Rohini is a Residential / Group Housing project by Thilayaparambil Kumaran Joshi in Thane, Maharashtra, registered with MahaRERA as P51700013602 on 16 Oct 2017. The registration is recorded completed; possession was promised by 30 Dec 2024. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameRohini
  • TypeResidential / Group Housing
  • Location
    • Khativali
    • Thane
    • Shahapur
    • 421604
  • Pincode421604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700013602
  • ReraGenie IDRG-MH-46902

Builder

  • NameThilayaparambil Kumaran Joshi
  • Entity typeIndividual
  • Declared earlier projects5 →

Key dates

this monthRegisteredOct 2017First promiseJun 2021Revised toDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Oct 2017
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building Number - 1NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Building Number - 1: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area864 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI835.38
Proposed, not sanctioned835 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTulsi Height, Shop No - 8,9,10, Plot No - 1, Sector-5, New Panvel, maharashtra

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRagini Jadaun
ArchitectArun Ramkrishna Karnik
PartnerRole in project
Thilayaparambil Kumaran Joshi-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010159Jun 2021 → Jun 2024

Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Dec 2022

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: New Format Form 5 Rohini FY 2022-23.pdf29 Aug 2023
Disclosure of sold/ booked inventoryFile: Circular 29- Rohini.pdf13 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Rohini as on December 2022.pdf8 Feb 2023
Certificates of CA (Form 3)File: Form 3- Rohini as on December 2022.pdf8 Feb 2023
CERSAI detailsFile: Rohini.pdf27 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Rohini as on September 2022.pdf23 Dec 2022
Certificates of CA (Form 3)File: Form 3- Rohini as on September 2022.pdf23 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Rohini- Occupancy Certificate.pdf23 Dec 2022
Architect’s Certificate on Completion of Project (Form 4)File: Rohini- Form 4.pdf23 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Rohini FY 21-22.pdf30 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Rohini Certificate as on 31-08-2022 CA' Certificate.pdf16 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Final Form 5 Rohini FY 20-21_compressed.pdf2 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Rohini as on 31-03-2022.pdf24 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Rohini as on 30-06-2022.pdf24 Aug 2022
Certificates of CA (Form 3)File: Form 3 Certificate as on 31-03-2022.pdf24 Aug 2022
Certificates of CA (Form 3)File: Form 3 Certificate as on 30-06-2022.pdf24 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Rohini 30-09-2021.pdf9 Aug 2022
Certificates of CA (Form 3)File: Form 3 Certificate 177.pdf9 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rohini dec 2021_compressed (1).pdf1 Aug 2022
Certificates of CA (Form 3)File: Form 3 Rohini as on 31st December 2021.pdf1 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Rohini.pdf2 Jul 2021
Declaration about Commencement CertificateFile: CC Declaration Rohini .pdf1 Jul 2021
Disclosure of sold/ booked inventoryFile: Lakshmi Developers -Rohini.pdf26 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Rohini FY 18-19.pdf26 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Rohini FY 19-20.pdf26 Jun 2021
Certificates of CA (Form 5)File: Lakshmi developers form 5 .pdf1 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - compressed .pdf28 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 lakshmi -compressed.pdf28 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Lakshmi Developers Form 1.pdf29 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf28 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf28 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate.pdf28 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf28 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf28 Mar 2018
Certificates of CA (Form 3)File: Form 3.pdf28 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf27 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf27 Dec 2017
Certificates of CA (Form 3)File: Form 3.pdf27 Dec 2017
Building plan approvalFile: Building Plan - 1 (1).pdf29 Sep 2017
Building plan approvalFile: Building Plan - 1 (2).pdf29 Sep 2017
Building plan approvalFile: Building Plan - 1 (3).pdf29 Sep 2017
Layout approvalFile: Layout Plan - NA.pdf29 Sep 2017
Layout approvalFile: Layout Plan Drawing.pdf29 Sep 2017
PAN CardFile: Pan Card.pdf29 Sep 2017
Copy of the legal title reportFile: Search_Report.pdf29 Sep 2017
Copy of the legal title reportFile: Title Certificate.pdf29 Sep 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf29 Sep 2017
Copy of Layout Approval (in case of layout)File: Layout Plan - NA.pdf29 Sep 2017
Copy of Layout Approval (in case of layout)File: Layout Plan Drawing.pdf29 Sep 2017
Building Plan Approval (IOD)File: Building Plan - 1 (1).pdf29 Sep 2017
Building Plan Approval (IOD)File: Building Plan - 1 (2).pdf29 Sep 2017
Building Plan Approval (IOD)File: Building Plan - 1 (3).pdf29 Sep 2017
Declaration in FORM BFile: Form B.pdf29 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf29 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf29 Sep 2017
Certificates of CA (Form 3)File: Form 3.pdf29 Sep 2017
Proforma of Allotment letterFile: Rera Agreement FINAL .pdf29 Sep 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER .pdf29 Sep 2017
OtherFile: Development 1.pdf29 Sep 2017
OtherFile: Development 2.pdf29 Sep 2017
OtherFile: Development 3.pdf29 Sep 2017

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Parthasarathi A , BPlot no - 11 12 13 Khativali Shahpur Thane 42160435CompletedSep 2015Sep 2015
GokulPlot No - 26 Khativali Shahpur Thane - 42160414CompletedDec 2013Nov 2013
Radheshyam BPlot No - 23 Khativali Shahpur thane - 42160414CompletedDec 2012Late, Jan 2013
Radheshyam APlot No - 22 Khativali Shahpur Thane - 42160414CompletedJun 2012Jun 2012
RukminiPlot No - 5 Khativali Shahpur Thane - 42160410CompletedApr 2012Apr 2012

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 42 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rohini on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane7,600+ in Thane

2 kmRohiniCompleted 4Lapsed / revoked 10Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 28 registered projects within 2 km.

Builder: Thilayaparambil Kumaran Joshi

Thilayaparambil Kumaran Joshi has 1 registration on MahaRERA, including Rohini. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 5 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Rohini is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rohini?

The registered promoter entity is Thilayaparambil Kumaran Joshi, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rohini?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rohini?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rohini?

The professionals named in the filing: Architect: Ragini Jadaun; Architect: Arun Ramkrishna Karnik. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rohini?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rohini. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rohini to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.