Home / Browse projects / Bengaluru Urban, Karnataka / Rohan Upavan - Phase 3

Registration approved Residential/Group Housing project

Rohan Upavan - Phase 3

By Rohan Builders

RG-KA-69840 · RERA PRM/KA/RERA/1251/309/PR/190517/002554 · Last updated on RERA Karnataka portal: 2 Feb 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jun 2024Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 89 documents Report an error

Rohan Upavan - Phase 3 is a Residential/Group Housing project by Rohan Builders in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/190517/002554 on 17 May 2019. Possession is promised by 30 Jun 2024. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameRohan Upavan - Phase 3
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/190517/002554
  • ReraGenie IDRG-KA-69840

Builder

  • NameRohan Builders
  • Entity typePartnership Firm
  • Authorized SignatorySantosh B Lunkad
  • OthersMr K Balaraj and Others, Suhas K Lunkad
  • Other registrations8 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredMay 2019First promiseSep 2023Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 May 2019
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Sep 2023)
  • BuildingsNot stated in filing
  • Documents filed89 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,293 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 52.88 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP.N.MEDAPPA
EngineerMR. T S GURURAJ

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2023 → not stated

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed89

As listed on the registration, under the names the promoter filed them with; the newest 80 of 89 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/190517/002554 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement CertificateFile: Upavan Commencement Certificate Bldg 2.pdf2 Feb 2022
Commencement CertificateFile: Upavan CC Bldg-2 Partial (F,G,H,I).pdf27 Sep 2021
modified sanction planFile: Modified Site Plan with all Phase Marked.jpg20 May 2021
earlier sanction planFile: Upavan Original Plan Sanction.jpg20 May 2021
breakup of the earlier sanctioned project for 144 units wing wiseFile: break up for 144 unit -earlier plan.xlsx20 May 2021
breakup of the modified sanctioned project for 127 units wing wiseFile: break up for 127 units wing BHK wise.xlsx20 May 2021
Modified planFile: Modified Site Plan with all Phase Marked.jpg19 Mar 2021
breakup of the earlier sanctioned project for 144 units wing wiseFile: breakup of the earlier sanctioned project for 144 units wing wise.pdf19 Mar 2021
breakup of the modified sanctioned project for 127 units wing wiseFile: breakup of the modified sanctioned project for 127 units wing wise.pdf19 Mar 2021
Floor Plans of the original registered projectFile: ORIGINAL UPAVAN FLOOR PLANS.pdf4 Feb 2021
project-wise marking on the modified site planFile: Modified Site Plan with all Phase Marked.jpg4 Feb 2021
modified sanction floor plansFile: Modified Upavan Floor Plans.pdf4 Feb 2021
carpet areas as per original sanctionedFile: Upavan Phase 3 Carpet Area as per original sanction plan.pdf4 Feb 2021
carpet areas as per modified sanction planFile: Upavan Phase 3 Carpet Area as per modified sanction plan.pdf4 Feb 2021
Breakup for 127 units as per modified plan wing wiseFile: Upavan Phase 3 Abstract of the total, sold and unsold units and block wise number of units4 Feb 2021
Fire NOCFile: Fire Corrigendum Noc Upavan.pdf4 Feb 2021
ECFile: Environment Clearance.pdf4 Feb 2021
AAI NOCFile: New AAI NOC.pdf4 Feb 2021
BWSSB NOCFile: BWSSB NOC.pdf4 Feb 2021
BSNL NOCFile: BSNL Kyalasanahalli NOC.pdf4 Feb 2021
KSPCB NOCFile: KSPCB NOC.pdf4 Feb 2021
CertificateFile: RB ROF Certificate.pdf-
Already registered project ongoing detailsFile: Upavan 3 Project Registration Details.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified BBMP Licence Plan Building 2.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Elevation Section Upavan.pdf-
List Of AllotteesFile: Sold Unsold and List of Alloottees Upavan Phase 3.pdf-
Consent LetterFile: Consent Letters Upavan Phase 3.pdf-
Chartered Accountant CertificateFile: CA Certificate Upavan Phase 3 Modification Application.pdf-
Notarized AffidavitFile: Notarized Affidavit Upavan Phase 3 Modification Application.pdf-
Engineer CertificateFile: Engineer Certificate Modification Application Upavan Phase 3.pdf-
Architect CertificateFile: Architect Certificate Modification Application Upavan Phase 3.pdf-
Structural Engineer Certificate for stability of structureFile: Structural Engineer Certificate Modification Application Upavan Phase 3.pdf-
Modification of Plan DetailsFile: Building Plan First Floor .pdf-
Modification of Plan DetailsFile: Modified Project:Site Plan.jpg-
Modification of Plan DetailsFile: Upavan Phase 3A and 3 Commencement Certificate F,G,H,I Wings.pdf-
Modification of Plan DetailsFile: Upavan Phase 3A and 3 Commencement Certificate F,G,H,I Wings.pdf-
Modification of Plan DetailsFile: Sold Unsold and List of Alloottees Upavan Phase 3.pdf-
Modification of Plan DetailsFile: Sold Unsold and List of Alloottees Upavan Phase 3.pdf-
Document 1File: Fire Corrigendum Noc Upavan.pdf-
CC-
BBMP Site Plan-
Sale Deed Draft Upavan-
ATS Phase 3 - FG Block-
Saledeed & RTC-
Approved Section Plan-
DP Approval-
Allotment Letter for Phase 3 (FG)-
Upavan Brochure-
Upavan SPECIFICATIONS-
All Encumbrance Certificates-
Khata-
JD-
Title Opinion-
Conversion Order-
Relinquishment BDA-
Fire Force NOC-
AAI NOC-
BESCOM NOC-
BWSSB NOC-
KSPCB NOC-
SEIAA NOC-
BSNL NOC-
BBMP Approved Layout Plan-
Approved Section Plan-
CLU-NA-
Balance Sheet 2016 - 2017File: Balance Sheet 2017.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 2016.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet 2015.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & Loss Account 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss Account 2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit & Loss Account 2015.pdf-
Director's Report 2016 - 2017File: Directors Report.pdf-
Director's Report 2015 - 2016File: Directors Report.pdf-
Director's Report 2014 - 2015File: Directors Report.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow Statement.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow Statement.pdf-
Auditor's Report 2016 - 2017File: Auditors Report.pdf-
Auditor's Report 2015 - 2016File: Auditors Report.pdf-
Auditor's Report 2014 - 2015File: Auditors Report.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR-Ack 2017.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Rohan Upavan - Phase 1-OngoingSep 2022Not delivered

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Rohan Upavan - Phase 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmRohan Upavan - Phase 3Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: Rohan Builders

Rohan Builders has 9 registrations on RERA Karnataka, including Rohan Upavan - Phase 1 and Rohan Upavan - Phase 2. Its filings declare 6 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Rohan Upavan - Phase 3 is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Rohan Upavan - Phase 3?

The registered promoter entity is Rohan Builders, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Rohan Upavan - Phase 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Rohan Upavan - Phase 3?

The professionals named in the filing: Architect: P.N.MEDAPPA; Engineer: MR. T S GURURAJ. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rohan Upavan - Phase 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rohan Upavan - Phase 3. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rohan Upavan - Phase 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.