ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Right Grishma

Registration approved Residential/Group Housing project

Right Grishma

By Right Properties INc

RG-KA-62990 · RERA PRM/KA/RERA/1251/308/PR/210319/004018 · Last updated on RERA Karnataka portal: 5 Mar 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Aug 2023Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 93 documents Report an error

Right Grishma is a Residential/Group Housing project by Right Properties INc in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/210319/004018 on 19 Mar 2021. Possession is promised by 16 Aug 2023. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameRight Grishma
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/210319/004018
  • ReraGenie IDRG-KA-62990

Builder

  • NameRight Properties INc
  • Entity typePartnership Firm
  • Authorized SignatoryHarish Kumar Kudlu

Key dates

this monthRegisteredMar 2021First promiseAug 2022Revised toAug 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Mar 2021
  • Promised completion16 Aug 2023
  • Revised completionRevised to 16 Aug 2023 (originally 16 Aug 2022)
  • Buildings1 building record
  • Documents filed93 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Grishma---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 5 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 5 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,526 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJagadish M
EngineerC Manjunath

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/308/PR/230606/004018Aug 2022 → Aug 2023

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed93

As listed on the registration, under the names the promoter filed them with; the newest 80 of 93 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/210319/004018 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Bank Account for the projectFile: Bank Account.pdf5 Mar 2021
Audited Balance Sheet for FY 201819with CA UDINFile: Balance Sheet year 1819.pdf5 Mar 2021
Audited Profit and Loss account for FY 201819with CA UDINFile: Profit and Loss year 1819.pdf5 Mar 2021
Notarised Form BFile: Notarised Form B.pdf5 Mar 2021
Approved Plan GF FF SF TF and TerraceFile: Plans GF FF SF TF and Terrace.pdf5 Mar 2021
Stilt and SectionFile: Plans Stilt and Section.pdf5 Mar 2021
NOC for Water SupplyFile: NOC for water supply.pdf5 Mar 2021
Bank StatementFile: Bank Statement.pdf21 Oct 2020
P&L and Balance Sheet for year 2018-19File: 20200928 - Final Accounts 18-19 with Auditor Membership No..pdf21 Oct 2020
Notarised AffidavitFile: Notarised Affidavit on Stamp paper.pdf21 Oct 2020
Approved plan for Ground, First, Second, Third and Terrace planFile: Ground, First, Second, Third and Terrace.pdf21 Oct 2020
Approved plan for Stilt & SectionFile: Stilt & Section.pdf21 Oct 2020
Bank StatementFile: Bank Statement.pdf15 Oct 2020
Notarised AffidavitFile: Notarised Affidavit in Stamp paper (1).pdf5 Oct 2020
Sale Deed Site No. 44File: Site 44.pdf7 Sep 2020
Sale Deed Site No. 48File: Site 48.pdf7 Sep 2020
EC for Site 43File: Site43.pdf7 Sep 2020
EC for Site 44File: Site44.pdf7 Sep 2020
EC for Site 48File: Site48.pdf7 Sep 2020
GF, FFFile: 20200813 - Approved Ploan Ground, First, Second, Third and Terrace.pdf7 Sep 2020
Stilt & SectionFile: 20200813 - Approved Plan Stilt & Section.pdf7 Sep 2020
Partnership DeedFile: 20141226 - RPI partnership deed.pdf7 Sep 2020
Notarised AffidavitFile: Affidavit.pdf7 Sep 2020
CertificateFile: 20150315 - RPI Registration Certificate.jpg-
Architect Certificate for Work Completion Schedule till DateFile: 20230309 - Architect Certificate on status - Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: 20230330 - Chartered Engineer -Form Ex 5 - Status of work.pdf-
CA Certificate for Funds UtilizationFile: 20230224 - CA Certificate.pdf-
Architect Certificate for Pending Work Completion Schedule.File: 20230309 Architect Certificate for pending work Ex2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: 20230330 - Chartered Engineer -Form Ex 6 - Pending work.pdf-
CA Certificate for Funds required for Project CompletionFile: WILL PROVIDE SOON.pdf-
AffidavitFile: 20230309 - Affidavit Form - Ex7compressed.pdf-
Latest Encumbrance CertificateFile: 20230120 - EC for sites 43, 44 & 48 from 1Apr21 to 17Jan23.pdf-
Details Of Sold/ Un-sold UnitsFile: WILL PROVIDE SOON.pdf-
20200323 - Purasabha Construction License-
20200813 - Approved Ploan Ground, First, Second, Third and Terrace-
Sreenidhi Layout Plan-
Proforma Sale Deed-
Agreement to Sell-
Sale Deed - 43-
20200813 - Approved Plan Stilt & Section-
Area Development plan-
In Process-
20200129 - Single Khatha - Right Grishma-
WILL PROVIDE SOON-
20200129 - Single Khatha - Right Grishma-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Right Grishma - PCB-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Sreenidhi Layout Plan-
20200813 - Approved Plan Stilt & Section-
Land conversion-
Unnamed document-
Balance Sheet 2018 - 2019File: In Process.pdf-
Balance Sheet 2017 - 2018File: 20200813 - 2018-19 Balance Sheet.pdf-
Balance Sheet 2016 - 2017File: 20200709 - 2017-18 Balance Sheet.pdf-
Audited Profit and Loss Statement 2018 - 2019File: In Process.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 20200709 - 2018-19 P & L.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 20200709 - 2017-18 P & L.pdf-
Auditor's Report 2018 - 2019File: In Process.pdf-
Auditor's Report 2017 - 2018File: 20200813 - 2018-19 Audit Report.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Right Grishma on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Right Properties INc

Right Properties INc has 1 registration on RERA Karnataka, including Right Grishma. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Right Grishma is delayed beyond 16 Aug 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Right Grishma?

The registered promoter entity is Right Properties INc, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Right Grishma?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Right Grishma?

The professionals named in the filing: Architect: Jagadish M; Engineer: C Manjunath. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Right Grishma?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Right Grishma. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Right Grishma to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.