Home / Browse projects / Thane, Maharashtra / Regency Anantam Phase IV

Completed No litigation declared Residential / Group Housing project

Regency Anantam Phase IV

By REGENCY NIRMAN LTD

RG-MH-56319 · RERA P51700033477 · Last updated on MahaRERA portal: 24 Dec 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Aug 2023Possession promisedregistration recorded completed
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

Regency Anantam Phase IV is a Residential / Group Housing project by REGENCY NIRMAN LTD in Thane, Maharashtra, registered with MahaRERA as P51700033477 on 22 Feb 2022. The registration is recorded completed; possession was promised by 31 Aug 2023. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRegency Anantam Phase IV
  • TypeResidential / Group Housing
  • Location
    • Dombivli
    • Dombivli (East)
    • Dawadi
    • Kalyan
    • Thane
    • 421203
  • Pincode421203
  • RERA no.P51700033477
  • ReraGenie IDRG-MH-56319

Builder

  • NameREGENCY NIRMAN LTD
  • Entity typeCompany
  • CINU41001MH2005PLC153966
  • GSTIN27AADCR5058B1ZK
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorMAHESH SATYANARAYAN KHAIRARI
  • Other registrations28 more →
  • Completed19 of 29
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects12 →

Key dates

this monthRegisteredFeb 2022PromisedAug 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Feb 2022
  • Promised completion31 Aug 2023
  • Revised completionNone
  • Buildings2 building records
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASPEN Building No 5NA310000
ZINNIA Building No 23NA310000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

ASPEN Building No 5100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ZINNIA Building No 23100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,417 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI30143.54
Proposed, not sanctioned30,144 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVIKHROLI

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
REGENCY NIRMAN LTD-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604352MUKUND MAHADEO KHAMKARREGENCY NIRMAN LTD12/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Nov 2023

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: REGENCY ANANTAM PHASE IV.pdf24 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold PHASE IV.pdf23 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Anantam Phase 4.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Certificate Anantam Phase IV_compressed.pdf29 Nov 2023
Layout approvalFile: pHASE IV.pdf28 Nov 2023
Layout approvalFile: pHASE IV.pdf28 Nov 2023
Copy of Layout Approval (in case of layout)File: pHASE IV.pdf28 Nov 2023
Copy of Layout Approval (in case of layout)File: pHASE IV.pdf28 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for28 Nov 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Phase IV.pdf28 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC dated 01082023 phase 4 5 6.pdf19 Sep 2023
Disclosure of sold/ booked inventoryFile: anantam phase 4.pdf16 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Anantam Phase IV.pdf14 Dec 2022
Proforma of Allotment letterFile: Agreement Letter.pdf20 Sep 2022
Copy of the legal title reportFile: Anantam Title Report compressed.pdf9 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anantam Phase 4 CA CERTIFICATE compressed.pdf29 Jan 2022
Layout approvalFile: Anantam 081021.pdf25 Jan 2022
Building plan approvalFile: Bldg 5 and 23.pdf25 Jan 2022
PAN CardFile: 1 PAN Card.pdf25 Jan 2022
Details of encumbrancesFile: Saraswat Bank Sanction Letter 080621.pdf25 Jan 2022
Copy of Layout Approval (in case of layout)File: Anantam 081021.pdf25 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: Bldg 5 and 23.pdf25 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 081021.pdf25 Jan 2022
Declaration about Commencement CertificateFile: Anantam Phase IV form D.pdf25 Jan 2022
Declaration in FORM BFile: Affidavit Anantam Phase IV.PDF25 Jan 2022
CERSAI detailsFile: DAVDI SR 51 2A 52 297.pdf25 Jan 2022
Proforma of Allotment letterFile: Allottment Letter.pdf25 Jan 2022
Proforma of Allotment letterFile: Agreement of sale.pdf25 Jan 2022

Promoter's earlier projects14

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise9 delivered late3 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Regency Antilia Phase VIII AvanaP51700052485Mharal, Thane475Sep 2023OngoingDec 2026Not due yet
Regency Antilia Phase VIII AvanaP51700052485Mharal, Thane475Sep 2023OngoingDec 2026Not due yet
Regency Antilia Phase VIII AvanaP51700052485Mharal, Thane475Sep 2023OngoingDec 2026Not due yet
Regency Sarvam Phase 7Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605271-CompletedMay 2017Late, Jul 2017
Regency Sarvam Phase 6Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605271-CompletedMay 2017May 2017
Regency Sarvam Phase 5Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605134-CompletedDec 2016Late, Feb 2017
Regency Sarvam Phase 4Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605234-CompletedApr 2016Late, Jun 2016
Regency ClassicSurvey NO 54 Hissa no 4 Mumbai Bangalore Highway Near Mahindra Showroom Baner Pune-411045132-CompletedOct 2015Late, Mar 2016
Regency Sarvam Phase 3Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605552-CompletedMar 2015Late, Dec 2015
Regency Sarvam Phase 2Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605424-CompletedMar 2015Late, Aug 2015
Regency HeightsNr Brahmand Phase-1 AzadNagar Kolshet Road Thane W - 400607320-CompletedMar 2015Late, Mar 2015
Regency CrestRegency Crest Plot no 40 Sector 19 Kharghar Navi Mumbai - 410 210142-CompletedJun 2014Late, Dec 2014
Regency WillowsPlot no 61 Green Valley Behind Fariyas Hotel Tungari Lonavala24-CompletedFeb 2014Feb 2014
Regency Sarvam Phase 1Gupta Estates Near Titwala Railway Station Ganpati Mandir Road Titwala E - 421605.350-CompletedOct 2013Late, Mar 2014

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Regency Anantam Phase IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dombivli (East)7,600+ in Thane

Builder: REGENCY NIRMAN LTD

REGENCY NIRMAN LTD has 29 registrations on MahaRERA, including Regency Antilia Phase - I and Regency Antilia Phase - II. Its filings disclose 12 earlier MahaRERA projects: declares 2 of 11 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Regency Anantam Phase IV is delayed beyond 31 Aug 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Regency Anantam Phase IV?

The registered promoter entity is REGENCY NIRMAN LTD, a company as per the filing. Its CIN U41001MH2005PLC153966 and GSTIN 27AADCR5058B1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Regency Anantam Phase IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Regency Anantam Phase IV?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Regency Anantam Phase IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Regency Anantam Phase IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Regency Anantam Phase IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Regency Anantam Phase IV to a free account