Red flags

  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 42 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 70%
41 of 46Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

Redevelopment of Vijayshree Chsl is a Residential / Group Housing project by Heritage Lifestyles & Developers Pvt Ltd in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800025556 on 28 Jun 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 42 months from the original filing. 5 of the 46 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameRedevelopment of Vijayshree Chsl
  • TypeResidential / Group Housing
  • Location
    • nath pai Nagar
    • Ghatkopar
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • RERA no.P51800025556
  • ReraGenie IDRG-MH-28305

Builder

  • NameHeritage Lifestyles & Developers Pvt Ltd
  • Entity typeCompany
  • CINU70102MH2009PTC190870
  • DirectorGirish Partabrai Gangwani
  • ChairpersonPradeep Somashekar Shetty
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects18 →

Key dates

this monthRegisteredJun 2020First promiseJun 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Jun 2020
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed85 files

Current status

11%5 of 46 units booked
75.0%Work done, per cost certificate

Figures as on 18 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Anjali HeritageNA151246046

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.

Anjali Heritage: 55% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes30%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes85%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered44
Open Space16

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,066 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Nov 2025
LandownerVillageDistrict
Vijayshree ChslKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityBrihanmumbai Municipal Corporation
Permissible FSI3165.12
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Shabi Complex, Plot no 110- 111, Sector 12, vashi mumbai 400703
Estimated costRs 32.00 cr
Cost incurredRs 24.01 cr
Work done75.02%
BuildingWingEstimatedIncurred
-NARs 17.92 crRs 13.60 cr
Anjali HeritageNARs 14.08 crRs 10.41 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectConstructive India
EngineerVishwakarma Enterprises
Chartered AccountantShyom C Agrowol AND Co
PartnerRole in project
Heritage Lifestyles & Developers Pvt Ltd-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800019102Jun 2024 → Jun 2025

Reason as filed by the promoterDUE TO A DISPUTE RAISED BY THE NAEHIBOURING SOCIETY WITH BMC IN REGARDING OUR PROJECT DUE TO WHICH THE PROJECT GOT STALLED FOR 2 YEARS EVENTUALLY, WE AND OUR SOCIETY JOINTLY APPROACHED THE COLLECTOR SUBURBAN. HE CALLED FOR JOINT HEARING WITH ALL PARTIES AND PASSED ORDER IN OUR FAVOUR

EA17022619881Jun 2024 → Dec 2027

Reason as filed by the promoterDue to unforeseen legal and technical challenges beyond the control of the Developer which led to procedural delays in obtaining necessary approvals, sanctions, and permissions from MCGM and other competent authorities

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 May 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 May 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 May 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: VIJAYSHREE CHS Architect Certificate Form1_compressed.pdf18 Dec 2025
Withdrawal Update Form 2File: VIJAYSHREE CHS Annexure B FORM 2 Engineer Form_compressed.pdf18 Dec 2025
Withdrawal Update Form 3File: Anjali CA certificate April to June 2025.pdf18 Dec 2025
Form 3File: ANJALI HERITAGE CA.pdf6 Dec 2025
Form 2File: ANJALI HERITAGE ANNEXURE B FORM 2_0001.pdf6 Dec 2025
Form 1File: VIJAYSHREE CHSL ANNEXURE A FORM 1 ARCHITECT CERTIFICATE q4.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: sold unsold inventory Vijayshree.pdf6 Dec 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANJALI HERITAGE ANNEXURE B FORM 2_0001.pdf19 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VIJAYASHREE.PDF19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ANJALI HERITAGE ANNEXURE C FORM 2A_0001.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIJAYSHREE CHSL ANNEXURE A FORM 1 ARCHITECT CERTIFICATE q4.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ANJALI HERITAGE CA Q4_compressed.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VIJAYSHREE CHSL ANNEXURE B FORM 2 ENGINEER'S CERTIFICATE_compressed.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: sold unsold inventory Vijayshree.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: VIJAYSHREE CHSL ANNEXURE C FORM 2A ENGINEER'S CERTIFICATE_compressed.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: VIJAYSHREE CHSL ANNEXURE C FORM 2A ENGINEER'S CERTIFICATE_compressed.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANJALI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE (4).pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANJALI HERITAGE ANNEXURE B FORM 2 ENGINEER'S CERTIFICATE_4.pdf17 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: ANJALI CA.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANJALI HERITAGE.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VIJAYSHREE CA.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PDF.pdf19 Oct 2024
Declaration in FORM BFile: form B Anjali.pdf4 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANJALI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE.pdf25 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANNEXURE B FORM 2 ENGINEERS CERTIFICATE.pdf25 May 2024
Building plan approvalFile: ANJALI DRAWING.pdf23 May 2024
Building plan approvalFile: anjali plan compressed.pdf23 May 2024
Building Plan Approval / NA Order for plotted developmentFile: ANJALI DRAWING.pdf23 May 2024
Building Plan Approval / NA Order for plotted developmentFile: anjali plan compressed.pdf23 May 2024
Declaration about Commencement CertificateFile: Format D Anjali Heritage.pdf23 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anjali Heritage CA.pdf23 May 2024
Building plan approvalFile: Drawing.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Drawing.pdf10 Apr 2024
Disclosure of sold/ booked inventoryFile: sold unsold inventory Anjali.pdf29 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: oct - dec CA.pdf29 Mar 2024
Disclosure of sold/ booked inventoryFile: sold and unsold inventory - Anjali.pdf20 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 Anjali.pdf15 Mar 2024
Declaration in FORM BFile: affidavit cum declaration ANJALI.pdf14 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Anjali Form 5.pdf8 Mar 2024
Proforma of Agreement for saleFile: Sale Agreement anjali.pdf7 Mar 2024
Declaration about Commencement CertificateFile: CC REVALIDATION ANJALI HERITAGE.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: sold unsold inventory.pdf29 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of intrest in other real estate organisation.pdf26 Feb 2024
Proforma of Agreement for saleFile: Agreement-for-Sale Format ANJALI.pdf23 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANJALI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anjali Heritage Engineer Certificate.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate ( Oct- Dec 2023).pdf19 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format A anjali.pdf8 Dec 2023
Proforma of Agreement for saleFile: Agreement-for-Sale Format.pdf7 Dec 2023
Declaration about Commencement CertificateFile: Validated CC Anjali.pdf14 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf14 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANJALI HERITAGE ANNEXURE B FORM 2 ENGINEERS CERTIFICATE.pdf14 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE.pdf14 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ANJALI HERTAGE CA CERTIFICATE_.pdf14 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANJALI HERITAGE ANNEXURE B FORM 2 ENGINEERS CERTIFICATE _0001.pdf11 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ANJALI HERITAGE ANEXURE C FORM 2A QUALITY ASSURANCE CERTIFICATE _0001.pdf11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ANJALI HERTAGE CA CERTIFICATE.pdf11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ANJALI HERTAGE CA CERTIFICATE.pdf11 Nov 2023
Details of encumbrancesFile: Encumbrance on Project.pdf17 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTFICATE- ANJALI_.pdf8 Feb 2023
Details of encumbrances concerned to LegalFile: Encumbrances.pdf27 Jul 2022
Declaration about Commencement CertificateFile: Format- D.pdf27 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200243108609_For_Asset_Based_Search_26_07_2022_13_15_21_997.pdf26 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_ Anjali Heritage.pdf26 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANJALI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE.pdf19 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANJALI HERITAGE ANNEXURE A FORM 1 ARCHITECT CERTIFICATE (4).pdf19 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ANJALI HERITAGE ANNEXURE-B FORM -2 ENGINEER CERTIFICATE.pdf19 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ANJALI HERITAGE ANNEXURE-C FORM -2A ENGINEER CERTIFICATE QUALITY ASSURANCE CERTIFICATE.pdf19 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE ANJALI HERITAGE.pdf19 Jul 2022
Proforma of Allotment letterFile: RERA Agreement for Sale draft.pdf30 May 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijayshree Architect's Certificate (Form-1) Ongoing Projects.pdf23 May 2020
Proforma of Allotment letterFile: Vijayshree Allottment Letter Format.pdf23 May 2020
Declaration in FORM BFile: RERA Form B_Vijayshree.pdf16 May 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 engineers certificate .pdf16 May 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 10 Engineers Certificate on Quality Assurance Form 2A.pdf16 May 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 CA certificate.pdf16 May 2020
Building plan approvalFile: IOD Vijayshree.pdf14 May 2020
Layout approvalFile: CTS Plan Vijayshree .pdf14 May 2020
Copy of Layout Approval (in case of layout)File: CTS Plan Vijayshree .pdf14 May 2020

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Heritage CastlePlot no 121 Sindhi Society Chembur Mumbai21CompletedSep 2016Late, Nov 2016
Mahalaxmi HeritagePlot no 159A Central Avenue Road Chembur Mumbai26CompletedDec 2015Late, Feb 2016
Amar Villa HeritagePlot no 375 Road no 09 Chembur Mumbai20CompletedDec 2015Late, Feb 2016
Krishna HeritagePlot no 146 14th Road Chembur Mumbai20CompletedOct 2015Late, Dec 2015
Sringar HeritagePlot no 209 11th Road Chembur Mumbai24CompletedMay 2010Late, Jul 2010

How this compares with Mumbai Suburban

11%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Redevelopment of Vijayshree Chsl on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghatkopar6,700+ in Mumbai Suburban

Builder: Heritage Lifestyles & Developers Pvt Ltd

Heritage Lifestyles & Developers Pvt.Ltd. has 5 registrations on MahaRERA, including Redevelopment of Apsara CHS Ltd. and Redevelopment of Tirandaz Subha Niketan CHS Ltd.. Its filings disclose 18 earlier MahaRERA projects: declares 0 of 18 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Redevelopment of Vijayshree Chsl is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Redevelopment of Vijayshree Chsl?

The registered promoter entity is Heritage Lifestyles & Developers Pvt Ltd, a company as per the filing. Its CIN U70102MH2009PTC190870 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Redevelopment of Vijayshree Chsl?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Redevelopment of Vijayshree Chsl?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Redevelopment of Vijayshree Chsl?

The professionals named in the filing: Architect: Constructive India; Engineer: Vishwakarma Enterprises; Chartered Accountant: Shyom C Agrowol AND Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Redevelopment of Vijayshree Chsl?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Redevelopment of Vijayshree Chsl. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Redevelopment of Vijayshree Chsl to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.