Registration approved Residential/Group Housing project

RBD STILLWATERS-BLOCK 2 WING C

By RBD Shelters LLP

RG-KA-65502 · RERA PRM/KA/RERA/1251/446/PR/170824/000104

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
May 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 57 documents Report an error

RBD STILLWATERS-BLOCK 2 WING C is a Residential/Group Housing project by RBD Shelters LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/170824/000104 on 24 Aug 2017. Possession is promised by 5 May 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameRBD STILLWATERS-BLOCK 2 WING C
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/170824/000104
  • ReraGenie IDRG-KA-65502

Builder

  • NameRBD Shelters LLP
  • Entity typePartnership Firm
  • Authorized SignatoryAustin Roach
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseAug 2021Revised toMay 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Aug 2017
  • Promised completion5 May 2022
  • Revised completionRevised to 5 May 2022 (originally 5 Aug 2021)
  • Buildings6 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
O - Tower---11011
V- Tower---13013
W - Tower---12012
X - Tower---909
Y - Tower---707
Z -Tower---909

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,800 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 25.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTUSHAR VASUDEVAN
EngineerMANOHAR CONSULTANTS

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionAug 2021 → May 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/170824/000104 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: RBD- Conversion Certificate.pdf-
COMMENCEMENT CERTIFICATE-
BBMP PLAN SANCTION-
DEVELOPMENT PLAN-
Sale Deed-
AGREEMENT TO SELL-
SALE DEED IN SY NO 71 89 90-
BUILDING 1 AND 2 Section & Elevation Wing C & D-
DEVELOPMENT PLAN-
Allotment Letter-
UNDER PROGRESS-
all Nocs-
Specification_Apt-
ENCUMBRANCE CERIFICATE 01-04-2017 TO 14-08-2017-
KHATA CERTIFICATE-
JDA-
Official Memorandum SY NO 71 89 90-
DEED OF RELINQUISHMENT-
FIRE NOC DATED 29-06-2017-
Airport Authority NOC-
BESCOM-
BWSSB-
KSPCB-
MOEF-
BSNL-
Balance Sheet 2015 - 2016File: BS 2015-16.pdf-
Balance Sheet 2014 - 2015File: BS 2014-15.pdf-
Balance Sheet 2013 - 2014File: BS 2013-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P n L 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P n L 2014-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P n L 2013-14.pdf-
Director's Report 2015 - 2016File: no director report.pdf-
Director's Report 2014 - 2015File: no director report.pdf-
Director's Report 2013 - 2014File: no director report.pdf-
Auditor's Report 2015 - 2016File: Audit Report 2015-16.pdf-
Auditor's Report 2014 - 2015File: Audit Report 2014-15.pdf-
Auditor's Report 2013 - 2014File: audit report.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2014-15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR 2013-14.pdf-
FORM B-
Prospectus/BrochureFile: Prospectus NA.pdf-
Advertisement Copy 1File: Marketing NA.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_170824_000104 (1).xlsx-
Stability CertificateFile: Stability Certificate.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: BWSSB.pdf-
NOC issued by the Fire Force department after completion of workFile: FIRE NOC.pdf-
Occupancy CertificateFile: Occupancy Certificate.pdf-
Consent for operation issued by KSPCBFile: KSPCB.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: BESCOM.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4CC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit Notary.PDF-
Engineer CertificateFile: Form-6 Engineer Certificate.pdf-
Approved PlanFile: Approved Plan.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep RBD STILLWATERS-BLOCK 2 WING C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmRBD STILLWATERS-BLOCK 2 Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: RBD Shelters LLP

RBD SHELTERS LLP has 3 registrations on RERA Karnataka, including RBD MEADOWS 1 and ROACH CICADA. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if RBD STILLWATERS-BLOCK 2 WING C is delayed beyond 5 May 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of RBD STILLWATERS-BLOCK 2 WING C?

The registered promoter entity is RBD Shelters LLP, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in RBD STILLWATERS-BLOCK 2 WING C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RBD STILLWATERS-BLOCK 2 WING C?

The professionals named in the filing: Architect: TUSHAR VASUDEVAN; Engineer: MANOHAR CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RBD STILLWATERS-BLOCK 2 WING C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RBD STILLWATERS-BLOCK 2 WING C. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RBD STILLWATERS-BLOCK 2 WING C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.