Home / Browse projects / Shivamogga, Karnataka / RASHI PURALE1
RASHI PURALE1
By Rashi Infra
RG-KA-19156 · RERA PRM/KA/RERA/1271/486/PR/110422/004826 · Last updated on RERA Karnataka portal: 25 Mar 2022
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
RASHI PURALE1 is a Plotted Development project by Rashi Infra in Shivamogga, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1271/486/PR/110422/004826 on 11 Apr 2022. Possession is promised by 31 Jul 2022.
At a glance
Project
- NameRASHI PURALE1
- TypePlotted Development
- Location
- Shivamogga
- 577222
- Pincode577222
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1271/486/PR/110422/004826
- ReraGenie IDRG-KA-19156
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on11 Apr 2022
- Promised completion31 Jul 2022
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed122 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership3
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Babanna | - | - |
| Malleshappa | - | - |
| Nanjundappa | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 67.21 lakh | - |
| Project approval- JDA stamp duty, UGD, Water, MESCOM, SUDA supervision etc | Rs 32.75 lakh | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | Jeevan Kumar K |
| Chartered Accountant | Bheemashankar Deshmukh |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed122
As listed on the registration, under the names the promoter filed them with; the newest 80 of 122 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1271/486/PR/110422/004826 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Profit and Loss with UDINFile: Rashi Infra - 2020-21 Audited Profit Loss Statement.pdf | 25 Mar 2022 |
| CA certificate for the projectFile: RASHI_Purale1-CA-Certificate.pdf | 25 Mar 2022 |
| Title deed siddappa to babanaFile: Siddappa-to-Nanjappa-sons-Deed.pdf | 25 Mar 2022 |
| Title deed siddappa to malleshapaFile: Siddappa-to-Nanjappa-sons-Deed.pdf | 25 Mar 2022 |
| Title deed siddappa to najundappaFile: Siddappa-to-Nanjappa-sons-Deed.pdf | 25 Mar 2022 |
| Relinquishment Deed CAFile: Purale 05 CA Handover.pdf | 25 Mar 2022 |
| Relinquishment Deed Park and RoadFile: Purale 05 Relinquishment Deed - Road_Park.pdf | 25 Mar 2022 |
| Approved layout planFile: Final release plan-Signed-engineer.jpg | 25 Mar 2022 |
| SUDA land use - yellow for residentialFile: SUDA-CDP-Demaraction-Purale-Syno5.jpg | 25 Mar 2022 |
| SUDA approved residential DemarcationFile: SUD-Approved-Demarcation-Plan.jpg | 25 Mar 2022 |
| Architect-engineer-with-COA-numberFile: 2021R-Architect-Certificate-Jeevan.pdf | 25 Mar 2022 |
| Engineer certified planFile: Final release plan-Signed-engineer.jpg | 25 Mar 2022 |
| Attested copy water NOCFile: Purale 05 - WATER NOC With Notaty-attested.pdf | 25 Mar 2022 |
| Attested copy power supply MESCOMFile: Purale 05 - MESCOM NOC With Notaty-attested.pdf | 25 Mar 2022 |
| Notarized affidavit with acknowledgementFile: Notarized-Affidavit-with-ACK.pdf | 25 Mar 2022 |
| AoS proforma updated with amenities etcFile: Purale1-Proforma AGREEMENT FOR SALE.pdf | 25 Mar 2022 |
| RTC, survey 5/4 | - |
| Mutation, survey 5/4 | - |
| Encumbrance Certificate, survey 5/4 | - |
| Conversion/Alienation Order, survey 5/4 | - |
| JDA, survey 5/4 | - |
| Khatha, survey 5/4 | - |
| RTC, survey 5/5 | - |
| Mutation, survey 5/5 | - |
| Encumbrance Certificate, survey 5/5 | - |
| Conversion/Alienation Order, survey 5/5 | - |
| JDA, survey 5/5 | - |
| Khatha, survey 5/5 | - |
| RTC, survey 5/8 5/7 5/6 | - |
| Mutation, survey 5/8 5/7 5/6 | - |
| Encumbrance Certificate, survey 5/8 5/7 5/6 | - |
| Conversion/Alienation Order, survey 5/8 5/7 5/6 | - |
| JDA, survey 5/8 5/7 5/6 | - |
| Khatha, survey 5/8 5/7 5/6 | - |
| Registration CertificateFile: Rashi Infra - Partnership Registration Certificate.pdf | - |
| Partnership DeedFile: Rashi Infra - Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1 | - |
| Certificate issued by Engineer Form 3 | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: Signed-Non-Litigation.pdf | - |
| Certificate from Chartered Account | - |
| Certificate issued by Architect | - |
| Balance Sheet 2020 - 2021File: Rashi Infra - 2020-21 Balance Sheet.pdf | - |
| Balance Sheet 2019 - 2020File: Rashi Infra - 2019-20 Balance Sheet.pdf | - |
| Balance Sheet 2018 - 2019File: Rashi Infra - 2018-19 Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: Rashi Infra - 2020-21 Audited Profit Loss Statement.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Rashi Infra - 2019-20 Profit Loss Statement.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: Rashi Infra - 2018-19 Audited PandL_with UDIN.pdf | - |
| Director's Report 2020 - 2021File: Directors_Report_NA.pdf | - |
| Director's Report 2019 - 2020File: Directors_Report_NA.pdf | - |
| Director's Report 2018 - 2019File: Directors_Report_NA.pdf | - |
| Cash Flow Statement 2020 - 2021File: CashFlowStatement_NA.pdf | - |
| Cash Flow Statement 2019 - 2020File: CashFlowStatement_NA.pdf | - |
| Auditor's Report 2020 - 2021File: Rashi Infra - 2020-21 Auditor Report.pdf | - |
| Auditor's Report 2019 - 2020File: Rashi Infra - 2019-20 Auditor Report.pdf | - |
| Auditor's Report 2018 - 2019File: Rashi Infra - 2018-19 Auditor Report.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: Rashi Infra - 2020-21 IT Return Acknowledgement.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: Rashi Infra - 2019-20 IT Return Acknowledgement.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: Rashi Infra - 2018-19 IT Return Acknowledgement.pdf | - |
| Purale 05 Approved Plan With Letter | - |
| Purale 05 - NOC MESCOM | - |
| Purale 05 - NOC WATER | - |
| Purale Sy No 05 Final Plan | - |
| Purale Sy No 05 Final Plan | - |
| Purale Sy No 05 Final Plan | - |
| Purale1-Project-Specification | - |
| Purale Sy No 05 Final Plan | - |
| Merge_JDAs | - |
| Purale Sy No 5-6-7-8-DC Conversion | - |
| Purale1-Proforma AGREEMENT FOR SALE | - |
| Purale1-Proforma-ALLOTMENT-LETTER | - |
| LATER | - |
| LATER | - |
| Signed-Affidavit-Voilation | - |
| Signed-Joint-Cum-Declaration | - |
| Purale 05 - NOC MESCOM | - |
| Purale 05 - NOC WATER | - |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| VIRUPINAKOPPA | Sy No 32, Virupinakoppa village, Shivamogga Tq | Completed | - | No date filed |
| SrirampuraShivamogga | Sy No 81,Srirampura village,Shivamogga Tq, Shivamogga | Completed | - | No date filed |
| RASHIBGANGUR1 | Sy No 66/3 BasavanagangurHolaluru Shivamogga | Completed | - | No date filed |
| RASHI BOMMANAKATTE1 | SY NO 125/4, 125/5, 125/6, 126/1,127/1, 127/2, 127/3 AND 127/6BOOMANAKATTE VILLAGESHIVAMOGGA, SHIVAMOGGA dist | Completed | - | No date filed |
| HarigeShimoga | Sy No 22/3, Harigevillage,Shivamogga Tq | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Shivamogga
Computed across the 140+ Shivamogga projects on ReraGenie, from their own filings.
Keep RASHI PURALE1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shivamogga140+ in Shivamogga
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
Construction of 2048 houses at Bhadravathi
Commissioner
Construction of1836 Houses at Gopishetty koppa
Rajiv Gandhi Housing corporation ltd
Construction of 288 Dus for houseless at Sorab
TMC soraba
LAGANA SKYLINE
G P BUILDERS & DEVELOPERS
Construction of Powra Karmika Housing
CIty Corporation Shivamogga
SIRI
M R GROUPS
See every Shivamogga project, with the district possession charts
Builder: Rashi Infra
Rashi Infra has 9 registrations on RERA Karnataka, including HarigeShimoga and RASHI ISLAPUR1. Its filings declare 13 earlier projects, 11 of them declared completed. Read the full track record. See more projects on the Shivamogga district page.
Frequently asked questions
What are my rights if RASHI PURALE1 is delayed beyond 31 Jul 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of RASHI PURALE1?
The registered promoter entity is Rashi Infra, a partnership firm as per the filing. Its GSTIN 29AASFR7264F1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in RASHI PURALE1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at RASHI PURALE1?
The professionals named in the filing: Engineer: Jeevan Kumar K; Chartered Accountant: Bheemashankar Deshmukh. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RASHI PURALE1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback