Home / Browse projects / Bengaluru Urban, Karnataka / RAMYA WATER FRONT

Registration approved No litigation declared Residential/Group Housing project

RAMYA WATER FRONT

By RAMYA ESTATES

RG-KA-73805 · RERA PRM/KA/RERA/1251/472/PR/051225/008313 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2027Possession promisedno revision filed
4 of 16Construction stages donefurthest along: RCC or MS Framed structure, 72%
39 of 39Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 103 documents Report an error

RAMYA WATER FRONT is a Residential/Group Housing project by RAMYA ESTATES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/051225/008313 on 5 Dec 2025. Possession is promised by 30 Jun 2027. 0 of the 39 units on this registration are recorded sold or booked, and 4 of 16 construction stages are filed complete.

At a glance

Project

  • NameRAMYA WATER FRONT
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/472/PR/051225/008313
  • ReraGenie IDRG-KA-73805

Builder

  • NameRAMYA ESTATES
  • Entity typePartnership Firm
  • GSTIN29ABAFR4070N1ZS
  • Authorized SignatoryP. Umapathi Naidu

Key dates

this monthRegisteredDec 2025PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Dec 2025
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed103 files

Current status

0%0 of 39 units booked
2.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RAMYA WATER FRONT---39039

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 16 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 72%.

Building: 38% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure72%
Masonry Construction52%
Plastering inside , outside & Ceiling39%
Joinery: Doors, Windows, Ventilators etc20%
Basic work of Water supply, Sanitary and Electrification18%
Dadoing, Skirting, Flooring, Tiles work (All types)10%
Railing and Grill fixing5%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes21%
Sewage and Drainage SystemYes32%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes39%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes32%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes15%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes26%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes38%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffYes25%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners3
LandownerVillageDistrict
Narayanaswamy--
K. Gowramma--
Nagashayana H--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 89.42 cr
Cost incurredRs 2.53 cr
Spent of the estimate2.83%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 85.05 crRs 2.53 cr
Payment of taxesRs 3.00 cr-
On-site expenditure-Salaries of workersRs 50.00 lakh-
Payment of cessRs 50.00 lakh-
On-site expenditure-Site OverheadRs 25.25 lakh-
On-site expenditure-Consultants FeesRs 11.43 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAni Sambyal
EngineerManjunatha K K
Chartered AccountantA Subramanyam Reddy

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed103

As listed on the registration, under the names the promoter filed them with; the newest 80 of 103 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/051225/008313 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4_CA 4.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q3.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Arc Q3.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Q3.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
ADLR Survey SketchFile: ADLR Survey Sketch.pdf2 Dec 2025
Certified Village MAP with Proposed LandFile: Village Map with Proposed Site.pdf2 Dec 2025
BESCOM NOCFile: BESCOM NOC.pdf2 Dec 2025
WATER NOCFile: Water NOC.pdf2 Dec 2025
KSPCB NOCFile: KSPCB NOC.pdf2 Dec 2025
Explanation Letter for Reason for Delay Reg. & No Sales InvolvementFile: Reason for Delay Explanation.pdf2 Dec 2025
Land Cost Sheet with Guidance ValueFile: Land Cost Calc with Guidance Value.pdf2 Dec 2025
Form 6 Eng Certificate - Ongoing ProjectFile: Form 6.pdf2 Dec 2025
Certified STP Drawing by EngFile: Certified STP Drawing.pdf2 Dec 2025
Certified Estimated Construction cost by EngFile: Certified Construction Estimation Sheet.pdf2 Dec 2025
Proforma Agreement for SaleFile: Proforma Sale Agreement.pdf2 Dec 2025
Project SpecificationsFile: Project Specs.pdf2 Dec 2025
Building LicenseFile: Building License.pdf2 Dec 2025
Proposed Land in Master PlanFile: Master Plan.pdf2 Dec 2025
Commencement CertificateFile: Commencement Letter.pdf2 Dec 2025
RTC, survey 13-
Mutation, survey 13-
Encumbrance Certificate, survey 13-
Conversion/Alienation Order, survey 13-
JDA, survey 13-
Khatha, survey 13-
RTC, survey 12/1, 12/2, 12/3 & 12/4-
Mutation, survey 12/1, 12/2, 12/3 & 12/4-
Encumbrance Certificate, survey 12/1, 12/2, 12/3 & 12/4-
JDA, survey 12/1, 12/2, 12/3 & 12/4-
Khatha, survey 12/1, 12/2, 12/3 & 12/4-
Registration CertificateFile: Form C.pdf-
GST CertificateFile: GST Certificate.pdf-
Partnership DeedFile: Final Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA Reg 1.pdf-
Certificate issued by Architect Form 2File: Arc Reg 2.pdf-
Certificate issued by Engineer Form 3File: Eng Reg 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Balance Sheet 2024 - 2025File: BS.pdf-
Balance Sheet 2023 - 2024File: BS.pdf-
Balance Sheet 2022 - 2023File: BS.pdf-
Audited Profit and Loss Statement 2024 - 2025File: P&L.pdf-
Audited Profit and Loss Statement 2023 - 2024File: P&L.pdf-
Audited Profit and Loss Statement 2022 - 2023File: P&l.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR ACK.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR ACK.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR ACK.pdf-
Commencement Letter-
All pages 4 of 4-
All pages 4 of 4-
Stability Certificate-
Project Specs-
BLANK-
Reliquishment Deed-
BLANK-
Proforma Allotment Letter-
Form B-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep RAMYA WATER FRONT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: RAMYA ESTATES

RAMYA ESTATES has 1 registration on RERA Karnataka, including RAMYA WATER FRONT. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if RAMYA WATER FRONT is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of RAMYA WATER FRONT?

The registered promoter entity is RAMYA ESTATES, a partnership firm as per the filing. Its GSTIN 29ABAFR4070N1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in RAMYA WATER FRONT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RAMYA WATER FRONT?

The professionals named in the filing: Architect: Ani Sambyal; Engineer: Manjunatha K K; Chartered Accountant: A Subramanyam Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAMYA WATER FRONT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAMYA WATER FRONT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAMYA WATER FRONT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.