Home / Browse projects / Akola, Maharashtra / Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola

Registered No litigation declared Others project

Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola

By SUGAT WAGHMARE

RG-MH-47321 · RERA P50100031464 · Last updated on MahaRERA portal: 2 May 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Akola registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 42 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 25%
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola is a Others project by SUGAT WAGHMARE in Akola, Maharashtra, registered with MahaRERA as P50100031464 on 23 Oct 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameRajgruh Magasvargiya Co-operative Housing Society Ltd. Akola
  • TypeOthers
  • Location
    • Ghod Dod Road
    • Aadarsh Colony
    • Akola (M Corp.)
    • Akola
    • 444004
  • Pincode444004
  • RERA no.P50100031464
  • ReraGenie IDRG-MH-47321

Builder

  • NameSUGAT WAGHMARE
  • Entity typeIndividual

Key dates

this monthRegisteredOct 2021First promiseJun 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rajgruh Magasvargiya Co-operative Housing Society Ltd AkolaNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 25%.

Rajgruh Magasvargiya Co-operative Housing Society Ltd Akola: 33% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor25%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered23

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,800 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Sugat WaghmareAkola (M Corp.)Akola
Rajgruha Magasvargiya Gruha ColonyAkola (M Corp.)Akola

Approvals and building plan

Permissible FSI3414.02
Proposed, not sanctioned2,327 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKedia Plot, Akola

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
SUGAT WAGHMARE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50100024106Jun 2024 → Dec 2027

Reason as filed by the promoterWhile making application for registration of project, I have erred estimating the time for completion of the project. Also, due to some technical & other problems the work on site was stopped. I have not accepted any booking in the project till the date.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q4.pdf2 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q4.pdf2 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q4.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: Inventory 31-03-2025.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q2.pdf14 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q3.pdf14 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q2.pdf14 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q3.pdf14 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q2.pdf14 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q3.pdf14 Mar 2025
Disclosure of sold/ booked inventoryFile: Inventory 30-09-2024.pdf14 Mar 2025
Disclosure of sold/ booked inventoryFile: Inventory 31-12-2024.pdf14 Mar 2025
Details of encumbrances concerned to FinanceFile: No Encumbrance - Legal.pdf24 Jun 2024
Details of encumbrances concerned to LegalFile: No Encumbrance - Legal.pdf24 Jun 2024
Declaration in FORM BFile: Form B.pdf24 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: New Form 2A - 2023.pdf24 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: New Form 2A - 2024.pdf24 Jun 2024
CERSAI detailsFile: Cersai Declaration.pdf24 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf24 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf24 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf24 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-22.pdf24 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-23.pdf24 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-24.pdf24 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf24 Jun 2024
Deviation Report with respect to Allotment letterFile: No Deviation - Allotment Letter.pdf24 Jun 2024
Deviation Report with respect to model copy of AgreementFile: No Deviation - Agreement for sale.pdf24 Jun 2024
Other - TechnicalFile: Application For Extension.pdf24 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate rajgruha.pdf4 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate rajgruha.pdf4 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certifocate rajgruha.pdf4 May 2023
OtherFile: Clarification from Architect regards Area of Plot.pdf11 Oct 2021
Details of encumbrancesFile: No Encumbrance Certificate_Sugat Waghmare.pdf4 Oct 2021
Declaration about Commencement CertificateFile: FORM D_Declaration of Commencement Certificate.pdf4 Oct 2021
Declaration in FORM BFile: Form B Clarfication_Sugat Waghmare.pdf4 Oct 2021
Layout approvalFile: Layout map rajgruh (.pdf21 Sep 2021
Copy of the legal title reportFile: legal.pdf21 Sep 2021
Copy of Layout Approval (in case of layout)File: Layout map rajgruh (.pdf21 Sep 2021
Building plan approvalFile: rajgruh layout-R.pdf20 Sep 2021
Copy of the legal title reportFile: legal title report.pdf20 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: rajgruh layout-R.pdf20 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf20 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(Architect Certificate)_compressed.pdf2 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EngineerCertificate_compressed.pdf2 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA_compressed.pdf2 Sep 2021
PAN CardFile: PAN_Sugat Waghmare.pdf1 Sep 2021
Declaration in FORM BFile: From B Sugat Waghmare_compressed.pdf1 Sep 2021
Proforma of Allotment letterFile: Superb_Agreement for Sale.pdf1 Sep 2021

How this compares with Akola

10%of Akola projects moved their completion datethis one moved by 42 months
33%of Akola registrations have lapsed or been cancelledthis one is on the register

Computed across the 120+ Akola projects on ReraGenie, from their own filings.

Keep Rajgruh Magasvargiya Co-operative Housing So on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Aadarsh Colony120+ in Akola

Builder: SUGAT WAGHMARE

SUGAT WAGHMARE has 1 registration on MahaRERA, including Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Akola district page.

Frequently asked questions

What are my rights if Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?

The registered promoter entity is SUGAT WAGHMARE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rajgruh Magasvargiya Co-operative Housing So to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.