Home / Browse projects / Akola, Maharashtra / Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola
Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola
RG-MH-47321 · RERA P50100031464 · Last updated on MahaRERA portal: 2 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 42 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Akola registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola is a Others project by SUGAT WAGHMARE in Akola, Maharashtra, registered with MahaRERA as P50100031464 on 23 Oct 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 42 months from the original filing.
At a glance
Project
- NameRajgruh Magasvargiya Co-operative Housing Society Ltd. Akola
- TypeOthers
- Location
- Ghod Dod Road
- Aadarsh Colony
- Akola (M Corp.)
- Akola
- 444004
- Pincode444004
- RERA no.P50100031464
- ReraGenie IDRG-MH-47321
Builder
- NameSUGAT WAGHMARE
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Oct 2021
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed50 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Rajgruh Magasvargiya Co-operative Housing Society Ltd Akola | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 25%.
Rajgruh Magasvargiya Co-operative Housing Society Ltd Akola: 33% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 25% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 2 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed23
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Sugat Waghmare | Akola (M Corp.) | Akola |
| Rajgruha Magasvargiya Gruha Colony | Akola (M Corp.) | Akola |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| SUGAT WAGHMARE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWhile making application for registration of project, I have erred estimating the time for completion of the project. Also, due to some technical & other problems the work on site was stopped. I have not accepted any booking in the project till the date.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Sep 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Sep 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed50
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q4.pdf | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q4.pdf | 2 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q4.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory 31-03-2025.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q2.pdf | 14 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q3.pdf | 14 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q2.pdf | 14 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q3.pdf | 14 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q2.pdf | 14 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q3.pdf | 14 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory 30-09-2024.pdf | 14 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory 31-12-2024.pdf | 14 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance - Legal.pdf | 24 Jun 2024 |
| Details of encumbrances concerned to LegalFile: No Encumbrance - Legal.pdf | 24 Jun 2024 |
| Declaration in FORM BFile: Form B.pdf | 24 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 24 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 24 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: New Form 2A - 2023.pdf | 24 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: New Form 2A - 2024.pdf | 24 Jun 2024 |
| CERSAI detailsFile: Cersai Declaration.pdf | 24 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf | 24 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 24 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf | 24 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-22.pdf | 24 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-23.pdf | 24 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-24.pdf | 24 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf | 24 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: No Deviation - Allotment Letter.pdf | 24 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: No Deviation - Agreement for sale.pdf | 24 Jun 2024 |
| Other - TechnicalFile: Application For Extension.pdf | 24 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate rajgruha.pdf | 4 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate rajgruha.pdf | 4 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certifocate rajgruha.pdf | 4 May 2023 |
| OtherFile: Clarification from Architect regards Area of Plot.pdf | 11 Oct 2021 |
| Details of encumbrancesFile: No Encumbrance Certificate_Sugat Waghmare.pdf | 4 Oct 2021 |
| Declaration about Commencement CertificateFile: FORM D_Declaration of Commencement Certificate.pdf | 4 Oct 2021 |
| Declaration in FORM BFile: Form B Clarfication_Sugat Waghmare.pdf | 4 Oct 2021 |
| Layout approvalFile: Layout map rajgruh (.pdf | 21 Sep 2021 |
| Copy of the legal title reportFile: legal.pdf | 21 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: Layout map rajgruh (.pdf | 21 Sep 2021 |
| Building plan approvalFile: rajgruh layout-R.pdf | 20 Sep 2021 |
| Copy of the legal title reportFile: legal title report.pdf | 20 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: rajgruh layout-R.pdf | 20 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 20 Sep 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(Architect Certificate)_compressed.pdf | 2 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EngineerCertificate_compressed.pdf | 2 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA_compressed.pdf | 2 Sep 2021 |
| PAN CardFile: PAN_Sugat Waghmare.pdf | 1 Sep 2021 |
| Declaration in FORM BFile: From B Sugat Waghmare_compressed.pdf | 1 Sep 2021 |
| Proforma of Allotment letterFile: Superb_Agreement for Sale.pdf | 1 Sep 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Akola
Computed across the 120+ Akola projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 50 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Rajgruh Magasvargiya Co-operative Housing So on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Aadarsh Colony120+ in Akola
Heritage Home
RAM SANJEEVANI BUILDCON
Rama Residency
Rudra Construction
Pinnacle Heights
Sambhav Developers
Chaitra Keshav
Chaitra Santosh Hudlikar
GALAXY APPARTMENT
Kishor Mukundlal Agrawal
LANDMARK
RAJESHWAR BUILDERS AND DEVELOPERS
See every Akola project, with the district possession charts
Builder: SUGAT WAGHMARE
SUGAT WAGHMARE has 1 registration on MahaRERA, including Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Akola district page.
Frequently asked questions
What are my rights if Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?
The registered promoter entity is SUGAT WAGHMARE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in Rajgruh Magasvargiya Co-operative Housing Society Ltd. Akola?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback