Home / Browse projects / Bengaluru Urban, Karnataka / RAJA WOODS PARKK
RAJA WOODS PARKK
RG-KA-62631 · RERA PRM/KA/RERA/1251/310/PR/171031/001262
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
RAJA WOODS PARKK is a Residential/Group Housing project by RAJA HOUSING LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171031/001262 on 31 Oct 2017. Possession is promised by 30 Aug 2022. The completion date has moved by 21 months from the original filing.
At a glance
Project
- NameRAJA WOODS PARKK
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/171031/001262
- ReraGenie IDRG-KA-62631
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on31 Oct 2017
- Promised completion30 Aug 2022
- Revised completionRevised to 30 Aug 2022 (originally 30 Nov 2020)
- Buildings1 building record
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block A & B | - | - | - | 43 | 0 | 43 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | Not applicable |
| Joinery: Doors, Windows, Ventilators etc | Not applicable |
| Basic work of Water supply, Sanitary and Electrification | Not applicable |
| Dadoing, Skirting, Flooring, Tiles work (All types) | Not applicable |
| Railing and Grill fixing | Not applicable |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | No | Not applicable |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr. JAGALUR.F.F |
| Engineer | Mr. H J RADHAKRISHNA SETTY |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterAwaiting OC
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed68
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171031/001262 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: RHL Reg Certificate.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Certificate under Process.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Certificate under Process.pdf | - |
| CA Certificate for Funds UtilizationFile: Certificate under Process.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Certificate under Process.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Certificate under Process.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Certificate under Process.pdf | - |
| AffidavitFile: Certificate under Process.pdf | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Consent letter from 2/3rd of AllotteesFile: Consent Letter under Process.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| RWP - CC | - |
| RWP - Site plan & front elevation | - |
| RWP - Site plan & front elevation | - |
| RWP - Sale Deed Format | - |
| RWP - Ex for Sale Agreement | - |
| RWP - Land Docs and Location | - |
| RWP - Site plan & front elevation | - |
| RWP - Ground floor Sanction plan | - |
| RWP - Allotment Letter Format | - |
| RWP - Project Brochure | - |
| RWP - Specification & Carpet Area Statement | - |
| RWP - EC | - |
| Khata Certificate & Extract and RTC | - |
| Letter of Possession | - |
| Title Deeds Raja Woods Parkk | - |
| Conversion Orders | - |
| Conversion Orders | - |
| Ex for Noc Utilization Certificate | - |
| Ex for TDR Certificate | - |
| Ex for Relinquishment Deed | - |
| Ex for Noc Fire Force Department | - |
| Ex for Noc Airport Authority of India | - |
| Ex for Noc Bescom | - |
| Ex for Noc BWSSB | - |
| Ex for Noc KSPCB | - |
| Ex for Noc SEIAA | - |
| Ex for Noc BSNL | - |
| Ex for Noc for Building abbuting | - |
| Unnamed document | - |
| Ex for Noc Urban Land Ceiling | - |
| Ex for Noc BMRCL | - |
| Ex for Noc of Bang Urban Arts Commission | - |
| Ex for Noc of Inspector of Factories | - |
| Ex for Noc District Magistrate | - |
| Ex for Noc Coastal Reg Zone Authority | - |
| Ex for Cert from Reg Eng for Struct Safety | - |
| Site plan & front elevation | - |
| Legal Opinion | - |
| Balance Sheet 2015 - 2016File: Balance Sheet 2015-16.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet 2014-15.pdf | - |
| Balance Sheet 2013 - 2014File: Balance Sheet 2013-14.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Audited Profit and Loss statement 2015-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Audited Profit and Loss Statement 2014-15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: Audited Profit and Loss Statement 2013-14.pdf | - |
| Director's Report 2013 - 2014File: Directors Report 2013-14.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow Statement 2015-16.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash Flow Statement 2014-15.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor's Report 2015-16.pdf | - |
| Auditor's Report 2014 - 2015File: Auditors Report 2014-15.pdf | - |
| Auditor's Report 2013 - 2014File: Auditor's Report 2013-14.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR Acknw 2015-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR Acknw 2014-15.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR Acknw 2013-14.pdf | - |
| RWP - Declaration | - |
| Prospectus/BrochureFile: Raja Woods Parkk Presentation_compressed.pdf | - |
| Advertisement Copy 1File: Woods Parkk_Full Page Advt.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_171031_001262.xlsx | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| RAJA ARISTOS | - | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep RAJA WOODS PARKK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: RAJA HOUSING LIMITED
RAJA HOUSING LIMITED has 6 registrations on RERA Karnataka, including Raja Magnum and RAJA WOODS PARKK. Its filings declare 9 earlier projects, 8 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if RAJA WOODS PARKK is delayed beyond 30 Aug 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of RAJA WOODS PARKK?
The registered promoter entity is RAJA HOUSING LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in RAJA WOODS PARKK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at RAJA WOODS PARKK?
The professionals named in the filing: Architect: Mr. JAGALUR.F.F; Engineer: Mr. H J RADHAKRISHNA SETTY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAJA WOODS PARKK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.