Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Dec 2028Possession promisedmoved 48 months from the original
12 of 18Construction stages donefurthest along: Electrification, 75%
128 of 225Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 73 documents Report an error

RADIANT KAIRA is a Residential/Group Housing project by Radiant Kaira in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/210416/004130 on 16 Apr 2021. Possession is promised by 31 Dec 2028. The completion date has moved by 48 months from the original filing. 97 of the 225 units on this registration are recorded sold or booked, and 12 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRADIANT KAIRA
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/210416/004130
  • ReraGenie IDRG-KA-13292

Builder

  • NameRadiant Kaira
  • Entity typePartnership Firm
  • Authorized SignatorySATHYA SHEKAR PITTA
  • Board MembersD RAMAKRISHNA, P SRINIVAS, P VIJAY KUMAR, DODDI JYOTHI

Key dates

this monthRegisteredApr 2021First promiseDec 2024Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Apr 2021
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed73 files

Current status

43%97 of 225 units booked
6.7%Of the estimated cost spent so far

Figures as on 28 Mar 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A Block---1440144
B Block---81081

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 18 construction stages are filed complete. The stage furthest along is Electrification, at 75%.

Building: 86% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing75%
Wardrobe, Showcase, Kitchen cabinet, Puja work65%
Fire prevention and fire fighting fitting and fixture with network60%
Weather Proof work(tile,concrete)Not applicable
Painting55%
Elevation work50%
Internal and External work including landscapes as per santioned drawings50%

Progress on shared amenities41

As on 28 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes65%
Internal Roads & FootpathsYes60%
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes65%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes60%
Club HouseYes50%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes50%
Swimming PoolYes50%
GymYes45%
ParksNoNot applicable
Power BackupYes45%
GasYes40%
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes70%
LiftsYes65%
Staircases and Lift lobbies, corridor,lobbies, corridorYes60%
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes55%
BasementYes55%
TerraceYes50%
Outer WallYes50%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,004 sq m
Named landowners5
LandownerVillageDistrict
P VIJAY KUMAR--
DODDI JYOTHI--
P SRINIVAS--
D RAMAKRISHNA--
P SATHYASHEKAR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 50.00 cr
Cost incurredRs 3.35 cr
Spent of the estimate6.7%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 45.00 crRs 1.61 cr
On-site expenditure-Site OverheadRs 3.50 crRs 20.00 lakh
On-site expenditure-Consultants FeesRs 1.50 crRs 1.54 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTV srinivas
EngineerG Mohan Reddy

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/308/PR/241205/004130Dec 2024 → Dec 2025

Reason as filed by the promoterForce Majeure

ExtensionDec 2025 → Dec 2028

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00094/2026-Radiant Kaira07/02/2026

Documents filed73

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/210416/004130 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_compressed.pdf28 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form5 .pdf28 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form6 Radiant Kiara .pdf28 Mar 2026
Q3 2025-26 KPTCL- BESCOM28 Mar 2026
Sale deeds six in numberFile: 2 Six sale deeds.pdf24 Mar 2021
Clarification about JDA and Joint Declaration AffidavitFile: 3 Clarification about all queries.pdf24 Mar 2021
Form- B AffidavitFile: 4 Form-B Affidavit.pdf24 Mar 2021
Upto date Encumbrance CertificateFile: 5 Kaira EC 01-04-2004 to 17-03-2021.PDF24 Mar 2021
Conversion OrderFile: 6 Conversion Order.PDF24 Mar 2021
partnership Deed with Registration CertificateFile: 7 Partnership Deed with Registration Certificate.pdf24 Mar 2021
Building LicenseFile: 8 Building License.pdf24 Mar 2021
All floor plansFile: 9 All floor plans.pdf24 Mar 2021
Sec 3(1) non-violation AffidavitFile: 10 Sec 3(1) non-violation Affidavit.pdf24 Mar 2021
SpecificationFile: 11Specifications - Kaira.pdf24 Mar 2021
khathaFile: Khata.pdf24 Mar 2021
CertificateFile: Firm Registration Certificate.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Form Ex2 Architect Work Pending.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5 Radiant kiara.pdf-
CA Certificate for Funds UtilizationFile: Form Ex3 Funds Utilized.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form Ex1 Architect Work Pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form Ex6 Radiant kiara.pdf-
CA Certificate for Funds required for Project CompletionFile: Form Ex4 Funds Required.pdf-
AffidavitFile: Form-Ex7.pdf-
Latest Encumbrance CertificateFile: ECC-upto Date.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Kaira Plan Licence -CC-489-2019-2020-
Site Plan-
Site Plan-
Absolute Sale Deed Kaira-
Section AA-
Kaira Building Licence-
specifications-
specifications-
Kaira-EC1-
Decleration cum Affidavit-
Kaira Final Khata-
Unnamed document-
KLR 77A Kaira-
PTCL Kaira-
Unnamed document-
Unnamed document-
Unnamed document-
FIRE-
AIRPORT-
BESCOM NOC-
Unnamed document-
signedpdfnew (1)-
SEIAA-
BSNL NOC--
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Site Plan-
Section AA-
Unnamed document-
Balance Sheet 2019 - 2020File: Balence sheet.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P & L account.pdf-
Director's Report 2019 - 2020File: PSS_ITR 19-20.pdf-
Cash Flow Statement 2019 - 2020File: cash flow statement.pdf-
Auditor's Report 2019 - 2020File: Audit Report.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR ack.pdf-
Affidavit-
Prospectus/BrochureFile: E-Brochure_Amenities.pdf-
Advertisement Copy 1File: Advertisement.pdf-
Tower Excel SheetFile: PRMKARERA1251308PR210416004130.xlsx-

How this compares with Bengaluru Urban

43%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 48 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep RADIANT KAIRA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Radiant Kaira

Radiant Kaira has 1 registration on RERA Karnataka, including RADIANT KAIRA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if RADIANT KAIRA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of RADIANT KAIRA?

The registered promoter entity is Radiant Kaira, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in RADIANT KAIRA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RADIANT KAIRA?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at RADIANT KAIRA?

The professionals named in the filing: Architect: TV srinivas; Engineer: G Mohan Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADIANT KAIRA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADIANT KAIRA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADIANT KAIRA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.