Home / Browse projects / Bengaluru Urban, Karnataka / RADHESHYAM KARNASREE BRINDAVAN
RADHESHYAM KARNASREE BRINDAVAN
RG-KA-64295 · RERA PRM/KA/RERA/1251/446/PR/230726/008834 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
RADHESHYAM KARNASREE BRINDAVAN is a Residential/Group Housing project by RADHESHYAM BUILDERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/230726/008834 on 23 Jul 2026. Possession is promised by 30 Dec 2028. 0 of the 232 units on this registration are recorded sold or booked, and 2 of 16 construction stages are filed complete.
At a glance
Project
- NameRADHESHYAM KARNASREE BRINDAVAN
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/230726/008834
- ReraGenie IDRG-KA-64295
Builder
- NameRADHESHYAM BUILDERS
- Entity typePartnership Firm
- GSTIN29ABHFR1599P1Z5
- Authorized SignatorySATHYANARYANA J
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on23 Jul 2026
- Promised completion30 Dec 2028
- Revised completionNone
- Buildings5 building records
- Documents filed123 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A BLOCK | - | - | - | 48 | 0 | 48 |
| Block B | - | - | - | 40 | 0 | 40 |
| C Block | - | - | - | 36 | 0 | 36 |
| D Block | - | - | - | 40 | 0 | 40 |
| E Block | - | - | - | 68 | 0 | 68 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 16 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 60%.
Building: 16% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 60% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | Yes | 0% |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| K MALAINI | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 66.87 cr | Rs 11.57 cr |
| all other adminstrative and marketing and Misc | Rs 8.02 cr | - |
| Confirmation Deed and Goodwill | Rs 2.49 cr | - |
| On-site expenditure-Consultants Fees | Rs 55.00 lakh | Rs 1.29 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SRINIVAS |
| Engineer | MANDHADI VENKAT RAMANA REDDY |
| Chartered Accountant | L KRISHNA MOORTHY |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed123
As listed on the registration, under the names the promoter filed them with; the newest 80 of 123 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/230726/008834 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, CA Q2 sept 2025-26 (1).pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 -Q2 -Architect Certificate.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 -Q2 -Engineer Ceritificate.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Building License from Local Authority Request letterFile: RERA-Building License-Letter.pdf | 13 Jul 2026 |
| BDA LETTERFile: BDA license.pdf | 13 Jul 2026 |
| title deed of the current landowner 1File: SALE DEEDNo8298.pdf | 23 Jun 2026 |
| title deed of the current landowner 2File: SALE DEED DocNo14780.pdf | 23 Jun 2026 |
| title deed of the current landowner 3File: ABSOLUTE SALE DEED MALINI 1.pdf | 23 Jun 2026 |
| Sources of funds to complete the projectFile: RERAIT FilingRSB (1).pdf | 3 Jun 2026 |
| ITS STATMENTFile: StatementofIncomeABHFR1599P (1).pdf | 3 Jun 2026 |
| ITS STATMENTFile: RADHESHYAM BUILDERSITR V 2.pdf | 3 Jun 2026 |
| advocate search reportFile: RadheyshyamLegal Report (1).pdf | 3 Jun 2026 |
| title deed of the current landownerFile: ABSOLUTE SALE DEED MALINI (1).pdf | 3 Jun 2026 |
| Building License from Local Authority OriginalFile: ReraBuilding licenseRSB.pdf | 3 Jun 2026 |
| commencement certificateFile: BDA CC (1).pdf | 3 Jun 2026 |
| CDP MAPFile: CDP Horamavu 1_page-0001.jpg | 3 Jun 2026 |
| Village Map.File: Kithgannur Village Map.pdf | 3 Jun 2026 |
| uploaded SEIAA NOCFile: SEIAA 09 CON 2026.pdf | 3 Jun 2026 |
| BESCOM NOCFile: BESCOM NOC.pdf | 3 Jun 2026 |
| BESCOM NOCFile: Bescom-RSB.pdf | 3 Jun 2026 |
| structural engineer licenceFile: eNG lICE.pdf | 3 Jun 2026 |
| structural stability certificateFile: RSB-Stability Certificate-S n S Associates.pdf | 3 Jun 2026 |
| CA CERTIFICATEFile: CA Certificate V.pdf | 3 Jun 2026 |
| Allotment letterFile: allotment_page-0001.pdf | 3 Jun 2026 |
| Corrected ATSFile: Sale Agreemen.pdf | 3 Jun 2026 |
| sources of funds to complete the projectFile: RERA-IT Filing-RSB.pdf | 22 May 2026 |
| ITS STATMENTFile: RADHESHYAM BUILDERSITR V (2).pdf | 22 May 2026 |
| ITS STATMENTFile: StatementofIncomeABHFR1599P.pdf | 22 May 2026 |
| advocate search reportFile: RadheyshyamLegal Report.pdf | 22 May 2026 |
| title deed of the current landownerFile: ABSOLUTE SALE DEED MALINI.pdf | 22 May 2026 |
| Building License from Local Authority OriginalFile: Rera-Building license-RSB.pdf | 22 May 2026 |
| ommencement certificateFile: BDA CC.pdf | 22 May 2026 |
| CDP MAPFile: CDP Horamavu.pdf | 22 May 2026 |
| sources of funds to complete the projectFile: RADHESHYAM BUILDERS_ITR V.pdf | 6 May 2026 |
| ITS STATMENTFile: Statement_of_Income_ABHFR1599P.pdf | 6 May 2026 |
| title deed of the current landownerFile: ABSOLUTE SALE DEED MALINI.pdf | 6 May 2026 |
| advocate search report duly certified by the advocateFile: Radheyshyam_Legal Report.pdf | 6 May 2026 |
| proposed land in original Village map certified by the competent authorityFile: Kithgannur Village Map.pdf | 6 May 2026 |
| CDP MAPFile: CDP Horamavu.pdf | 6 May 2026 |
| commencement certificateFile: BDA CC.pdf | 6 May 2026 |
| Bank 100%, 70%, and 30% account pass sheetsFile: account details bank letter.pdf | 20 Feb 2026 |
| chartered accountant certificate (CA)File: CA Certificate V (1).pdf | 20 Feb 2026 |
| chartered accountant certificateFile: CA LICENSE V.pdf | 20 Feb 2026 |
| profit and loss account and balance sheetFile: Balance sheet as at 31st March , 2025.pdf | 20 Feb 2026 |
| profit and loss account and balance sheetFile: Statement_of_Income_ABHFR1599P.pdf | 20 Feb 2026 |
| profit and loss account and balance sheetFile: RADHESHYAM BUILDERS_ITR V.pdf | 20 Feb 2026 |
| Bank affidavitFile: BANK AFFUDAVIT.pdf | 20 Feb 2026 |
| title deed of the current landownerFile: ABSOLUTE SALE DEED MALINI.pdf | 20 Feb 2026 |
| JDA between land owner and promoterFile: Malini-JDA-Radheshyam Builders.pdf | 20 Feb 2026 |
| certificate of registration of partnership firmFile: Form C & Partnership firm-1.pdf | 20 Feb 2026 |
| notarized affidavit in form-BFile: FORM - B.pdf | 20 Feb 2026 |
| notarized JD cum Affidavit.File: JD AFFIDAVIT.pdf | 20 Feb 2026 |
| advocate search reportFile: LEGAL OPENION.pdf | 20 Feb 2026 |
| Defect free EC from 1-4-2011 to till dateFile: ECC 01-04-2004 to 17-11-2025.pdf | 20 Feb 2026 |
| Approved Original Single Plot layout planFile: Single Layout Plan.pdf | 20 Feb 2026 |
| Building LicenseFile: BDA license.pdf | 20 Feb 2026 |
| ADLR Certified survey sketchFile: ADLR survey sketch.pdf | 20 Feb 2026 |
| all original sanctioned drawingsFile: Sheet 01.pdf | 20 Feb 2026 |
| all original sanctioned drawingsFile: Sheet 02.pdf | 20 Feb 2026 |
| all original sanctioned drawingsFile: Sheet 03.pdf | 20 Feb 2026 |
| all original sanctioned drawingsFile: Sheet 04.pdf | 20 Feb 2026 |
| all original sanctioned drawingsFile: Sheet 05.pdf | 20 Feb 2026 |
| commencement certificateFile: BDA license.pdf | 20 Feb 2026 |
| Approved Master plan CertifiedFile: map Horamavu.pdf | 20 Feb 2026 |
| Approved Master plan CertifiedFile: map(b) Horamavu.pdf | 20 Feb 2026 |
| original Village map certifiedFile: Kithgannur Village Map.pdf | 20 Feb 2026 |
| cost details as per CA and Engineer CertificateFile: Estimation.pdf | 20 Feb 2026 |
| cost details as per CAFile: CA Certificate V (1).pdf | 20 Feb 2026 |
| original engineer certificateFile: fORM 03.pdf | 20 Feb 2026 |
| original engineer certificate fORM 06File: Form 06 Eng.pdf | 20 Feb 2026 |
| structural stability certificateFile: Stablity Certificate.pdf | 20 Feb 2026 |
| self attested structural engineer licenceFile: Eng ID.pdf | 20 Feb 2026 |
| project specificationsFile: Specfication.pdf | 20 Feb 2026 |
| Proforma of agreement (AFS) for saleFile: Sale Agreement.pdf | 20 Feb 2026 |
| Allotment letterFile: allotment.pdf | 20 Feb 2026 |
| Section 3(1) Notarized affidavitFile: NOTARIZED AFFIDAVIT.pdf | 20 Feb 2026 |
| BESCOM NOCFile: BESCOM NOC.pdf | 20 Feb 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep RADHESHYAM KARNASREE BRINDAVAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: RADHESHYAM BUILDERS
RADHESHYAM BUILDERS has 1 registration on RERA Karnataka, including RADHESHYAM KARNASREE BRINDAVAN. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if RADHESHYAM KARNASREE BRINDAVAN is delayed beyond 30 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of RADHESHYAM KARNASREE BRINDAVAN?
The registered promoter entity is RADHESHYAM BUILDERS, a partnership firm as per the filing. Its GSTIN 29ABHFR1599P1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in RADHESHYAM KARNASREE BRINDAVAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at RADHESHYAM KARNASREE BRINDAVAN?
The professionals named in the filing: Architect: SRINIVAS; Engineer: MANDHADI VENKAT RAMANA REDDY; Chartered Accountant: L KRISHNA MOORTHY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RADHESHYAM KARNASREE BRINDAVAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback