Home / Browse projects / Mumbai Suburban, Maharashtra / RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
By SSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH
RG-MH-08874 · RERA P51800007086 · Last updated on MahaRERA portal: 29 Sep 2023
Source: official MahaRERA filing
Red flags
- Registration revoked
- 36 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT is a Others project by SSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007086 on 17 Aug 2017. Possession is promised by 1 Dec 2028. 36 complaints are on record with the regulator.
At a glance
Project
- NameRABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
- TypeOthers
- Location
- MAHARASHTRA
- MUMBAI
- Kurla
- Mumbai Suburban
- 400083
- Pincode400083
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800007086
- ReraGenie IDRG-MH-08874
Builder
- NameSSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration revoked
- Registered on17 Aug 2017
- Promised completion1 Dec 2028
- Revised completionNone
- Buildings5 building records
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VIGHNAHAR COMPOSITE | NA | 19 | 0 | 0 | 0 | 0 |
| NAVBHARAT R/C OM SAI RAM R/C SAIDHAM R/C - SALE / REHAB COMPOSITE | NA | 33 | 0 | 0 | 0 | 0 |
| LA ESTRELLA RESIDENCY / COMMERCIAL | NA | 69 | 0 | 0 | 0 | 0 |
| SHRADDHA SABURI / OM SAI RAM / PAP / SAIDHAM - RESIDENTIAL / COMMERCIAL - SALE / REHAB COMPOSITE | NA | 29 | 0 | 0 | 0 | 0 |
| LARIENA RESIDENCY / COMMERCIAL | NA | 30 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 29 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 85%.
VIGHNAHAR COMPOSITE55%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
NAVBHARAT R/C OM SAI RAM R/C SAIDHAM R/C - SALE / REHAB COMPOSITE0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LA ESTRELLA RESIDENCY / COMMERCIAL0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHRADDHA SABURI / OM SAI RAM / PAP / SAIDHAM - RESIDENTIAL / COMMERCIAL - SALE / REHAB COMPOSITE0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LARIENA RESIDENCY / COMMERCIAL39%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 43% |
| Podiums (if any) | 43% |
| Plinth | 43% |
| Stilt Floor | 43% |
| Slabs of Super Structure | 43% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 43% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 43% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 15% |
Progress on shared amenities15
As on 29 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 75% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 30% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 20% |
| Energy managemcnt | Yes | 10% |
| Fire protection and fire safety requirements | Yes | 10% |
| Electrical meter room, sub-station, receiving station | Yes | 10% |
| Aggregate area of recreational Open Space | Yes | 10% |
| Open Parking | No | Not applicable |
Parking filed33
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| LA ESTRELLA RESIDENCY / COMMERCIAL | 32 | 32 |
| LARIENA RESIDENCY / COMMERCIAL | 1 | 1 |
Land and ownership7
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SSV Developers and Builders Pvt Ltd | Mumbai City | Mumbai City |
| HPA SPACES PVT LTD | Mumbai City | Mumbai City |
| LAXMI CORPORATION | Mumbai City | Mumbai City |
| JAGANNATH AND PRABHAKAR SONAWANE | Mumbai City | Mumbai City |
| SAIDHAM CHSL | Mumbai City | Mumbai City |
| VIGHNAHAR CHSL | Mumbai City | Mumbai City |
| OM SAI RAM CHSL | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Heman Parikh & Associates |
| Architect | Hafeez Contractor |
| Engineer | Mahimtura Consultants Pvt Ltd |
| Partner | Role in project |
|---|---|
| SSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH | - |
Litigation declared6
| Case | Court | Status |
|---|---|---|
| 100023/2022 | City Sessions Court Mumbai | Case disposed |
| 126/2016 | Sewree City Civil Court | Case disposed |
| 406/2020 | Vikroli court | Case disposed |
| 6445/2019 | Bombay Civil appellate jurisdiction | Case disposed |
| 9329/2022 | HIGH COURT OF JUDICATURE AT BOMBAY | ongoing |
| 6445/2019 | Bombay Civil appellate jurisdiction | ongoing |
Complaints filed with MahaRERA36
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012326 | Sagar Chavan | Hemant Vinaykant Parikh | 27/12/2017 |
| CC006000000054616 | MANI AWASTHI | SSV DEVELOPERS AND BUILDERS | 23/05/2018 |
| CC006000000089962 | Mani Awasthi | S.S.V. Developers and Builders | 04/07/2019 |
| CC006000000001283 | Mrs.Suman J.Nar | SSV Devloper & Builder | 14/10/2017 |
| CC006000000012623 | SSV DEVELOPERS AND BUILDERS ( MUMBAI) HEMANT V. PARIKH | SAI ESTATE CONSULTANT CHEMBUR PVT LTD | 30/12/2017 |
| CC006000000044169 | VIJAY SHIWA DHURI | S S V DEVELOPERS & BUILDERS (MUMBAI) | 19/04/2018 |
| CC006000000044423 | DALVI MOHD. SHARIF | Mr. Hemant Parekh | 09/05/2018 |
| CC006000000055149 | Narain Dass | Sai estate consultants chembur pvt. ltd. and S.S.V. Builders and Developers | 28/06/2018 |
| CC006000000078866 | Vijay Vishnu Kadam | S S V Developers and Builders | 12/04/2019 |
| CC006000000079159 | Rajesh Singh | Mr. Hemant Vinaykant Parikh | 05/05/2019 |
| CC006000000078971 | Anil Lawrence Quadras and Fatima Anil Quadras | SSV Developers and Builders | 20/04/2019 |
| CC006000000079463 | Nirmalya Banerjee | Hemant Parekh of SSV Developers & Builders | 26/05/2019 |
| CC006000000089984 | Shankar Madhukar Parkar | SSV Developers & Builders (Mumbai) | 04/07/2019 |
| CC006000000089997 | Navandu Tanaji Rane | SSV Developers and Builders Mumbai | 05/07/2019 |
| CC006000000090107 | Yeshwant Sadanand Gangan | SSV Builders and Developers (Mumbai) | 13/07/2019 |
| CC006000000090176 | Dipti Dattatray Khochare | SSV Developers & Builders (Mumbai) | 16/07/2019 |
| CC006000000100206 | Maharukh Darayus Hozdar | S.S.V. Builders and Developers (Mumbai) | 18/07/2019 |
| CC006000000100310 | KISHORE KUMAR CHIMANLAL KATARIYA | M/s. SSV BUILDERS & DEVELOPERS (MUMBAI) | 26/07/2019 |
| CC006000000100400 | Mihir M Mehta | S.S.V Developers & Builders | 03/08/2019 |
| CC006000000100474 | AKSHATA ANANT NAYAK | M/s. S.S.V. Builders & Developers (Mumbai) | 09/08/2019 |
| CC006000000100476 | RAJESH TIWARI | M/s. S.S.V. Builders & Developers (Mumbai) | 09/08/2019 |
| CC006000000100532 | SANDIP BABU JAITAPKAR | S.S.V DEVELOPERS AND BUILDERS | 15/08/2019 |
| CC006000000110701 | Jayashree Suresh Mhatre | M/s. S.S.V. Builders & Developers (Mumbai) | 26/08/2019 |
| CC006000000171507 | Milind Murlidhar Rane | M/s. S.S.V. Builders and Developers | 12/11/2019 |
| CC006000000171709 | NEERAV YOGESH SHAH | M/S S.S.V. DEVELOPERS & BUILDERS | 30/11/2019 |
| CC006000000192342 | LAREINA RESIDENCY FLAT OWNERS ASSOCIATION | SSV DEVELOPERS AND BUILDERS | 29/01/2020 |
| CC006000000194671 | Susheel Ratnakar Shetty | SSV Developers and Builders Mumbai | 25/10/2020 |
| CC006000000194672 | Meena Bharat Arote | SSV Developers and Builders Mumbai | 25/10/2020 |
| CC006000000194692 | CHARLES S. RAJ & Anr | S.S.V. Developers and Builders Mumbai | 27/10/2020 |
| CC006000000194693 | Hitesh Narayanji Bhanushali | S.S.V. Developers and Builders Mumbai | 27/10/2020 |
| CC006000000194716 | Pramod Balasaheb Nanavare | S.S.V. Developers and Builders Mumbai | 29/10/2020 |
| CC006000000194725 | HARSHAD UMESH BHOITE | S.S.V. DEVELOPERS AND BUILDERS MUMBAI | 30/10/2020 |
| CC006000000194837 | Shrikant Suryakant Koyande | SSV Developers and Builders Mumbai | 06/11/2020 |
| CC006000000251349 | Lareina Residency Flat Owners Association Lareina Residency Flat Owners Association | SSV Developers and Builders Mumbai Proprietor Hemant Vinayak Parikh | 02/06/2022 |
| CC006000000428711 | ARUN KHANDERAO DUSING | SSV DEVELOPERS AND BUILDERS | 04/01/2024 |
| CC12502493 | Sunanda Chintaman Ingale | SSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH | 21/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 1 Dec 2028
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrances concerned to FinanceFile: RECALL PETITION IN WP 6445 OF 2019 - SSV DEVELOPERS.pdf | 29 Sep 2023 |
| Details of encumbrances concerned to LegalFile: RECALL PETITION IN WP 6445 OF 2019 - SSV DEVELOPERS.pdf | 29 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: ordjud (7).pdf | 30 Mar 2023 |
| Details of encumbrances concerned to LegalFile: ordjud (7).pdf | 30 Mar 2023 |
| Certificates of CA (Form 3)File: FORM 3 ay 21 22.pdf | 29 Jan 2023 |
| Details of encumbrancesFile: form-3 encumberence AADPP2558B_Computation Sheet_1037639683(1)_09122021.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: form 3 ITR- FORM- HEMANT VINAYKANT PARIKH -2020.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: form-3 lareina Annexure 2 HPA - Revised Balance sheet.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: form-3 encumberence AADPP2558B_Computation Sheet_1037639683(1)_09122021.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: form3ack_itr3_compressed.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: form 3 lareina_compressed.pdf | 20 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 rera lareina FY 21-22.pdf | 9 Dec 2022 |
| Building plan approvalFile: lareina approval.pdf | 26 Mar 2022 |
| Building Plan Approval (IOD)File: lareina approval.pdf | 26 Mar 2022 |
| Layout approvalFile: Vighnahar___Sai_Dham_CHS_Ltd-Model.pdf | 17 Mar 2022 |
| Building plan approvalFile: Om sai Ram owner ship remarks_compressed.pdf | 17 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Vighnahar___Sai_Dham_CHS_Ltd-Model.pdf | 17 Mar 2022 |
| Building Plan Approval (IOD)File: Om sai Ram owner ship remarks_compressed.pdf | 17 Mar 2022 |
| Building plan approvalFile: lareina approval 1.pdf | 14 Mar 2022 |
| Building plan approvalFile: lareina approval 2.pdf | 14 Mar 2022 |
| Building Plan Approval (IOD)File: lareina approval 1.pdf | 14 Mar 2022 |
| Building Plan Approval (IOD)File: lareina approval 2.pdf | 14 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 annual report 20-21.pdf | 14 Mar 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: lareina soc formation.pdf | 24 Jan 2022 |
| OtherFile: form 6- Hemant Parikh.pdf | 19 Aug 2020 |
| Certificates of CA (Form 3)File: ITR V HEMANTA VINAYAK PARIKH.pdf | 25 May 2019 |
| OtherFile: lareina.pdf | 24 May 2019 |
| OtherFile: saidham.pdf | 24 May 2019 |
| Certificates of CA (Form 3)File: SSV 1.pdf | 17 May 2019 |
| Certificates of CA (Form 5)File: ANNUAL REPORT ON STATEMENT OF ACCOUNTS RAVINDRANATH.pdf | 17 May 2019 |
| OtherFile: AGRC doc.pdf | 10 Jan 2019 |
| OtherFile: SSVM- Saidham - Minutes of Decision.pdf | 19 May 2018 |
| OtherFile: LEGAL SAIDHAM SRA ACK.pdf | 30 Dec 2017 |
| Layout approvalFile: PRAPOSED LAYOUT PLAN.pdf | 15 Dec 2017 |
| Copy of Layout Approval (in case of layout)File: PRAPOSED LAYOUT PLAN.pdf | 15 Dec 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Attachment - Enginaring certificate - Lareina.pdf | 15 Dec 2017 |
| Certificates of CA (Form 3)File: Form 3 CA RERA - Format -LAREINA.pdf | 15 Dec 2017 |
| Certificates of CA (Form 3)File: Form 3 -CA - LAREINA.pdf | 15 Dec 2017 |
| OtherFile: PRINCIPAL OF SEC- SAIDHAM.pdf | 15 Dec 2017 |
| OtherFile: TERMINATION LTR - SAIDHAM STY - 1mb.pdf | 5 Dec 2017 |
| Details of encumbrancesFile: encumbrance.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: SSV.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: SSV 2.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 22 Attachement - Form- 1- original Lareina rsz.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 rsz.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: affidavid mumbai.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE-Lareina.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Attachment - allotment letter draft.pdf | 30 Jul 2017 |
| Layout approvalFile: LareinaApprovedPlan-PAGE-1.pdf | 17 Jul 2017 |
| Layout approvalFile: LareinaApprovedPlan-PAGE-2.pdf | 17 Jul 2017 |
| Layout approvalFile: LareinaApprovedPlan-PAGE-3.pdf | 17 Jul 2017 |
| Layout approvalFile: LareinaApprovedPlan-PAGE-4.pdf | 17 Jul 2017 |
| Layout approvalFile: LareinaApprovedPlan-PAGE-5.pdf | 17 Jul 2017 |
| Layout approvalFile: LareinaApprovedPlan-PAGE-6.pdf | 17 Jul 2017 |
| Building plan approvalFile: LERINA-IOA-253-254-255.pdf | 17 Jul 2017 |
| Building plan approvalFile: LERINA-IOA-256-257-258.pdf | 17 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LareinaApprovedPlan-PAGE-1.pdf | 17 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LareinaApprovedPlan-PAGE-2.pdf | 17 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LareinaApprovedPlan-PAGE-3.pdf | 17 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LareinaApprovedPlan-PAGE-4.pdf | 17 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LareinaApprovedPlan-PAGE-5.pdf | 17 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LareinaApprovedPlan-PAGE-6.pdf | 17 Jul 2017 |
| Building Plan Approval (IOD)File: LERINA-IOA-253-254-255.pdf | 17 Jul 2017 |
| Building Plan Approval (IOD)File: LERINA-IOA-256-257-258.pdf | 17 Jul 2017 |
| Copy of the legal title reportFile: LerinaTitleReport.pdf | 29 Jun 2017 |
| PAN CardFile: hp-pancard.pdf | 27 Jun 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: LareinaCC1.pdf | 27 Jun 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: LareinaCC2.pdf | 27 Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
Keep RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MUMBAI6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 151 registered projects within 2 km.
Cons 1221 MIG T/S and 100 Shops S. No. 113 (pt
Mumbai Housing And Area Development Board
Om Siddhivinayak CHS and Gurukrupa CHS
Shreeji Developers
AKASSH AMAZONIA TOWER 1
HEER MEHTA LANDMARK DEVELOPERS PRIVATE LIM
Ajmera Solis
Shree Yogi Realcon Private Limited
CENTRAL PARK
V LAXMI NURSES DEVELOPERS LLP
Swastik Platinum
SUVASYA BUILDERS AND DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH
SSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH has 1 registration on MahaRERA, including RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT shows as registration revoked on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT is delayed beyond 1 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT?
The registered promoter entity is SSV DEVELOPERS AND BUILDERS MUMBAI PROPRIETOR HEMANT VINAYKANT PARIKH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT?
The professionals named in the filing: Architect: Heman Parikh & Associates; Architect: Hafeez Contractor; Engineer: Mahimtura Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback