Home / Browse projects / Bengaluru Urban, Karnataka / PURVI ARVINDAM

Registration approved No litigation declared Residential/Group Housing project

PURVI ARVINDAM

By SAI PURVI INFRASTRUCTURES

RG-KA-31333 · RERA PRM/KA/RERA/1251/446/PR/200924/007055 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2027Possession promisedno revision filed
9 of 19Construction stages donefurthest along: Masonry Construction, 95%
42 of 76Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 115 documents Report an error

PURVI ARVINDAM is a Residential/Group Housing project by SAI PURVI INFRASTRUCTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200924/007055 on 20 Sep 2024. Possession is promised by 16 May 2027. 34 of the 76 units on this registration are recorded sold or booked, and 9 of 19 construction stages are filed complete.

At a glance

Project

  • NamePURVI ARVINDAM
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/200924/007055
  • ReraGenie IDRG-KA-31333

Builder

  • NameSAI PURVI INFRASTRUCTURES
  • Entity typePartnership Firm
  • GSTIN29AEKFS4470C1ZU
  • Authorized SignatoryP PRABHAKARNAIDU

Key dates

this monthRegisteredSep 2024PromisedMay 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Sep 2024
  • Promised completion16 May 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed115 files

Current status

45%34 of 76 units booked
93.8%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ARVINDAM---76076

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 19 construction stages are filed complete. The stage furthest along is Masonry Construction, at 95%.

Building: 84% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction95%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)85%
Railing and Grill fixing50%
Electrification, Water supply and Sanitary Finishing80%
Painting80%
Fire prevention and fire fighting fitting and fixture with network70%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings80%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes85%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes80%
Energy managementYes0%
Fire protection and fire safety requirementsYes80%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes80%
Internal Roads & FootpathsYes80%
Electricity supply transformer and substationYes50%
Storm water drainsYes80%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingYes10%
Street LightingYes40%
ElectricityYes85%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes85%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes90%
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes60%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes80%
Corridor/LobbiesYes80%
Fire escapesYes80%
Common entrance and exit for the building/common portico/foyer/verandahYes90%
BasementYes95%
TerraceYes95%
Outer WallYes95%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes90%
Water conservation and renewable energyYes30%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
SREYAS SAMSKRUTHI--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 54.76 cr
Cost incurredRs 51.35 cr
Spent of the estimate93.77%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 48.24 crRs 43.99 cr
Payment of taxesRs 3.60 crRs 2.19 cr
On-site expenditure-Site OverheadRs 2.27 crRs 2.11 cr
On-site expenditure-Consultants FeesRs 65.00 lakhRs 40.00 lakh
Payment of Premiums-Rs 2.66 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHANUMATHY G
EngineerARUN KUMAR S R
Chartered AccountantUDAYKUMAR.B.

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed115

As listed on the registration, under the names the promoter filed them with; the newest 80 of 115 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200924/007055 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA-SAI PURVI INFRASTRUCTURES-Q2 form 4.PDF13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: SAI PURVI-FORM-5_0001 (1) Architect Certificate.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: SAI PURVI-FORM-6_0001 (1) Engineer Letter.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA-Q1-SAI PURVI INFRASTRUCTURES Form 4.PDF14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: SAI PURVI-FORM-5 (QU1) 2026 27.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: SAI PURVI-FORM-6 ( Q1) 2026-27.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA-Q4-SAI PURVI INFRASTRUCTURES.PDF13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: SAI PURVI ARVINDAM-FORM-5_0001 31 Mar 2026.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: SAI PURVI ARVINDAM-FORM-6 31 mar 2026.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ca certificates Purvi Arvindam.PDF15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: SAI PURVI-FORM-5_0001.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: SAI PURVI-FORM-6_0001.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Airport Authority of India15 Jan 2026
CLARIFICATION ON QUIRYFile: Clarification reply.pdf20 Sep 2024
SOURCES OF FUNDFile: Source of funds.pdf20 Sep 2024
Respected Sir, as per the clarification asked we are providing with the balance sheet of partners.File: Krishna balance sheet 2023.pdf6 Sep 2024
Respected Sir, as per the clarification asked we are providing with the balance sheet of partners.File: prabhakar balancesheet 2023.pdf6 Sep 2024
Sources of fundFile: Sources of fund.pdf28 Aug 2024
BWSSB NOC WITH FEES DETAILSFile: BWSSB NOC sai purvi.pdf31 Jul 2024
LAND CALCULATION SHEET AS PER GUIDANCE VALUE CERTIFICATEFile: Guidance value certificate.pdf31 Jul 2024
HAL NOCFile: HAL NOC Sai Purvi Infrastructures.pdf31 Jul 2024
STP DRAWINGFile: SPIS 55KLD STP Plan and Elevation.pdf31 Jul 2024
STRUCTURAL SAFETY ADOPTED CERTIFICATEFile: STRUCTURAL SAFETY ADOPTED CERTIFICATE_0001_0001.pdf31 Jul 2024
CDP MAPFile: CDP MAP COM.pdf18 Jul 2024
VILLAGE MAPFile: VILLAGE MAP NEW.pdf18 Jul 2024
LEGAL OPINIONFile: Legal opinion.pdf27 Jun 2024
RTCFile: RTC.pdf27 Jun 2024
CDP MAPFile: CDP MAP COM.pdf27 Jun 2024
SINGLE PLAN LAYOUTFile: single plan layout purvi.pdf27 Jun 2024
SINGLE PLAN LAYOUT ORDERFile: single plan layout purvi.pdf27 Jun 2024
HAL NOCFile: HAL NOC.pdf27 Jun 2024
SECTION 3 VIOLATIONFile: Section 3 violation.pdf27 Jun 2024
RERA BANK ACCOUNT BUILDERS ACCOUNTFile: Builder account.jpg27 Jun 2024
RERA COLLECTION ACCOUNTFile: Collection account.pdf27 Jun 2024
RERA DESIGNATED BANK ACCOUNTFile: Rera designated account.pdf27 Jun 2024
KRISHNA FINANCIAL STATEMENT 2021File: Krishna financial staetment 2020 21.pdf27 Jun 2024
KRISHNA FINANCIAL STATEMENT 2022File: Krishna financial statement 2021 22.pdf27 Jun 2024
KRISHNA FINANCIAL STATEMENT 2023File: Krishna financial statement 2022 23.pdf27 Jun 2024
PRABHAKAR FINANCIAL STATEMENT 2021File: Prabhakar financial statement 2020 21.pdf27 Jun 2024
PRABHAKAR FINANCIAL STATEMENT 2022File: Prabhakar financial statement 2021 22.pdf27 Jun 2024
PRABHAKAR FINANCIAL STATEMENT 2023File: Prabhakar financial statement 2022 23.pdf27 Jun 2024
BWSSB NOCFile: water NOC.pdf27 Jun 2024
MOTHER DEEDFile: mother deed purvika.pdf27 Jun 2024
FORM B AFFIDAVITFile: Form B affidavit.pdf27 Jun 2024
AREA DETAILS AND CARPET AREA CALCULATIONFile: Area details and carpet details.pdf27 Jun 2024
AREA DETAILSFile: Area details.pdf27 Jun 2024
AMENITIES AND PROJECT SPCIFICATIONFile: Amenities and specification.pdf27 Jun 2024
VFILLAGE MAPFile: VILLAGE MAP.pdf27 Jun 2024
MODEL FORM OF ALLOTMENT LETTERFile: MODEL FORM OF ALLOTMENT LETTER.pdf27 Jun 2024
PROFORMA OF AGREEMENT OF SALEFile: Agreement of Sale Proforma final.pdf27 Jun 2024
SOURCES OF FUNDFile: Sources of fund.pdf27 Jun 2024
LAND CALCULATION SHEET AS PER GUIDANCE VALUEFile: Land calculation as per guidance value.pdf27 Jun 2024
FORM-6 ENGINEER CERTIFICATEFile: Form -6.pdf27 Jun 2024
EC FROM 2008 TILL DATEFile: ECC 1.pdf27 Jun 2024
BREIEF ESTIMATED COST CERTIFIED BY ENGINEERFile: Brief estimated cost.pdf27 Jun 2024
STP DRAWINGFile: STP.png27 Jun 2024
RTC, survey 11/3-
Mutation, survey 11/3-
Encumbrance Certificate, survey 11/3-
Conversion/Alienation Order, survey 11/3-
JDA, survey 11/3-

How this compares with Bengaluru Urban

45%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep PURVI ARVINDAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SAI PURVI INFRASTRUCTURES

SAI PURVI INFRASTRUCTURES has 1 registration on RERA Karnataka, including PURVI ARVINDAM. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if PURVI ARVINDAM is delayed beyond 16 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PURVI ARVINDAM?

The registered promoter entity is SAI PURVI INFRASTRUCTURES, a partnership firm as per the filing. Its GSTIN 29AEKFS4470C1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PURVI ARVINDAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PURVI ARVINDAM?

The professionals named in the filing: Architect: BHANUMATHY G; Engineer: ARUN KUMAR S R; Chartered Accountant: UDAYKUMAR.B.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PURVI ARVINDAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PURVI ARVINDAM. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PURVI ARVINDAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.