Registration approved Commercial project

Purva Zentech Business Park

By Purva Ruby Properties Limited

RG-KA-78408 · RERA PRM/KA/RERA/1251/310/PR/190219/002422

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2023Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 52 documents Report an error

Purva Zentech Business Park is a Commercial project by Purva Ruby Properties Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190219/002422 on 19 Feb 2019. Possession is promised by 31 Dec 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NamePurva Zentech Business Park
  • TypeCommercial
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/190219/002422
  • ReraGenie IDRG-KA-78408

Builder

  • NamePurva Ruby Properties Limited
  • Entity typeCompany
  • Authorized SignatoryNani R Choksey

Key dates

this monthRegisteredFeb 2019First promiseMar 2023Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Feb 2019
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Mar 2023)
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building---01010

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing workNot applicable
Retaining wall (All types)Not applicable
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,126 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 324.64 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2023 → Dec 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed52

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190219/002422 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Ruby Certificate of Incorporation.pdf-
Declaration 2-
Site Plan-
Site_Floors-
Allotment Letter (Zentech Park)-
Allotment Letter (Zentech Park)-
Sale Deeds_RTC-
Section_1-
Site Plan-
Allotment Letter (Zentech Park)-
Declaration 2-
Declaration 2-
RERA_Zentech EC-
3_1 Affidavit and CA Cert-
Khata_Assessment-
JDA and POA-
Fee Demand-
Conversion OM_All-
Deed of Relinquishment-
Fire NOC 061016-
AAI NOC-
BESCOM NOC 270616-
SEIAA 280317-
SEIAA 280317-
BSNL NOC 300816-
BMRCL NOC 080716-
Section_1-
Site Plan-
Site Plan-
Tax Receipt (2017-18)-
RERA_Title Certificate-
Balance Sheet 2017 - 2018File: 18 Bal Sheet.pdf-
Balance Sheet 2016 - 2017File: 17 Bal Sheet.pdf-
Balance Sheet 2015 - 2016File: 2016 Bal Sheet.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 18 PandL.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 17 PandL.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 2016 PandL.pdf-
Director's Report 2017 - 2018File: 18 Directors Report.pdf-
Director's Report 2016 - 2017File: 17 Directors Report.pdf-
Director's Report 2015 - 2016File: 16 Directors Report.pdf-
Cash Flow Statement 2017 - 2018File: 18 Cash Flow.pdf-
Cash Flow Statement 2016 - 2017File: 17 Cash Flow.pdf-
Auditor's Report 2017 - 2018File: 18 Auditors Report.pdf-
Auditor's Report 2016 - 2017File: 17 Auditors Report.pdf-
Auditor's Report 2015 - 2016File: 2016 Auditors Report.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: PRPL - ITR V - Mar-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: PRPL - ITR V - Mar-17.PDF-
Income Tax Return Acknowledgement 2015 - 2016File: PRPL ITR - 2015-16.pdf-
Affidavit-
Prospectus/BrochureFile: Zentech Declaration.pdf-
Advertisement Copy 1File: Zentech Declaration.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_190219_002422.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Purva Zentech Business Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPurva Zentech Business POther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: Purva Ruby Properties Limited

Purva Ruby Properties Limited has 1 registration on RERA Karnataka, including Purva Zentech Business Park. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Purva Zentech Business Park is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Purva Zentech Business Park?

The registered promoter entity is Purva Ruby Properties Limited, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Purva Zentech Business Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Purva Zentech Business Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Purva Zentech Business Park. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Purva Zentech Business Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.