Home / Browse projects / Bengaluru Urban, Karnataka / Purva Zentech Business Park
Purva Zentech Business Park
By Purva Ruby Properties Limited
RG-KA-78408 · RERA PRM/KA/RERA/1251/310/PR/190219/002422
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Purva Zentech Business Park is a Commercial project by Purva Ruby Properties Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190219/002422 on 19 Feb 2019. Possession is promised by 31 Dec 2023. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NamePurva Zentech Business Park
- TypeCommercial
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/190219/002422
- ReraGenie IDRG-KA-78408
Builder
- NamePurva Ruby Properties Limited
- Entity typeCompany
- Authorized SignatoryNani R Choksey
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Feb 2019
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 31 Mar 2023)
- Buildings1 building record
- Documents filed52 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building | - | - | - | 0 | 10 | 10 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | Not applicable |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | Not applicable |
| Plastering inside , outside & Ceiling | Not applicable |
| Joinery: Doors, Windows, Ventilators etc | Not applicable |
| Basic work of Water supply, Sanitary and Electrification | Not applicable |
| Dadoing, Skirting, Flooring, Tiles work (All types) | Not applicable |
| Railing and Grill fixing | Not applicable |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | No | Not applicable |
| Staircases and Lift lobbies, corridor,lobbies, corridor | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | No | Not applicable |
| Outer Wall | No | Not applicable |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed52
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190219/002422 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Ruby Certificate of Incorporation.pdf | - |
| Declaration 2 | - |
| Site Plan | - |
| Site_Floors | - |
| Allotment Letter (Zentech Park) | - |
| Allotment Letter (Zentech Park) | - |
| Sale Deeds_RTC | - |
| Section_1 | - |
| Site Plan | - |
| Allotment Letter (Zentech Park) | - |
| Declaration 2 | - |
| Declaration 2 | - |
| RERA_Zentech EC | - |
| 3_1 Affidavit and CA Cert | - |
| Khata_Assessment | - |
| JDA and POA | - |
| Fee Demand | - |
| Conversion OM_All | - |
| Deed of Relinquishment | - |
| Fire NOC 061016 | - |
| AAI NOC | - |
| BESCOM NOC 270616 | - |
| SEIAA 280317 | - |
| SEIAA 280317 | - |
| BSNL NOC 300816 | - |
| BMRCL NOC 080716 | - |
| Section_1 | - |
| Site Plan | - |
| Site Plan | - |
| Tax Receipt (2017-18) | - |
| RERA_Title Certificate | - |
| Balance Sheet 2017 - 2018File: 18 Bal Sheet.pdf | - |
| Balance Sheet 2016 - 2017File: 17 Bal Sheet.pdf | - |
| Balance Sheet 2015 - 2016File: 2016 Bal Sheet.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: 18 PandL.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: 17 PandL.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 2016 PandL.pdf | - |
| Director's Report 2017 - 2018File: 18 Directors Report.pdf | - |
| Director's Report 2016 - 2017File: 17 Directors Report.pdf | - |
| Director's Report 2015 - 2016File: 16 Directors Report.pdf | - |
| Cash Flow Statement 2017 - 2018File: 18 Cash Flow.pdf | - |
| Cash Flow Statement 2016 - 2017File: 17 Cash Flow.pdf | - |
| Auditor's Report 2017 - 2018File: 18 Auditors Report.pdf | - |
| Auditor's Report 2016 - 2017File: 17 Auditors Report.pdf | - |
| Auditor's Report 2015 - 2016File: 2016 Auditors Report.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: PRPL - ITR V - Mar-18.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: PRPL - ITR V - Mar-17.PDF | - |
| Income Tax Return Acknowledgement 2015 - 2016File: PRPL ITR - 2015-16.pdf | - |
| Affidavit | - |
| Prospectus/BrochureFile: Zentech Declaration.pdf | - |
| Advertisement Copy 1File: Zentech Declaration.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_190219_002422.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Purva Zentech Business Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Purva Ruby Properties Limited
Purva Ruby Properties Limited has 1 registration on RERA Karnataka, including Purva Zentech Business Park. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Purva Zentech Business Park is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Purva Zentech Business Park?
The registered promoter entity is Purva Ruby Properties Limited, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Purva Zentech Business Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Purva Zentech Business Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback