Home / Browse projects / Bengaluru Urban, Karnataka / Purva Zentech
Purva Zentech
By Purva Ruby Properties Pvt Ltd
RG-KA-32312 · RERA PRM/KA/RERA/1251/310/PR/071022/005301 · Last updated on RERA Karnataka portal: 19 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Purva Zentech is a Commercial project by Purva Ruby Properties Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/071022/005301 on 7 Oct 2022. Possession is promised by 1 Jun 2027. 18 of the 18 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.
At a glance
Project
- NamePurva Zentech
- TypeCommercial
- Location
- Bengaluru South
- Bengaluru Urban
- 560062
- Pincode560062
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/071022/005301
- ReraGenie IDRG-KA-32312
Builder
- NamePurva Ruby Properties Pvt Ltd
- Entity typeCompany
- CINU45203KA2007PTC042433
- GSTIN29AAECP7176R1ZD
- Authorized SignatoryJatin Ujjini C S
- Chief Executive OfficerAbhishek Kapoor
- DirectorAbhishek Kapoor
- Project HeadSanjay Sharma
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on7 Oct 2022
- Promised completion1 Jun 2027
- Revised completionNone
- Buildings1 building record
- Documents filed158 files
Current status
Figures as on 19 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Purva Zentech | - | - | - | 0 | 18 | 18 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 19 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 17 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
Progress on shared amenities40
As on 19 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Emergency Evacuation services | Yes | 100% |
| Internal Roads & Footpaths | Yes | 100% |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 100% |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 100% |
| Piped Gas | Yes | 100% |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | Yes | 100% |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | Yes | 100% |
| Provision for lodging of management staff and security staff | Yes | 100% |
| Water conservation and renewable energy | Yes | 100% |
| Common storage spaces | Yes | 100% |
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mr. S.Sharadaprasad | - | - |
| M/s Alblanc Private Limited | - | - |
| M/s. Oasis Construactions | - | - |
| Mr. S.Lakshminarayan | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 221.36 cr | Rs 267.21 cr |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 45.53 cr | Rs 71.99 cr |
| Payment of taxes | Rs 44.46 cr | - |
| On-site expenditure-Site Overhead | Rs 30.88 cr | Rs 1.59 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RSP Design Consultants (India) Pvt ltd. |
| Engineer | WTP Cost Advisory Services (I) Pvt Ltd |
| Chartered Accountant | V D S R & Co LLP |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed158
As listed on the registration, under the names the promoter filed them with; the newest 80 of 158 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/071022/005301 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy CertficateFile: Purva OC Signed.pdf | 19 Oct 2026 |
| Renewed Approved Building plan order letterFile: cc_BBMP_EoDB_CH_12382_26-27.pdf | 19 Oct 2026 |
| Form 6File: Eng Certificate modification Plan Form 6 Zentech.pdf | 19 Oct 2026 |
| Declaration ConsentFile: Query Consent.pdf | 19 Oct 2026 |
| Modified PlanFile: PRJ_0896_25-26 Site Plan_compressed.pdf | 19 Oct 2026 |
| Structural stabilityFile: DT-stability certificate_260322_170413.pdf | 19 Oct 2026 |
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Purva Zentech_compressed.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Zentech - Form 1 (RERA) - Architect Certificate-Sep-23, 2026.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Zentech Engineers Certificate Fy 26-27 Q2.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Ruby RERA_compressed.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Zentech - Form 1 (RERA) - Architect Certificate-June 30, 2026.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 4 Ruby RERA_compressed.pdf | 15 Jul 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Ruby Dec 25.pdf | 25 May 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Zentech - Form 1 (RERA) - Architect Certificate-Jan 02, 2026.pdf | 25 May 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Ruby RERA March 26.pdf | 25 May 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Zentech - Form 1 (RERA) - Architect Certificate- March 2026.pdf | 25 May 2026 |
| AOS ZentechFile: RERA ZENTECH.pdf | 23 Sep 2022 |
| AOSFile: ATS - Proforma Zen.pdf | 24 Aug 2022 |
| Annexure 1File: Annexure 1_compressed.pdf | 24 Aug 2022 |
| Annexure 2File: Annexure 2.pdf | 24 Aug 2022 |
| Annexure 3File: Annexure 3_compressed.pdf | 24 Aug 2022 |
| Annexure 4File: Annexure 4.pdf | 24 Aug 2022 |
| Order copyFile: Zentech Order.pdf | 26 Jul 2022 |
| Document No. 1 AOSFile: Document 1 Zentech ATS (070522).pdf | 26 Jul 2022 |
| CDP Plan and extract of zoning regulationsFile: CDP_merged (1).pdf | 26 Jun 2022 |
| Non Litigation AffidavitFile: Non Lit Affidavit.pdf | 8 Jun 2022 |
| BWSSBFile: BWSSB NOC Undertaking.pdf | 8 Jun 2022 |
| DPFile: Doddakallasandra village DP (This saved by RKV Pan Drive)_compressed.pdf | 8 Jun 2022 |
| Query 2File: Release Deed.pdf | 2 Jun 2022 |
| Query 1 MRFile: MR Zen 44-5-6.pdf | 2 Jun 2022 |
| Zentech ATSFile: Zentech ATS (070522).pdf | 2 Jun 2022 |
| BWSSBFile: Declaration BWSSB NOC (1).pdf | 2 Jun 2022 |
| BESCOMFile: BESCOM.pdf | 2 Jun 2022 |
| Zentech Order copyFile: Zentech Order.pdf | 7 May 2022 |
| CA CertificateFile: Form1 CA Certificate-Zentech.pdf | 7 May 2022 |
| Directors reportFile: DIRECTORS REPORT 2019.pdf | 7 May 2022 |
| RTCFile: RTC-1_merged.pdf | 7 May 2022 |
| MRFile: MR Zen.pdf | 7 May 2022 |
| Sale deedFile: Sale Deed.pdf | 7 May 2022 |
| Release deedFile: Release Deed.pdf | 7 May 2022 |
| Form BFile: Form B.pdf | 7 May 2022 |
| Annexure 1File: UDD Secretariat Notification No UDD 255 MNJ 2018.pdf | 7 May 2022 |
| CDPFile: CDP_merged.pdf | 7 May 2022 |
| KSPCB CFEFile: KSPCB CFE.pdf | 7 May 2022 |
| Demarcated planFile: Site Plan_Building Extent Demarcated.pdf | 7 May 2022 |
| Building LicenseFile: BBMP Building Licence.pdf | 7 May 2022 |
| BMRCLFile: BMRCL NOC.pdf | 7 May 2022 |
| Advocate search ReportFile: Advocate Search Report.pdf | 7 May 2022 |
| SpecificationFile: Specification.pdf | 7 May 2022 |
| STP DemarcatedFile: STP Demarcated.pdf | 7 May 2022 |
| STP ReportFile: STP report_merged.pdf | 7 May 2022 |
| Engineer certificateFile: Engineer Certificate.pdf | 7 May 2022 |
| AOSFile: Zentech ATS Proforma.pdf | 7 May 2022 |
| BWSSBFile: Declaration BWSSB NOC.pdf | 7 May 2022 |
| AffidavitFile: Affidavit.pdf | 7 May 2022 |
| Sanction DrawingFile: BBMP Sanction drawing signed.pdf | 7 May 2022 |
| RTC, survey 43/1,43/2,44/4,44/5,44/6,44/7 | - |
| Mutation, survey 43/1,43/2,44/4,44/5,44/6,44/7 | - |
| Encumbrance Certificate, survey 43/1,43/2,44/4,44/5,44/6,44/7 | - |
| Conversion/Alienation Order, survey 43/1,43/2,44/4,44/5,44/6,44/7 | - |
| Sale/Title/Gift Deed, survey 43/1,43/2,44/4,44/5,44/6,44/7 | - |
| JDA, survey 43/1,43/2,44/4,44/5,44/6,44/7 | - |
| Khatha, survey 43/1,43/2,44/4,44/5,44/6,44/7 | - |
| Registration CertificateFile: Company Registeration Certificate.pdf | - |
| Organization StructureFile: Org chart_ 2022.xlsx | - |
| Certificate issued by CA Form 1File: Form1 CA Certificate-Zentech.pdf | - |
| Certificate issued by Architect Form 2File: NA (1).pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: NA (2).pdf | - |
| Certificate from Chartered AccountFile: NA (1).pdf | - |
| Balance Sheet 2020 - 2021File: Balance Sheet 2021_compressed.pdf | - |
| Balance Sheet 2019 - 2020File: Balance Sheet 2020_compressed.pdf | - |
| Balance Sheet 2018 - 2019File: Balance Sheet 2019.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: Statement of P & L 2021_compressed.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Statement of P & L 2020_compressed.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: Statement of P & L 2019.pdf | - |
| Director's Report 2020 - 2021File: NA (1).pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Purva Zentech on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 21 registered projects within 2 km.
CASAGRAND CASABLANCA
CASAGRAND LOTUS PRIVATE LIMITED
Assetz Meru & Meadow
GOKULAM SHELTERS PRIVATE LIMITED
Sattva Forest Ridge
Sattva Resi Private Limited
CASAGRAND ZAIDEN
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
MAHINDRA EDEN PHASE-1
MAHINDRA LIFESPACE DEVELOPERS LIMITED
MAHINDRA EDEN PHASE-2
MAHINDRA LIFESPACE DEVELOPERS LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: Purva Ruby Properties Pvt Ltd
Purva Ruby Properties Pvt Ltd has 1 registration on RERA Karnataka, including Purva Zentech. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Purva Zentech is delayed beyond 1 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Purva Zentech?
The registered promoter entity is Purva Ruby Properties Pvt Ltd, a company as per the filing. Its CIN U45203KA2007PTC042433 and GSTIN 29AAECP7176R1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Purva Zentech?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Purva Zentech?
The professionals named in the filing: Architect: RSP Design Consultants (India) Pvt ltd.; Engineer: WTP Cost Advisory Services (I) Pvt Ltd; Chartered Accountant: V D S R & Co LLP. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Purva Zentech?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback