ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Purva Orient Grand

Registration approved No litigation declared Residential/Group Housing project

Purva Orient Grand

By Puravankara Limited

RG-KA-56102 · RERA PRM/KA/RERA/1251/310/PR/210907/004299 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2027Possession promisedno revision filed
6 of 17Construction stages donefurthest along: Joinery: Doors, 45%
85 of 97Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 148 documents Report an error

Purva Orient Grand is a Residential/Group Housing project by Puravankara Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210907/004299 on 7 Sep 2021. Possession is promised by 30 Jun 2027. 12 of the 97 units on this registration are recorded sold or booked, and 6 of 17 construction stages are filed complete.

At a glance

Project

  • NamePurva Orient Grand
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/210907/004299
  • ReraGenie IDRG-KA-56102

Builder

  • NamePuravankara Limited
  • Entity typeCompany
  • CINL45200KA1986PLC051571
  • Authorized SignatoryNani R Choksey
  • DirectorAshish Puravankara
  • Other registrations26 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredSep 2021PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Sep 2021
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed148 files

Current status

12%12 of 97 units booked
74.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Purva Orient Grand---97097

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 17 construction stages are filed complete. The stage furthest along is Joinery: Doors, at 45%.

Building: 43% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)Not applicable
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling26%
Joinery: Doors, Windows, Ventilators etc45%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)45%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network6%
Weather Proof work(tile,concrete)8%
Painting8%
Elevation work0%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes88%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes38%
Water conservationYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes50%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes0%
Smart Home AutomationYes0%
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes82%
LiftsYes82%
Staircases and Lift lobbies, corridor,lobbies, corridorYes82%
Fire escapesYes82%
Common entrance and exit for the building / common portico/foyer/verandahYes82%
BasementYes82%
TerraceYes82%
Outer WallYes82%
Open parking areas and common storage spacesYes82%
Provision for lodging of management staff and security staffYes82%
Water conservation and renewable energyYes0%

Land and ownership28

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,677 sq m
Named landowners28
LandownerVillageDistrict
S KUSUMA--
S V MEGHA--
SAROJA--
ARJUN B GOWDA--
S V HEMANTH KUMAR--
G S KUSUMA RANI--
G S SARASWATHI--
S K MANASWINI--
MANU GOWDA S V--
S J KIRAN--
S K VINAY--
KALAVATHI--
S K ANOOP--
BHAVANI GOWDA--
G S VIJAYA RAGHAVA--
G S PRABHAKAR--
RAMYA VENKATA RAJU--
S J SUMAN--
S DAMODHAR--
S P ROHINI--
S V SANJAY--
SMITHA ANIL--
S P ASHWINI--
G S AMARNATH--
G S DHANALAKSHMI--
S V BHASKAR--
V HARSHA--
B N KAMALA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 108.63 cr
Cost incurredRs 81.12 cr
Spent of the estimate74.68%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 65.99 crRs 34.94 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 15.52 crRs 32.47 cr
Payment of taxesRs 13.67 cr-
On-site expenditure-Site OverheadRs 13.45 crRs 13.71 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC B Vivek Uthaiah
EngineerStarworth Infrastructure and Construction Limited

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed148

As listed on the registration, under the names the promoter filed them with; the newest 80 of 148 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210907/004299 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Orient Grand Form 4 Mar 2026.pdf15 Oct 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Orient Grand Architect Certificate Mar26.pdf15 Oct 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: QU Form-6 Engineer Certificate -Orient Grand Q4 FY 25-26.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Orient Grand RERA Form 4 Jun26.pdf15 Oct 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Orient Grand Architect Certificate Jun26.pdf15 Oct 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Orient Grand Engineering Certificate Jun26.pdf15 Oct 2026
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Orient Grand RERA Form4-Sep26 Final.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Orient Grand Architect Certificate.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: 3 Purva Orient Grand Qu 2 2026-27.pdf15 Oct 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Orient Grand RERA Form4 Dec25.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Orient Grand-Architect certificate Dec25.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Orient Grand Engineer Certificate Dec25.pdf31 Mar 2026
CA Certificate in prescribed formatFile: Form -4, Chartered Accountant Orient Grand.pdf23 May 2022
Fire NOCFile: Fire NOC POG.pdf23 May 2022
Airport NOCFile: AAI.pdf7 May 2022
BESCOMFile: BESCOM NOC.pdf7 May 2022
BWSSBFile: BWSSB NOC .pdf7 May 2022
EnvironmentFile: Environmental Clearance.pdf7 May 2022
KSPCBFile: KSPCB POG.pdf7 May 2022
BSNLFile: BSNL.pdf7 May 2022
Form 4 CA CertifcateFile: Form -4, Chartered Accountant Orient Grand.pdf7 May 2022
Sold and Unsold inventoriesFile: Sold and Unsold Inventories Details.pdf7 May 2022
STP DesignFile: 70kld.pdf7 May 2022
SpecificationFile: Specs_compressed.pdf7 May 2022
Structural Stability CertifcateFile: Strctural Stability Certificate.pdf7 May 2022
Engineer CertificateFile: Engineer Certifcate.pdf7 May 2022
Annexure 1File: Declaration POG.pdf7 May 2022
BrochureFile: Brochure.jpg7 May 2022
AOSFile: Orient Grand-ATS.pdf7 May 2022
Declaration and Undertaking (BWSSB)File: Promoter Declaration POG (BWSSB).pdf4 Sep 2021
BESCOM NOCFile: BESCOM NOC (POG).pdf12 Aug 2021
BSNL NOCFile: BSNL NOC (POG).pdf12 Aug 2021
BWSSB NOCFile: BWSSB NOC (POG).pdf12 Aug 2021
KSPCB NOCFile: KSPCB NOC (POG).pdf12 Aug 2021
SEIAA NOCFile: SEIAA NOC (Extension Notification Included).pdf12 Aug 2021
FIRE NOCFile: Fire NOC (POG).pdf12 Aug 2021
AAI NOCFile: AAI (POG).pdf12 Aug 2021
Bank Account Details (POG)File: Purva Orient Grand (Bank Account Details).jpg12 Aug 2021
Financial Statements with CA UDIN(2019-2020)File: Puravankara Audited Financial Statement with CA UDIN (2019-2020).pdf5 Aug 2021
ITR (2019-2020)File: Puravankara Limited ITR (2019-20).pdf5 Aug 2021
Declaration (BESCOM)File: Declaration (BESCOM NOC).pdf5 Aug 2021
Declaration (Bank Account)File: Declaration (Bank Account).pdf5 Aug 2021
Revised Master Plan 2015 (Chapter 7 - Relinquishment)File: RMP 2015 (Chapter 7 - Relinquishment).pdf5 Aug 2021
Floor PlansFile: Floor Plans (POG).pdf30 Jul 2021
Section and Elevation PlanFile: Section Plan (POG).pdf30 Jul 2021
Form BFile: Form B (POG).pdf30 Jul 2021
Encumbrance CertificatesFile: EC final (POG).pdf30 Jul 2021
Title DeedsFile: Sale and Amalagamated Agreement (POG).pdf30 Jul 2021
Partition DeedsFile: Partition Deeds (POG).pdf30 Jul 2021
Airport NOCFile: Airport NOC (POG).pdf30 Jul 2021
BESCOM NOCFile: BESCOM NOC (POG).pdf30 Jul 2021
BSNL NOCFile: BSNL NOC (POG).pdf30 Jul 2021
BWSSB NOCFile: BWSSB NOC (POG).pdf30 Jul 2021
Fire NOCFile: Fire NOC (POG).pdf30 Jul 2021
KSPCB NOCFile: KSPCB NOC (POG).pdf30 Jul 2021
Financial StatementFile: PL SA-Financials 31-Mar-20-Audited.pdf30 Jul 2021
ITR (2019-20)File: ITR-V_Acknowledgement.pdf30 Jul 2021
CMP 3570 (Sale Deed)File: CMP 3570 (Sale Deed).pdf15 Jul 2021
CMP 3570 (Statement of Accounts)File: CMP 3570 (SOA - Compensation Paid).pdf15 Jul 2021
(Supporting Documents)File: 849 (Supporting Docs).pdf12 Jul 2021
CMP 512 (Supporting Documents)File: Niranjan Goyal (KREAT Appeal 295 of 2020).pdf2 Jul 2021
CMP 775 (Supporting Documents)File: Magesh Nandakumar (Docs).pdf2 Jul 2021
CMP 849 (Supporting Documents)File: Manjunath KS (Deposit).pdf2 Jul 2021
CMP 979 (Supporting Documents)File: Magesh Nandakumar (Docs).pdf2 Jul 2021
CMP 1834 (Supporting Documents)File: Memo for Deposit - Appeal 370 of 2020.pdf2 Jul 2021
CMP 2977 (Supporting Documents)File: Memo of Calculation and Deposit (Appeal No 371 of 2020).pdf2 Jul 2021
CMP 3715 (Supporting Documents)File: Magesh Nandakumar (Docs).pdf2 Jul 2021
CMP 3859 (Supporting Documents)File: Suman Pirgal (Order Copy - 3859).pdf2 Jul 2021
CertificateFile: COI (Puravankara).pdf-
Already registered project ongoing detailsFile: RERA Progress certificate - Woodfield Q2 2021.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Sanctioned Plans.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Section Plan (Purva Orient Grand).pdf-
List Of AllotteesFile: NA (2).pdf-
List Of ComplaintsFile: NA (2).pdf-
Consent LetterFile: NA (2).pdf-
List Of Pending LitigationsFile: NA (2).pdf-
Chartered Accountant CertificateFile: Form -4, Chartered Accountant Orient Grand.pdf-
Notarized AffidavitFile: Affidavit - PL.pdf-
Engineer CertificateFile: Engineer Certifcate.pdf-
Architect CertificateFile: Form-2 Architect Certificate (PR) (2).pdf-

How this compares with Bengaluru Urban

12%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Purva Orient Grand on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Puravankara Limited

Puravankara Limited has 27 registrations on RERA Karnataka, including Provident Deansgate and Provident Deansgate Phase 2. Its filings declare 5 earlier projects, 5 of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Purva Orient Grand is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Purva Orient Grand?

The registered promoter entity is Puravankara Limited, a company as per the filing. Its CIN L45200KA1986PLC051571 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Purva Orient Grand?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Purva Orient Grand?

The professionals named in the filing: Architect: C B Vivek Uthaiah; Engineer: Starworth Infrastructure and Construction Limited. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Purva Orient Grand?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Purva Orient Grand. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Purva Orient Grand to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.