Home / Browse projects / Bengaluru Urban, Karnataka / PURSUIT OF HAPPINESS

Registration approved Residential/Group Housing project

PURSUIT OF HAPPINESS

By MUPPIRI DEVELOPERS

RG-KA-10092 · RERA PRM/KA/RERA/1251/310/PR/200103/003131 · Last updated on RERA Karnataka portal: 18 Dec 2019

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2025Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 53 documents Report an error

PURSUIT OF HAPPINESS is a Residential/Group Housing project by MUPPIRI DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/200103/003131 on 3 Jan 2020. Possession is promised by 1 Sep 2025. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NamePURSUIT OF HAPPINESS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/200103/003131
  • ReraGenie IDRG-KA-10092

Builder

  • NameMUPPIRI DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryNARASIMHA M S

Key dates

this monthRegisteredJan 2020First promiseDec 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on3 Jan 2020
  • Promised completion1 Sep 2025
  • Revised completionRevised to 1 Sep 2025 (originally 1 Dec 2024)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PURSUIT OF HAPPINESS---1470147

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 18 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities31

As on 18 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,548 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 40.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectT P SREE LAKSHMI
EngineerA RAMCHANDRAN

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2024 → Sep 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed53

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/200103/003131 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CASHFLOW STATEMENTFile: Cashflow statement.pdf18 Dec 2019
PLAN LICENCEFile: plan licence.pdf18 Dec 2019
PROJECT HEAD DETAILSFile: Head Details.pdf18 Dec 2019
2019 balance sheetFile: 1 BALANCE SHEET 2019.pdf9 Dec 2019
2019 audited profit and loss statementFile: 2 AUDITED PROFIT AND LOSS STATEMENT 2019.pdf9 Dec 2019
2109 directors reportFile: 3 DIRECTORS REPORT.pdf9 Dec 2019
2019 cash flow statementFile: 4 CASH FLOW STATEMENT 2019.pdf9 Dec 2019
2019 auditors reportFile: 5 AUDITOR REPORT 2019.pdf9 Dec 2019
2019 itr acknowledgementFile: 6 INCOME TAX RETURN 2019.pdf9 Dec 2019
sanctioned floor plans elevation and sectionsFile: PLAN COPY.pdf9 Dec 2019
licence copyFile: .pdf9 Dec 2019
CertificateFile: ACKNOWLEDGEMNT OF REGISTER OF FIRMS.pdf-
10 SANCTIONED PLAN -
10 SANCTIONED PLAN-
18 SALE DEED DRAFT-
12 SALE AGREEMENT-
13 SALE DEED-
14 SANCTIONED SECTION-
ALLOTMENT-
19 SPECIFICATIONS-
19 SPECIFICATIONS-
8 ENCUMBERANCE CERTIFICATE-
22 KATHA EXTRACT-
22 KATHA CERIFICATE-
25 CONVERSION-
27 FIRE NOCC-
28 AIRPORT NOC-
29 BESCOM NOC-
30 BWSSB NOC-
31 KSPCB NOC-
32 SEIAA NOC-
33 BSNL -
14 SANCTIONED SECTION-
25 CONVERSION-
Balance Sheet 2018 - 2019File: 1 BALANCE SHEET 2018.pdf-
Balance Sheet 2017 - 2018File: 1 BALANCE SHEET 2017.pdf-
Balance Sheet 2016 - 2017File: 1 BALANCE SHEET 2016pdf.pdf-
Audited Profit and Loss Statement 2018 - 2019File: 2 AUDITED PROFIT LOSS STATEMENT 2018.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 2 AUDITED PROFIT LOSS STATEMENT 2017.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 2 AUDITED PROFIT LOSS STATEMENT2016.pdf-
Director's Report 2018 - 2019File: 3 DIRECTORS REPORT.pdf-
Director's Report 2017 - 2018File: 3 DIRECTORS REPORT.pdf-
Director's Report 2016 - 2017File: 3 DIRECTORS REPORT.pdf-
Cash Flow Statement 2018 - 2019File: 4 CASH FLOW STATEMENT 2018.pdf-
Cash Flow Statement 2017 - 2018File: 4 CASH FLOW STATEMENT 2017.pdf-
Auditor's Report 2018 - 2019File: 5 AUDITOR REPORT 2018.pdf-
Auditor's Report 2017 - 2018File: 5 AUDITOR REPORT 2017.pdf-
Auditor's Report 2016 - 2017File: 5 AUDITOR REPORT 2016.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: 6 INCOME TAX RETURN 2018.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: 6 INCOME TAX RETURN 2017.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 6 INCOME TAX RETURN 2016.pdf-
21 AFFIDAVIT_compressed-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_200103_003131.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep PURSUIT OF HAPPINESS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPURSUIT OF HAPPINESSOther 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: MUPPIRI DEVELOPERS

MUPPIRI DEVELOPERS has 1 registration on RERA Karnataka, including PURSUIT OF HAPPINESS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if PURSUIT OF HAPPINESS is delayed beyond 1 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PURSUIT OF HAPPINESS?

The registered promoter entity is MUPPIRI DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PURSUIT OF HAPPINESS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PURSUIT OF HAPPINESS?

The professionals named in the filing: Architect: T P SREE LAKSHMI; Engineer: A RAMCHANDRAN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PURSUIT OF HAPPINESS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PURSUIT OF HAPPINESS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PURSUIT OF HAPPINESS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.