Home / Browse projects / Mumbai Suburban, Maharashtra / PUNEET SHIVALAYA
PUNEET SHIVALAYA
RG-MH-29774 · RERA P51800029659 · Last updated on MahaRERA portal: 31 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 6 months
- 1 extension taken
- Rs 44.00 crore secured on the land, in favour of Bajaj Housing Finance Limited
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PUNEET SHIVALAYA is a Residential / Group Housing project by PUNEET EDIFICE PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029659 on 14 Jun 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 6 months from the original filing. 141 of the 159 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NamePUNEET SHIVALAYA
- TypeResidential / Group Housing
- Location
- Tagore Nagar
- Hariyali
- Vikhroli
- Kurla
- Mumbai Suburban
- 400083
- Pincode400083
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800029659
- ReraGenie IDRG-MH-29774
Builder
- NamePUNEET EDIFICE PVT LTD
- Entity typeCompany
- CINU70109MH2019PTC333338
- GSTIN27AAKCP8860G1ZX
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsASHA SUBHASH PATIL, MEENA PRAKASH BAUSKAR
- Other registrations4 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Jun 2021
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2025)
- Buildings2 building records
- Documents filed114 files
Current status
Figures as on 31 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PUNEET SHIVALAYA A WING | NA | 25 | 23 | 107 | 0 | 107 |
| PUNEET SHIVALAYA B WING | NA | 25 | 0 | 52 | 0 | 52 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 31 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
PUNEET SHIVALAYA A WING91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
PUNEET SHIVALAYA B WING91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 31 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed73
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| PUNEET SHIVALAYA A WING | 36 | 36 |
| PUNEET SHIVALAYA B WING | 37 | 37 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| TAGORE NAGAR SANMITRA CO OP HSG SOC LTD | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| PUNEET SHIVALAYA A WING | NA | Rs 20.56 cr | Rs 19.28 cr |
| PUNEET SHIVALAYA B WING | NA | Rs 20.56 cr | Rs 19.28 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Subhash Ganpatrao Patil |
| Architect | Subhash Patil and Associates |
| Engineer | Rajesh B Harari |
| Engineer | Sharad D Prabhu |
| Engineer | Anand Krishnaji Kulkarni |
| Engineer | Sreekumar Girish Nair |
| Chartered Accountant | ANSHANI & ASSOCIATES CHARTERED ACCOUNTANTS |
| Chartered Accountant | Anshani & Associates Chartered Accounts |
| Chartered Accountant | SB Rohra and Co. |
| Partner | Role in project |
|---|---|
| PUNEET EDIFICE PVT LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per the provisions of the registered Development Agreement dated 21st January, 2021, the Promoter is required to give the possession of the building to the members within 60 months from the date of possession date or the date of first CC i.e. 07.06.2021, whichever is earlier, which is on or before 07.06.2026 and to the purchasers on or before 30th June, 2025 as per the Maharera Registration Certificate. The Project is under construction and has completed 95% of the construction work as per Form 1. The Promoter was to complete the project on or before 30th June 2025. However, the project was
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12502484 | Anil Upendra Panda | PUNEET EDIFICE PVT LTD | 19/07/2025 |
| CC12502720 | Subodh shivaji kachare | PUNEET EDIFICE PVT LTD | 04/08/2025 |
| CC12600046 | SHASHANK SHIRISH MORE | PUNEET EDIFICE PVT LTD | 03/01/2026 |
| CC12600094 | Sunny Suhas Sumanth Kanekal | PUNEET EDIFICE PVT LTD | 06/01/2026 |
| CC12600451 | Vinay shrikant Morajkar | PUNEET EDIFICE PVT LTD | 24/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 May 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 May 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Sep 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed114
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form -1 (2).pdf | 31 Dec 2025 |
| Withdrawal Update Form 1File: Form -1 (2).pdf | 31 Dec 2025 |
| Withdrawal Update Form 2File: FORM_2_Shivalaya_Q1 SIGNED (3).pdf | 31 Dec 2025 |
| Withdrawal Update Form 2File: FORM_2_Shivalaya_Q1 SIGNED (3).pdf | 31 Dec 2025 |
| Withdrawal Update Form 3File: FORM_3_Q1_Shivalaya SIGNED (2).pdf | 31 Dec 2025 |
| Withdrawal Update Form 3File: FORM_3_Q1_Shivalaya SIGNED (2).pdf | 31 Dec 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed Shivalaya_Q4.pdf | 22 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Signed Shivalaya_Q4.pdf | 22 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2025_03_31_ T28 SHIVALAYA ARCH CERT.pdf | 4 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q-2 Form-3.pdf | 27 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q-3 Form-3.pdf | 27 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q-2 Form2.pdf | 27 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q-3 Form2.pdf | 27 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122024 Form 1 Ac.pdf | 17 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122024 Form 1 Ac.pdf | 17 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122024 Form 1 Ac.pdf | 17 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Puneet Shivalaya 17122024.pdf | 17 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Puneet Shivalaya 17122024.pdf | 17 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Puneet Shivalaya 17122024.pdf | 17 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bldg no 28 Form 2.pdf | 7 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bldg no 28 Form 3.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B No 28 Arch.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B No 28 Arch.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bldg no 28 Form 2.pdf | 7 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bldg no 28 Form 3.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B No 28 Arch.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B No 28 Arch.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bldg no 28 Form 2.pdf | 7 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bldg no 28 Form 3.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B No 28 Arch.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B No 28 Arch.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B No 28 Arch.pdf | 7 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bldg no 28 Form 3.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bldg no 28 Form 2.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B No 28 Arch.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed T28 Architect Cert.pdf | 9 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed T28 Architect Cert.pdf | 9 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2.pdf | 8 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3.pdf | 8 Jul 2024 |
| Details of encumbrancesFile: encumbrance certificate bn 28 3rd.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT SHIVALAYA.pdf | 10 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Puneet Shivalay Form 3.pdf | 5 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Puneet Shivalaya.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg June 2023.pdf | 12 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Sept 2023.pdf | 12 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA shivalaya Sept 2023.pdf | 12 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: T 28.pdf | 11 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Shivalaya.pdf | 16 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate.pdf | 29 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shivalaya Certificate_form3_June23.pdf | 15 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 24072023.pdf | 30 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: buld 28 tagore nagar sanmitra chs ltd.pdf | 30 Aug 2023 |
| Details of encumbrancesFile: encumbrance certificate 1.pdf | 1 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shivalaya Architect.pdf | 26 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shivalaya CA.pdf | 26 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Puneet Shivalaya.pdf | 18 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate of Puneet Shivalaya as on 31122022.pdf | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 28 ca .pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Puneet Shivalaya.pdf | 9 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 31122022.pdf | 27 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ec Shivalaya.pdf | 20 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 7439_furthercc_signed.pdf | 9 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Puneet Shivalaya Form 5 31032022.pdf | 21 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ES QA Puneet Shivalaya.pdf | 15 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect CertificateREVISED.pdf | 12 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 30092022.pdf | 12 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shivalaya Engineer.pdf | 28 Sep 2022 |
| OtherFile: Offer letter 31122022.pdf | 28 Sep 2022 |
| Building plan approvalFile: Amended plan-ML- 28122021_compressed.pdf | 19 Sep 2022 |
| Building plan approvalFile: Amended Plans 28122021_to ML letter 28122021_1.pdf | 19 Sep 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended plan-ML- 28122021_compressed.pdf | 19 Sep 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended Plans 28122021_to ML letter 28122021_1.pdf | 19 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate for Shivalaya Project Jun'22.pdf | 19 Sep 2022 |
| OtherFile: Mhada NOC.pdf | 19 Sep 2022 |
| OtherFile: Mhada Offer letter.pdf | 19 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: First CC Signed.pdf | 5 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shivalaya arch certificate.pdf | 19 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate.pdf | 19 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate and Sold Unsold Inventory Puneet Shivalaya Project.pdf | 19 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 7 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 114 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PUNEET SHIVALAYA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hariyali, Vikhroli6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 145 registered projects within 2 km.
Cons 1221 MIG T/S and 100 Shops S. No. 113 (pt
Mumbai Housing And Area Development Board
Om Siddhivinayak CHS and Gurukrupa CHS
Shreeji Developers
AKASSH AMAZONIA TOWER 1
HEER MEHTA LANDMARK DEVELOPERS PRIVATE LIM
Ajmera Solis
Shree Yogi Realcon Private Limited
CENTRAL PARK
V LAXMI NURSES DEVELOPERS LLP
Swastik Platinum
SUVASYA BUILDERS AND DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: PUNEET EDIFICE PVT LTD
PUNEET EDIFICE PVT LTD has 5 registrations on MahaRERA, including PUNEET SHIVALAYA and Puneet Brahmand. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that PUNEET SHIVALAYA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PUNEET SHIVALAYA is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PUNEET SHIVALAYA?
The registered promoter entity is PUNEET EDIFICE PVT LTD, a company as per the filing. Its CIN U70109MH2019PTC333338 and GSTIN 27AAKCP8860G1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PUNEET SHIVALAYA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PUNEET SHIVALAYA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PUNEET SHIVALAYA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PUNEET SHIVALAYA?
The professionals named in the filing: Architect: Subhash Ganpatrao Patil; Architect: Subhash Patil and Associates; Engineer: Rajesh B Harari; Engineer: Sharad D Prabhu; Engineer: Anand Krishnaji Kulkarni; Engineer: Sreekumar Girish Nair. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PUNEET SHIVALAYA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback