Home / Browse projects / Bengaluru Urban, Karnataka / PSR KRISH KAMAL
PSR KRISH KAMAL
By SREE & SREE BUILDERS & PROMOTERS
RG-KA-14760 · RERA PRM/KA/RERA/1251/308/PR/180313/001839
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
PSR KRISH KAMAL is a Residential/Group Housing project by SREE & SREE BUILDERS & PROMOTERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180313/001839 on 13 Mar 2018. Possession is promised by 31 Dec 2020. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NamePSR KRISH KAMAL
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/308/PR/180313/001839
- ReraGenie IDRG-KA-14760
Builder
- NameSREE & SREE BUILDERS & PROMOTERS
- Entity typePartnership Firm
- Authorized SignatoryP Sreedhar Reddy
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on13 Mar 2018
- Promised completion31 Dec 2020
- Revised completionRevised to 31 Dec 2020 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed37 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | - | - | - | 351 | 0 | 351 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | V.Sivakumar |
| Engineer | Srinivasa Rao Bolimunta |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterShortage of Labour
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00009/2025 | - | SREE & SREE BUILDERS & PROMOTERS | 02/01/2025 |
Documents filed37
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180313/001839 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: SREE & SREE Registration certificate.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: ARC WORK COMP.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: ENG WORK COMP.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Funds Utilization Certificate-compressed.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: ARC WORK PENDING.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: ENG WORK PENDING.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA Funds Requirement Certificate-compressed.pdf | - |
| AffidavitFile: Rera Affidavit 1.PDF | - |
| Latest Encumbrance CertificateFile: EC April 2018 to Jan 2020.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| NOC DetailsFile: BESCOM NOC.jpg | - |
| Commenement cert | - |
| Approved Building Plan Plotting Plan | - |
| Aproved Layuot Plan | - |
| Sale Deed Draft | - |
| Agreement draft | - |
| Approved Building Plan Plotting Plan | - |
| Area develoment Plan | - |
| PSR - Krish Kamal (E-Brochure) | - |
| Project Specification | - |
| Encumbrance cert | - |
| Katha | - |
| JDA | - |
| Balance Sheet 2015 - 2016File: SREE & SREE FY 2015-16 Balance Sheet.pdf | - |
| Balance Sheet 2014 - 2015File: SREE & SREE FY 2014-15 Cash Flow Statement.pdf | - |
| Balance Sheet 2013 - 2014File: SREE & SREE FY 2013-14 Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: SREE & SREE FY 2015-16 Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: SREE & SREE FY 2014-15 Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: SREE & SREE FY 2013-14 Balance Sheet.pdf | - |
| Cash Flow Statement 2015 - 2016File: SREE & SREE FY 2015-16 Cash Flow Statement.pdf | - |
| Cash Flow Statement 2014 - 2015File: SREE & SREE FY 2014-15 Cash Flow Statement.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: SREE & SREE 2015-16 ACK.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: SREE & SREE 2014-15 ITR ACK.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: SREE & SREE 2013-14 ITR ACK.pdf | - |
| Prospectus/BrochureFile: PSR Krish Kamal-Broucher.pdf | - |
| Advertisement Copy 1File: PSR Krish Kamal-Broucher.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_180313_001839.xls | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep PSR KRISH KAMAL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SREE & SREE BUILDERS & PROMOTERS
SREE & SREE BUILDERS & PROMOTERS has 1 registration on RERA Karnataka, including PSR KRISH KAMAL. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if PSR KRISH KAMAL is delayed beyond 31 Dec 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of PSR KRISH KAMAL?
The registered promoter entity is SREE & SREE BUILDERS & PROMOTERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in PSR KRISH KAMAL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PSR KRISH KAMAL?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at PSR KRISH KAMAL?
The professionals named in the filing: Architect: V.Sivakumar; Engineer: Srinivasa Rao Bolimunta. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PSR KRISH KAMAL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.