Provident Park Square Phase 3 (Towers 5A and 5B)
RG-KA-47981 · RERA PRM/KA/RERA/1251/310/PR/180507/001671 · Last updated on RERA Karnataka portal: 23 Jun 2022
Source: official RERA Karnataka filing
Red flags
- 8 complaints at RERA Karnataka
- Completion date moved by 21 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
Provident Park Square Phase 3 (Towers 5A and 5B) is a Residential/Group Housing project by Puravankara Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/180507/001671 on 7 May 2018. Possession is promised by 30 Jul 2023. The completion date has moved by 21 months from the original filing. 8 complaints are on record with the regulator.
At a glance
Project
- NameProvident Park Square Phase 3 (Towers 5A and 5B)
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/180507/001671
- ReraGenie IDRG-KA-47981
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on7 May 2018
- Promised completion30 Jul 2023
- Revised completionRevised to 30 Jul 2023 (originally 31 Oct 2021)
- Buildings2 building records
- Documents filed82 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B5-5A | - | - | - | 112 | 0 | 112 |
| B5-5B | - | - | - | 112 | 0 | 112 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 23 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 23 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/200912/0006565 | - | Puravankara Limited | 12/09/2020 |
| CMP/210308/0007764 | - | Puravankara Limited | 08/03/2021 |
| CMP/210816/0008248 | - | Puravankara Limited | 16/08/2021 |
| CMP/210821/0008259 | - | Puravankara Limited | 21/08/2021 |
| CMP/220321/0009217 | - | Puravankara Limited | 21/03/2022 |
| 00346/2023 | - | Puravankara Limited | 18/03/2023 |
| 01532/2025 | - | Puravankara Limited | 29/12/2025 |
| 01224/2026 | - | Puravankara Limited | 13/10/2026 |
Documents filed82
As listed on the registration, under the names the promoter filed them with; the newest 80 of 82 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/180507/001671 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Form 3File: Form Ex3- Parksquare Phase 3.pdf | 23 Jun 2022 |
| CA Form 4File: Form Ex4- Parksquare Phase 3.pdf | 23 Jun 2022 |
| Engineer Form 5File: Form 5 Engineer.pdf | 23 Jun 2022 |
| Engineer Form 6File: Form 6 Engineer.pdf | 23 Jun 2022 |
| BESCOMFile: BESCOM _merged_compressed.pdf | 23 Jun 2022 |
| BWSSBFile: BWSSB Final.pdf | 23 Jun 2022 |
| AirportFile: Airport NOC.pdf | 23 Jun 2022 |
| Structural StabilityFile: park square stability certificate.pdf | 23 Jun 2022 |
| STP Demarcated PlanFile: SITE PLAN with STP Location.pdf | 23 Jun 2022 |
| STP Structural DrawingFile: STP STRUCTURAL FRAMING LAYOUT AND SECTIONS.pdf | 23 Jun 2022 |
| List of AllotteesFile: List of Allottees for Provident Park Square Phase 3.pdf | 23 Jun 2022 |
| BHKFile: Park Square Phase 3 BHK wise Breakup.pdf | 23 Jun 2022 |
| Consultant DetailsFile: Park square (Consultant Details) R2.xlsx | 23 Jun 2022 |
| Proforma AgreementFile: Park Square Proforma Phase 3_compressed.pdf | 23 Jun 2022 |
| CertificateFile: COI.PDF | - |
| Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate - phase- 3 Status.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Form 5 Engineer.pdf | - |
| CA Certificate for Funds UtilizationFile: Form Ex3- Parksquare Phase 3.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate - phase- 3 Pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Form 6 Engineer.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form Ex4- Parksquare Phase 3.pdf | - |
| AffidavitFile: Affidavit Phase 3.pdf | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| CC | - |
| Development Plan_size | - |
| Keppel Mallasandra Site Plan | - |
| Draft ATS Park Square 2 (RERA) - PR1(Res)_3 | - |
| ATS (Park Square 1) Template 280218 | - |
| Sale Deeds and RTC_sized | - |
| 5A Section | - |
| Phase plan | - |
| Upload_Allotment Letter | - |
| CC | - |
| Specs_sized | - |
| 13 years EC Development land | - |
| Consolidated Khata | - |
| Joint Development Agreement | - |
| Fire NOC New | - |
| AAI Old | - |
| BESCOM New | - |
| BWSSB | - |
| SEIAA New | - |
| SEIAA New | - |
| BSNL | - |
| Keppel Mallasandra Site Plan | - |
| Keppel Mallasandra Site Plan | - |
| Sl No 23 | - |
| Balance Sheet 2016 - 2017File: Balance Sheet 0317.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet Mar-16.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet-Mar-15.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: PL Statement 0317.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Profit and Loss account Mar-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Profit and Loss account-Mar-15.pdf | - |
| Director's Report 2016 - 2017File: Directors Report 2016-17 Puravankara Limited.pdf | - |
| Director's Report 2015 - 2016File: Directors Report -2015-16.pdf | - |
| Director's Report 2014 - 2015File: Directors Report-2014-15.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash Flow Statement 0317.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow Statement Mar-16.pdf | - |
| Auditor's Report 2016 - 2017File: Auditors Report 0317.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor Report Mar-16.pdf | - |
| Auditor's Report 2014 - 2015File: Auditor Report-Mar-15.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: Purvankara - ITR V Mar-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR V Ack_ AY-16-17.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR V Ack-AY-15-16.pdf | - |
| PHL Affidavit and Declaration | - |
| Prospectus/BrochureFile: Provident Park Square Floor Plan Brochure - Phase 1,2 & 3.pdf | - |
| Advertisement Copy 1File: Provident Park Square Floor Plan Brochure - Phase 1,2 & 3.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_180507_001671.xlsx | - |
| Loan raised documentFile: Park Square Phase-3 Form 4 CC.pdf | - |
| Stability CertificateFile: park square stability certificate Phase 2.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: Fire Completion Certificate.pdf | - |
| Occupancy CertificateFile: Occupancy Certificate 1(C,D) 2(C,D,E) 3(E) 4(A,B) 5(A,B).pdf | - |
| Consent for operation issued by KSPCBFile: KSPCB CFO.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Puruvankara 20 Lifts Licence.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Power Sanction.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Power Sanction.pdf | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: completion certificate Parksquare Phase 3.pdf | - |
| Details of undivided share of land handed over to the association of allotteesFile: UDS Final Park square.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: completion certificate Parksquare Phase 3.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Provident Park Square Phase 3 (Towers 5A and on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 44 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Puravankara Limited
Puravankara Limited has 27 registrations on RERA Karnataka, including Provident Deansgate and Provident Deansgate Phase 2. Its filings declare 5 earlier projects, 5 of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Provident Park Square Phase 3 (Towers 5A and 5B) is delayed beyond 30 Jul 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Provident Park Square Phase 3 (Towers 5A and 5B)?
The registered promoter entity is Puravankara Limited, a company as per the filing. Its CIN L45200KA1986PLC051571 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Provident Park Square Phase 3 (Towers 5A and 5B)?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Provident Park Square Phase 3 (Towers 5A and 5B)?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
What should I check before booking in Provident Park Square Phase 3 (Towers 5A and 5B)?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.