ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / PRESTIGE KENILWORTH

Registration approved Residential/Group Housing project

PRESTIGE KENILWORTH

By PRESTIGE ESTATES PROJECTS LIMITED

RG-KA-21516 · RERA PRM/KA/RERA/1251/309/PR/170915/000208

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2021Possession promisedmoved 9 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 35 documents Report an error

PRESTIGE KENILWORTH is a Residential/Group Housing project by PRESTIGE ESTATES PROJECTS LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/170915/000208 on 15 Sep 2017. Possession is promised by 30 Sep 2021. The completion date has moved by 9 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePRESTIGE KENILWORTH
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/170915/000208
  • ReraGenie IDRG-KA-21516

Builder

  • NamePRESTIGE ESTATES PROJECTS LIMITED
  • Entity typeCompany
  • CINU07010KA1997PLC022322
  • Authorized SignatorySWAROOP ANISH
  • OthersRAGHAVENDRA
  • Other registrations24 more →
  • Declared earlier projects28 →

Key dates

this monthRegisteredSep 2017First promiseDec 2020Revised toSep 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Sep 2017
  • Promised completion30 Sep 2021
  • Revised completionRevised to 30 Sep 2021 (originally 31 Dec 2020)
  • Buildings1 building record
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kenilworth---42042

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,439 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 80.79 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTILAK THOMAS
EngineerARUN NADIG

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2020 → Sep 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/201029/0006979-PRESTIGE ESTATES PROJECTS LIMITED29/10/2020

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/170915/000208 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Annexure 1 Incorporation Certificate.pdf-
Plan sanction letter-
Site Plan-
Site Plan-
Sale Deed-
Agreement to Sell-
GPA-
Section Elevation-
cdp-
Proforma of Allotment Letter - PKW-
Prestige Kenilworth Brochure-
NOC-
Kenilworth - Project Specs-
EC-16-
Balance Sheet 2015 - 2016File: PEPL BALANC E SHEET AS ON 31ST 2016.pdf-
Balance Sheet 2014 - 2015File: PEPL BALANC E SHEET AS ON 31ST 2015.pdf-
Balance Sheet 2013 - 2014File: PEPL BALANC E SHEET AS ON 31ST 2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: PEPL P L AS ON 31ST 2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: PEPL P L AS ON 31ST 2015.pdf-
Audited Profit and Loss Statement 2013 - 2014File: PEPL P L AS ON 31ST 2014.pdf-
Director's Report 2015 - 2016File: Directors Report 15-16.pdf-
Director's Report 2014 - 2015File: Directors Report 14-15.pdf-
Director's Report 2013 - 2014File: Directors Report 13-14.pdf-
Cash Flow Statement 2015 - 2016File: PEPL CASH FLOW AS ON 31ST 2016.pdf-
Cash Flow Statement 2014 - 2015File: CASH FLOW AS ON 31ST 2015.pdf-
Auditor's Report 2015 - 2016File: PEPL-Auditors Report -Mar16.pdf-
Auditor's Report 2014 - 2015File: PEPL Auditors Report Mar15.pdf-
Auditor's Report 2013 - 2014File: PEPL Auditors Report March 2014.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: PEPL INCOME TAX-2016-17.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: PEPL INCOM TAX-2015-16.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: PEPL-INCOM TAX-2014-15.pdf-
FORM B-
Prospectus/BrochureFile: Prestige Kenilworth - Brochure.pdf-
Advertisement Copy 1File: Advt Copy.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_170915_000208.xlsx-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
PRESTIGE TRINITY CENTER-Completed-No date filed
PRESTIGE SILVER SUN-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep PRESTIGE KENILWORTH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: PRESTIGE ESTATES PROJECTS LIMITED

PRESTIGE ESTATES PROJECTS LIMITED has 25 registrations on RERA Karnataka, including PRESTIGE DEJAVU and PRESTIGE KENILWORTH. Its filings declare 28 earlier projects, 28 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if PRESTIGE KENILWORTH is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PRESTIGE KENILWORTH?

The registered promoter entity is PRESTIGE ESTATES PROJECTS LIMITED, a company as per the filing. Its CIN U07010KA1997PLC022322 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PRESTIGE KENILWORTH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PRESTIGE KENILWORTH?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at PRESTIGE KENILWORTH?

The professionals named in the filing: Architect: TILAK THOMAS; Engineer: ARUN NADIG. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRESTIGE KENILWORTH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRESTIGE KENILWORTH. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRESTIGE KENILWORTH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.