RG-KA-85929 · RERA PRM/KA/RERA/1251/446/PR/180612/001902 · Last updated on RERA Karnataka portal: 25 Nov 2020

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • Separate project account declared
Nov 2021Possession promisedmoved 18 months from the original
2Complaints at RERA Karnatakaon this registration
Jump to the 120 documents Report an error

Premier Inspira Maplewood is a Mixed Development project by M/s Premier Properties in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180612/001902 on 12 Jun 2018. Possession is promised by 17 Nov 2021. The completion date has moved by 18 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NamePremier Inspira Maplewood
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/180612/001902
  • ReraGenie IDRG-KA-85929

Builder

  • NameM/s Premier Properties
  • Entity typePartnership Firm
  • Authorized SignatorySridhar M K
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2018First promiseMay 2020Revised toNov 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on12 Jun 2018
  • Promised completion17 Nov 2021
  • Revised completionRevised to 17 Nov 2021 (originally 18 May 2020)
  • Buildings1 building record
  • Documents filed120 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Premier Inspira Maple wood-----50

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 25 Nov 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 25 Nov 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,907 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.00 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMay 2020 → Feb 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/210518/001902Feb 2021 → Nov 2021

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
CMP/221116/0010343-M/s Premier Properties16/11/2022
01810/2023-M/s Premier Properties09/12/2023

Documents filed120

As listed on the registration, under the names the promoter filed them with; the newest 80 of 120 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180612/001902 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Bank StatementFile: Bank Statement.pdf25 Nov 2020
2/3rd consent merged in one docFile: Consent_compressed.pdf13 Nov 2020
Bank StatementFile: Bank Statement.pdf13 Nov 2020
abstract of sold and unsold unitsFile: Abstract of sold and unsold units.pdf13 Nov 2020
commencement CertificateFile: Commencement Certificate.pdf13 Nov 2020
Affidavit abiding to pay compensationFile: Affidavit.pdf13 Nov 2020
Architect certificateFile: Architect modification.pdf19 Oct 2020
Engineer certificateFile: Engineer modification.pdf19 Oct 2020
ECFile: EC modification.pdf19 Oct 2020
Clarification letter regarding Total AreaFile: Clarification regarding total area.pdf19 Oct 2020
Development detailsFile: Development Details.pdf19 Oct 2020
CertificateFile: registration Certificate.pdf-
Already registered project ongoing detailsFile: Development Details.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Combined Plan-compressed.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Modified Combined Plan-compressed.pdf-
List Of AllotteesFile: List of Allottees.pdf-
List Of ComplaintsFile: List of Complaints.pdf-
Consent LetterFile: Consent letter-merged.pdf-
List Of Pending LitigationsFile: List of Pending Litigation.pdf-
Chartered Accountant CertificateFile: Form 4 V1 Chartered Accountant.pdf-
Notarized AffidavitFile: Affidavit.pdf-
Engineer CertificateFile: Engineer.pdf-
Architect CertificateFile: Architect.pdf-
Structural Engineer Certificate for stability of structureFile: Engineer Certificate.pdf-
Modification of Plan DetailsFile: Temp01708.PDF-
Modification of Plan DetailsFile: Modified Combined Plan.pdf-
Modification of Plan DetailsFile: Commencement & LANCECC.pdf-
Modification of Plan DetailsFile: Commencement & LANCECC.pdf-
Modification of Plan DetailsFile: Sold & Unsold Units.pdf-
Modification of Plan DetailsFile: Sold & Unsold Units.pdf-
Document 1File: SEIA- MOEF Compressed.pdf-
sale DeedFile: Sale Deed .pdf-
kathaFile: Katha for 26-4.pdf-
conversionFile: Conversion Order for 26-4.pdf-
licenceFile: Licence.pdf-
EC latest for 15 yearsFile: EC.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate for work completion-1 .pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate for Completed work.pdf-
CA Certificate for Funds UtilizationFile: Form 4 V1 Chartered Accountant.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate for pending work-.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate for pending work (1).pdf-
CA Certificate for Funds required for Project CompletionFile: Form 4 V1 Chartered Accountant.pdf-
AffidavitFile: Affidavit-Form-ex7_compressed (1).pdf-
Latest Encumbrance CertificateFile: EC_compressed.pdf-
Consent letter from 2/3rd of AllotteesFile: Abha Shukla - Copy.pdf-
Details Of Sold/ Un-sold UnitsFile: Abstract of sold and unsold units.pdf-
Document 1File: KSPCB NOC .jpg-
Document 2File: Consent_compressed.pdf-
Document 3File: Commencement Certificate.pdf-
Document 4File: Bank Statement.pdf-
Document 5File: Affidavit.pdf-
Document 6File: Abstract of sold and unsold units.pdf-
Document 7File: Consent_compressed.pdf-
Document 8File: Consent_compressed.pdf-
Document 9File: Consent_compressed.pdf-
Document (1)-
Temp01708-
Document (1)-
Document (1)-
Sale deed (1)-
Temp01708-
Temp01708-
Document (1)-
Document (1)-
Document (1)-
EC mapalewood-
khata copy-
Document (1)-
mothee deed - Gift deed-
Conversion-
Document (1)-
Document (1)-
Document (1)-
Document (1)-
Document (1)-
Document (1)-
Document (1)-
Document (1)-
Document (1)-
Document (1)-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 18 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Premier Inspira Maplewood on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPremier Inspira MaplewooOther 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: M/s Premier Properties

M/s Premier Properties has 2 registrations on RERA Karnataka, including SLICE OF HEAVEN and Premier Inspira Maplewood. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Premier Inspira Maplewood is delayed beyond 17 Nov 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Premier Inspira Maplewood?

The registered promoter entity is M/s Premier Properties, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Premier Inspira Maplewood?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Premier Inspira Maplewood?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in Premier Inspira Maplewood?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Premier Inspira Maplewood. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Premier Inspira Maplewood to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.