Home / Browse projects / Bengaluru Urban, Karnataka / PRAMODH FORT HOUSE

Registration approved No litigation declared Residential/Group Housing project

PRAMODH FORT HOUSE

By Thipparthi Constructions And Housing Pvt Ltd

RG-KA-89211 · RERA PRM/KA/RERA/1251/472/PR/171225/008347 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
2 of 16Construction stages donefurthest along: Earth work and other leveling..., 95%
19 of 20Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 108 documents Report an error

PRAMODH FORT HOUSE is a Residential/Group Housing project by Thipparthi Constructions And Housing Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/171225/008347 on 17 Dec 2025. Possession is promised by 31 Dec 2027. 1 of the 20 units on this registration are recorded sold or booked, and 2 of 16 construction stages are filed complete.

At a glance

Project

  • NamePRAMODH FORT HOUSE
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
    • 560064
  • Pincode560064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/171225/008347
  • ReraGenie IDRG-KA-89211

Builder

  • NameThipparthi Constructions And Housing Pvt Ltd
  • Entity typeCompany
  • Authorized SignatoryRajasekhar Rao Thipperthy
  • DirectorsRajasekhar Rao Thipperthy, Rajasekhar Rao Thipperthy, Madhukar Rao Thipparthi, Thipparthi Sudhaker Rao
  • Project HeadRajasekhar Rao Thipperthy
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Dec 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed108 files

Current status

5%1 of 20 units booked
32.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRAMODH FORT HOUSE---20020

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 95%.

Building: 47% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work95%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)40%
Retaining wall (All types)70%
RCC or MS Framed structure90%
Masonry Construction90%
Plastering inside , outside & Ceiling50%
Joinery: Doors, Windows, Ventilators etc40%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)30%
Railing and Grill fixing50%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsYes0%
Corridor/LobbiesYes90%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes50%
BasementYes100%
TerraceYes70%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area841 sq m
Named landowners1
LandownerVillageDistrict
PRAMODH S R--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.31 cr
Cost incurredRs 2.38 cr
Spent of the estimate32.5%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 6.00 crRs 2.33 cr
On-site expenditure-Salaries of workersRs 1.15 crRs 3.83 lakh
Payment of feesRs 10.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 5.00 lakhRs 37,803
On-site expenditure-Consultants FeesRs 1.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPAMJULA MOHAN RAO
EngineerRamesh B
Chartered AccountantANJAN REDDY KANDULA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed108

As listed on the registration, under the names the promoter filed them with; the newest 80 of 108 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/171225/008347 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 TCHPL PFH Q2 26-27 CA.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 TCHPL PFH Q2 26-27 Architect.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 TCHPL PFH Q2 26-27 Engineer.pdf15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 TCHPL Pramodh Fort House Q1 2026-27 CA.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 TCHPL Pramodh Fort House Q1 2026-27 Architect.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 TCHPL Pramodh Fort House Q1 2026-27 Engineer.pdf15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 TCHPL Pramodh Fort House Q4 2025-26 CA.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 TCHPL Pramodh Fort House Q4 2025-26 Architect.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 TCHPL Pramodh Fort House Q4 2025-26 Engineer.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 TCHPL Pramodh Fort House Q3 2025-26 CA.pdf31 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 TCHPL Pramodh Fort House Q3 2025-26 Architect.pdf31 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 TCHPL Pramodh Fort House Q3 2025-26 Engineer.pdf31 Jan 2026
Engineer Certificate Form_3File: Engineer Certificate Form_3.pdf16 Dec 2025
Project Area statementFile: Project Area statement.pdf16 Dec 2025
Project EstimationFile: Project Estimation.pdf16 Dec 2025
Structural Safety CertificateFile: Structural Safety Certificate.pdf16 Dec 2025
Drinking Water facilitiesFile: Drinking Water facilities.pdf16 Dec 2025
Master PlanFile: Master Plan.pdf16 Dec 2025
Master Plan2File: Master Plan2.pdf16 Dec 2025
Query ReplyFile: Query Reply.pdf16 Dec 2025
Area Statement_Srirampura EngineerFile: Area Statement_Srirampura Engineer.pdf9 Dec 2025
Building LicenceFile: Building Licence.pdf9 Dec 2025
Clarification for Commencement Certificate-SrirampuraFile: Clarification for Commencement Certificate-Srirampura.pdf9 Dec 2025
STP Declaration and GOKFile: STP Declaration and GOK.pdf9 Dec 2025
Form3 cert by engineerFile: Form3 cert by engineer.pdf9 Dec 2025
Project EstimationFile: Project Estimation.pdf9 Dec 2025
Single Plot layout & Order_SrirampuraFile: Single Plot layout & Order_Srirampura.pdf9 Dec 2025
Structural Stability Certificate with Engineer licenceFile: Structural Stability Certificate with Engineer licence.pdf9 Dec 2025
Survey SketchFile: Survey Sketch.pdf9 Dec 2025
Survey Sketch_SrirampuraFile: Survey Sketch_Srirampura.pdf9 Dec 2025
Village MapFile: Village Map.pdf9 Dec 2025
Approved original PlanFile: Approved original Plan.pdf9 Dec 2025
Engineer Zaki Ahmed LicenseFile: Engineer Zaki Ahmed License.pdf9 Dec 2025
Proforma Agreement for Sale_pramodhFile: Proforma Agreement for Sale_pramodh.pdf9 Dec 2025
RTC, survey 3/4-
Mutation, survey 3/4-
Encumbrance Certificate, survey 3/4-
Conversion/Alienation Order, survey 3/4-
Sale/Title/Gift Deed, survey 3/4-
JDA, survey 3/4-
Khatha, survey 3/4-
Registration CertificateFile: Company Registration-TCAHPL.pdf-
Memorandum of AssociationFile: Memorandum of Association-TCAHPL.pdf-
Article of AssociationFile: Articles of Association-TCAHPL.pdf-
GST CertificateFile: GST Certificate-BLR-TCAHPL.pdf-
Organization StructureFile: Form-32 TCAHPL.pdf-
Certificate issued by CA Form 1File: FORM 1 CA -Pramodh Fort House.pdf-
Certificate issued by Architect Form 2File: Form-2 Arch-Pramodh Fort House.pdf-
Certificate issued by Engineer Form 3File: Form-3 Eng_Pramodh Fort House.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit-Non-Litigation_Srirampura.pdf-
Balance Sheet 2024 - 2025File: TCHPL_FY 2024-25-BALANCE SHEET.pdf-
Balance Sheet 2023 - 2024File: TCHPL-2023-24-BALANCE SHEET.pdf-
Balance Sheet 2022 - 2023File: TCHPL_FY 2022-23-BALANCE SHEET.pdf-
Audited Profit and Loss Statement 2024 - 2025File: TCHPL_FY 2024-25- P&L.pdf-
Audited Profit and Loss Statement 2023 - 2024File: TCHPL-2023-24-P&L.pdf-
Audited Profit and Loss Statement 2022 - 2023File: TCHPL_FY 2022-23-P&L.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR ACK FY 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR ACK FY 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR ACK FY 2022-23.pdf-
Cash Flow Statement 2024 - 2025File: TCHPL_FY 2024-25-CASH FLOW.pdf-
Cash Flow Statement 2023 - 2024File: TCHPL-2023-24-CASH FLOW.pdf-
Auditor's Report 2024 - 2025File: TCHPL_FY 2024-AUDIT REPORT.pdf-
Auditor's Report 2023 - 2024File: TCHPL-2023-24-AUDIT REPORT.pdf-
Auditor's Report 2022 - 2023File: TCHPL_FY 2022-23-AUDIT REPORT.pdf-
CC Clarification-Srirampura-
Approved Building Plan-
BBMP Building Licence-Pramodh Fort House-
Structure Stability Certificate-
Project Specification-Srirampura-
Agreement of Sale Pramodh Fort Gouse-
Allotment letter of PRAMODH FORT HOUSE-
Form B_Srirampura-
Affidavit-Srirampura-
Joint Affidavit from Promoter and Landowner -Srirampura-1-
Legal Opinion Thipparthi Constructions-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
FORT HOUSEFORT HOUSE, KHATA NO 1944/42 SY NO 42 WARD NO 7 AMRUTHAHALLI VILLAGECompleted-No date filed

How this compares with Bengaluru Urban

5%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep PRAMODH FORT HOUSE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPRAMODH FORT HOUSEOther 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 43 registered projects within 2 km.

Builder: Thipparthi Constructions And Housing Pvt Ltd

Thipparthi Constructions And Housing Pvt Ltd has 1 registration on RERA Karnataka, including PRAMODH FORT HOUSE. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if PRAMODH FORT HOUSE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PRAMODH FORT HOUSE?

The registered promoter entity is Thipparthi Constructions And Housing Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PRAMODH FORT HOUSE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRAMODH FORT HOUSE?

The professionals named in the filing: Architect: PAMJULA MOHAN RAO; Engineer: Ramesh B; Chartered Accountant: ANJAN REDDY KANDULA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRAMODH FORT HOUSE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRAMODH FORT HOUSE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRAMODH FORT HOUSE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.