ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / PMAY AHP MUNCIPAL COUNCIL

Registration lapsed No litigation declared Residential / Group Housing project

PMAY AHP MUNCIPAL COUNCIL

By INDAPUR MUNCIPAL COUNCIL

RG-MH-93023 · RERA P52100050165 · Last updated on MahaRERA portal: 17 Mar 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
0 of 77Construction stages doneacross 7 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

PMAY AHP MUNCIPAL COUNCIL is a Residential / Group Housing project by INDAPUR MUNCIPAL COUNCIL in Pune, Maharashtra, registered with MahaRERA as P52100050165 on 21 Mar 2023. Possession was promised by 30 Sep 2025 and is now 13 months past that date.

At a glance

Project

  • NamePMAY AHP MUNCIPAL COUNCIL
  • TypeResidential / Group Housing
  • Location
    • INDAPUR
    • Indapur (M Cl)
    • Pune
    • 413106
  • Pincode413106
  • RERA no.P52100050165
  • ReraGenie IDRG-MH-93023

Builder

  • NameINDAPUR MUNCIPAL COUNCIL
  • Entity typePublic Authority
  • Chief OfficerRAMESH SHANKAR DHAGE

Key dates

13 months past promisethis monthRegisteredMar 2023PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Mar 2023
  • Promised completion30 Sep 2025
  • Revised completionNone
  • Buildings7 building records
  • Documents filed56 files

Current status

17.2%Work done, per cost certificate

Figures as on 17 Mar 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1NA80000
B2NA80000
B3NA80000
B4NA80000
B5NA80000
B6NA80000
SOCIETY OFFICENA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 17 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Excavation, at 0%.

B10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B50%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SOCIETY OFFICE0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed398

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots398
Closed/Covered7
Open Space391
BuildingClosed/CoveredOpen SpaceTotal
B118081
B218081
B316364
B416061
B516061
B614849
SOCIETY OFFICE101

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024
LandownerVillageDistrict
INDAPUR MUNCIPAL COUNCILIndapur (M Cl)Pune

Approvals and building plan

Sanctioning authorityINDAPUR MUNCIPAL COUNCIL
Permissible FSI36000.0
Proposed, not sanctioned19,805 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchINDAPUR DIST PUNE
Estimated costRs 45.94 cr
Cost incurredRs 7.90 cr
Work done17.19%
BuildingWingEstimatedIncurred
B1NARs 7.57 crRs 1.32 cr
B2NARs 7.57 crRs 1.32 cr
B3NARs 7.57 crRs 1.32 cr
B4NARs 7.57 crRs 1.32 cr
B5NARs 7.57 crRs 1.32 cr
B6NARs 7.57 crRs 1.32 cr
SOCIETY OFFICENARs 50.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKewal Mehta
EngineerAmol M Mehta
Chartered AccountantCA Aejazahmed Muhammed Ishaque Jambhai
Chartered AccountantVINI P PICHA
PartnerRole in project
INDAPUR MUNCIPAL COUNCIL-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: 1.pdf17 Mar 2023
Building plan approvalFile: 2.pdf17 Mar 2023
Building plan approvalFile: 3.pdf17 Mar 2023
Building plan approvalFile: 4.pdf17 Mar 2023
Building plan approvalFile: 5.pdf17 Mar 2023
Building plan approvalFile: 6.pdf17 Mar 2023
Building plan approvalFile: 7.pdf17 Mar 2023
Building plan approvalFile: 8.pdf17 Mar 2023
Building plan approvalFile: 9.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 7.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 8.pdf17 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 9.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf17 Mar 2023
Proforma of Agreement for saleFile: MODEL COPY OF AGREEMENT.pdf17 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf17 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK STATEMENT.PDF17 Mar 2023
Layout approvalFile: 1.pdf14 Mar 2023
Layout approvalFile: 2.pdf14 Mar 2023
Layout approvalFile: 3.pdf14 Mar 2023
Layout approvalFile: 4.pdf14 Mar 2023
Layout approvalFile: 5.pdf14 Mar 2023
Layout approvalFile: 5.pdf14 Mar 2023
Layout approvalFile: 7.pdf14 Mar 2023
Layout approvalFile: 8.pdf14 Mar 2023
Layout approvalFile: 9.pdf14 Mar 2023
Building plan approvalFile: CONSTRUCTION PERMISION.pdf14 Mar 2023
PAN CardFile: PAN CARD OF MUNCIPAL COUNCIL.pdf14 Mar 2023
Copy of the legal title reportFile: LEGAT TITLE REPORT.pdf14 Mar 2023
Details of encumbrances concerned to FinanceFile: DECLARATION OF ENCUMBRANCES.pdf14 Mar 2023
Details of encumbrances concerned to LegalFile: DECLARATION OF ENCUMBRANCES.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 1.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 2.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 3.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 4.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 5.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 5.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 7.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 8.pdf14 Mar 2023
Copy of Layout Approval (in case of layout)File: 9.pdf14 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: CONSTRUCTION PERMISION.pdf14 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: CONSTRUCTION PERMISION.pdf14 Mar 2023
Declaration about Commencement CertificateFile: FORMAT D.pdf14 Mar 2023
Declaration in FORM BFile: FORM B.pdf14 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECTS CERTIFICATE.pdf14 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf14 Mar 2023
CERSAI detailsFile: CERSAI REPORT.pdf14 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANIZATION.pdf14 Mar 2023
Proforma of Allotment letterFile: ANNEXURE 1 - MODEL FORM OF ALLOTMENT LETTER.pdf14 Mar 2023
Deviation Report with respect to Allotment letterFile: DEVIATION - ALLOTMENT LETTER.pdf14 Mar 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION - MODEL COPY OF AGREEMENT.pdf14 Mar 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PMAY AHP MUNCIPAL COUNCIL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near INDAPUR13,700+ in Pune

Builder: INDAPUR MUNCIPAL COUNCIL

INDAPUR MUNCIPAL COUNCIL has 1 registration on MahaRERA, including PMAY AHP MUNCIPAL COUNCIL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that PMAY AHP MUNCIPAL COUNCIL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PMAY AHP MUNCIPAL COUNCIL is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PMAY AHP MUNCIPAL COUNCIL?

The registered promoter entity is INDAPUR MUNCIPAL COUNCIL, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PMAY AHP MUNCIPAL COUNCIL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PMAY AHP MUNCIPAL COUNCIL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PMAY AHP MUNCIPAL COUNCIL?

The professionals named in the filing: Architect: Kewal Mehta; Engineer: Amol M Mehta; Chartered Accountant: CA Aejazahmed Muhammed Ishaque Jambhai; Chartered Accountant: VINI P PICHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PMAY AHP MUNCIPAL COUNCIL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PMAY AHP MUNCIPAL COUNCIL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PMAY AHP MUNCIPAL COUNCIL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.