ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / PIONEER SUNBLOSSOM B BLOCK

Registration approved Residential/Group Housing project

PIONEER SUNBLOSSOM B BLOCK

By PIONEER SUNBLOSSOM B BLOCK

RG-KA-53861 · RERA PRM/KA/RERA/1251/308/PR/171215/000713

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Feb 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 36 documents Report an error

PIONEER SUNBLOSSOM B BLOCK is a Residential/Group Housing project by PIONEER SUNBLOSSOM B BLOCK in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/171215/000713 on 15 Dec 2017. Possession is promised by 16 Feb 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NamePIONEER SUNBLOSSOM B BLOCK
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/171215/000713
  • ReraGenie IDRG-KA-53861

Builder

  • NamePIONEER SUNBLOSSOM B BLOCK
  • Entity typePartnership Firm
  • Authorized SignatoryY.HANUMANTHA REDDY
  • OthersY.PAVANI

Key dates

this monthRegisteredDec 2017First promiseMay 2021Revised toFeb 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Dec 2017
  • Promised completion16 Feb 2022
  • Revised completionRevised to 16 Feb 2022 (originally 16 May 2021)
  • Buildings1 building record
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PIONEER SUNBLOSSOM B Block---76076

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,895 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSECANT ARCHITECTS LLP
EngineerP. RAMAKRISHNA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMay 2021 → Feb 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed36

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/171215/000713 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
E katha-
pioneer sunblossom B Block sanction plan-
pioneer sunblossom B Block sanction plan-
Sale deed copy-
Agreement of sale -
rtc FY2015-2016-
pioneer sunblossom B Block sanction plan-
pioneer sunblossom B Block sanction plan-
ALLOTMENT LETTER - Copy-
Pioneer_Sun_Blossom Broucher-
BDA Licenese-
Project Specification-
EC-
E katha-
MUTATION-
kSPCB-
Balance Sheet 2015 - 2016File: yhr FY2015-2016.pdf-
Balance Sheet 2014 - 2015File: FY2014-2015 IT YHR.pdf-
Balance Sheet 2013 - 2014File: FY2013-2014 IT YHR.pdf-
Audited Profit and Loss Statement 2015 - 2016File: yhr FY2015-2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: FY2014-2015 IT YHR.pdf-
Audited Profit and Loss Statement 2013 - 2014File: FY2013-2014 IT YHR.pdf-
Director's Report 2015 - 2016File: yhr FY2015-2016.pdf-
Director's Report 2014 - 2015File: FY2014-2015 IT YHR.pdf-
Director's Report 2013 - 2014File: FY2013-2014 IT YHR.pdf-
Cash Flow Statement 2015 - 2016File: yhr FY2015-2016.pdf-
Cash Flow Statement 2014 - 2015File: FY2014-2015 IT YHR.pdf-
Auditor's Report 2015 - 2016File: yhr FY2015-2016.pdf-
Auditor's Report 2014 - 2015File: FY2014-2015 IT YHR.pdf-
Auditor's Report 2013 - 2014File: FY2013-2014 IT YHR.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: yhr FY2015-2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: FY2014-2015 IT YHR.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: FY2013-2014 IT YHR.pdf-
FROM B-
Prospectus/BrochureFile: Pioneer_Sun_Blossom Broucher.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_171215_000713.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep PIONEER SUNBLOSSOM B BLOCK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: PIONEER SUNBLOSSOM B BLOCK

PIONEER SUNBLOSSOM B BLOCK has 1 registration on RERA Karnataka, including PIONEER SUNBLOSSOM B BLOCK. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if PIONEER SUNBLOSSOM B BLOCK is delayed beyond 16 Feb 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PIONEER SUNBLOSSOM B BLOCK?

The registered promoter entity is PIONEER SUNBLOSSOM B BLOCK, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PIONEER SUNBLOSSOM B BLOCK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PIONEER SUNBLOSSOM B BLOCK?

The professionals named in the filing: Architect: SECANT ARCHITECTS LLP; Engineer: P. RAMAKRISHNA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PIONEER SUNBLOSSOM B BLOCK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PIONEER SUNBLOSSOM B BLOCK. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PIONEER SUNBLOSSOM B BLOCK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.