Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Peninsula Prakruthi Phase - 2 is a Residential/Group Housing project by Peninsula Infra Developments Pvt. Ltd., in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/171118/001135 on 18 Nov 2017. Possession is promised by 26 Mar 2021. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NamePeninsula Prakruthi Phase - 2
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/308/PR/171118/001135
- ReraGenie IDRG-KA-64799
Builder
- NamePeninsula Infra Developments Pvt. Ltd.,
- Entity typeCompany
- CINU45201KA2009PTC051504
- Authorized SignatoryK N Raghu
- Other registrations4 more →
- No longer live1 withdrawn or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on18 Nov 2017
- Promised completion26 Mar 2021
- Revised completionRevised to 26 Mar 2021 (originally 26 Jun 2020)
- Buildings61 building records
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Villa No 01 | - | - | - | 1 | 0 | 1 |
| Villa No 02 | - | - | - | 1 | 0 | 1 |
| Villa No 03 | - | - | - | 1 | 0 | 1 |
| Villa No 04 | - | - | - | 1 | 0 | 1 |
| Villa No 05 | - | - | - | 1 | 0 | 1 |
| Villa No 06 | - | - | - | 1 | 0 | 1 |
| Villa No 07 | - | - | - | 1 | 0 | 1 |
| Villa No 08 | - | - | - | 1 | 0 | 1 |
| Villa No 09 | - | - | - | 1 | 0 | 1 |
| Villa No 10 | - | - | - | 1 | 0 | 1 |
| Villa No 11 | - | - | - | 1 | 0 | 1 |
| Villa No 12 | - | - | - | 1 | 0 | 1 |
| Villa No 13 | - | - | - | 1 | 0 | 1 |
| Villa No 14 | - | - | - | 1 | 0 | 1 |
| Villa No 15 | - | - | - | 1 | 0 | 1 |
| Villa No 16 | - | - | - | 1 | 0 | 1 |
| Villa No 17 | - | - | - | 1 | 0 | 1 |
| Villa No 18 | - | - | - | 1 | 0 | 1 |
| Villa No 19 | - | - | - | 1 | 0 | 1 |
| Villa No 20 | - | - | - | 1 | 0 | 1 |
| Villa No 21 | - | - | - | 1 | 0 | 1 |
| Villa No 22 | - | - | - | 1 | 0 | 1 |
| Villa No 23 | - | - | - | 1 | 0 | 1 |
| Villa No 24 | - | - | - | 1 | 0 | 1 |
| Villa No 25 | - | - | - | 1 | 0 | 1 |
| Villa No 26 | - | - | - | 1 | 0 | 1 |
| Villa No 27 | - | - | - | 1 | 0 | 1 |
| Villa No 28 | - | - | - | 1 | 0 | 1 |
| Villa No 29 | - | - | - | 1 | 0 | 1 |
| Villa No 30 | - | - | - | 1 | 0 | 1 |
| Villa No 31 | - | - | - | 1 | 0 | 1 |
| Villa No 32 | - | - | - | 1 | 0 | 1 |
| Villa No 33 | - | - | - | 1 | 0 | 1 |
| Villa No 34 | - | - | - | 1 | 0 | 1 |
| Villa No 35 | - | - | - | 1 | 0 | 1 |
| Villa No 36 | - | - | - | 1 | 0 | 1 |
| Villa No 37 | - | - | - | 1 | 0 | 1 |
| Villa No 38 | - | - | - | 1 | 0 | 1 |
| Villa No 39 | - | - | - | 1 | 0 | 1 |
| Villa No 40 | - | - | - | 1 | 0 | 1 |
| Villa No 41 | - | - | - | 1 | 0 | 1 |
| Villa No 42 | - | - | - | 1 | 0 | 1 |
| Villa No 43 | - | - | - | 1 | 0 | 1 |
| Villa No 44 | - | - | - | 1 | 0 | 1 |
| Villa No 45 | - | - | - | 1 | 0 | 1 |
| Villa No 46 | - | - | - | 1 | 0 | 1 |
| Villa No 47 | - | - | - | 1 | 0 | 1 |
| Villa No 48 | - | - | - | 1 | 0 | 1 |
| Villa No 49 | - | - | - | 1 | 0 | 1 |
| Villa No 50 | - | - | - | 1 | 0 | 1 |
| Villa No 51 | - | - | - | 1 | 0 | 1 |
| Villa No 52 | - | - | - | 1 | 0 | 1 |
| Villa No 53 | - | - | - | 1 | 0 | 1 |
| Villa No 54 | - | - | - | 1 | 0 | 1 |
| Villa No 55 | - | - | - | 1 | 0 | 1 |
| Villa No 56 | - | - | - | 1 | 0 | 1 |
| Villa No 57 | - | - | - | 1 | 0 | 1 |
| Villa No 58 | - | - | - | 1 | 0 | 1 |
| Villa No 59 | - | - | - | 1 | 0 | 1 |
| Villa No 60 | - | - | - | 1 | 0 | 1 |
| Villa No 61 | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | No | Not applicable |
| Staircases and Lift lobbies, corridor,lobbies, corridor | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed47
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/171118/001135 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Certificate of In corporation.pdf | - |
| Prakruthi Phase II STRR Release letter | - |
| Prakruthi Phase - 2 layout plan | - |
| Prakruthi Phase - 2 layout plan | - |
| Prakruthi Phase - Sale Deed | - |
| Prakruthi Phase - Sale Agreement | - |
| Prakruthi phase - 2 land document | - |
| Prakruthi Phase - 2 layout plan | - |
| Prakruthi Phase - 2 layout plan | - |
| BOOKING FORM FORMAT | - |
| Prakruthi-II Brochure New | - |
| Prakruthi Phase - 2 NOC | - |
| Prakruthi Phase - 2 Specification | - |
| Prakruthi Phase - 2 EC | - |
| kathas | - |
| JDA | - |
| PRAKRUTHI PHASE 2 CONVERSION ORDERS | - |
| KSPCB-Prakruthi | - |
| Balance Sheet 2015 - 2016File: Balance Sheet FY 2015-16.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet FY 2014-15.pdf | - |
| Balance Sheet 2013 - 2014File: Balance Sheet FY 2013-14.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Profit loss Statemnt FY 15-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Profit loss Statemnt FY 14-15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: Profit loss Statemnt FY 13-14.pdf | - |
| Director's Report 2015 - 2016File: Director_report FY 2015-16.pdf | - |
| Director's Report 2014 - 2015File: Director_report FY 2014-15.pdf | - |
| Director's Report 2013 - 2014File: Director_report FY 2013-14.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow Statemnt FY 15-16.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash Flow Statemnt FY 14-15.pdf | - |
| Auditor's Report 2015 - 2016File: Auditirs Report FY 15-16.pdf | - |
| Auditor's Report 2014 - 2015File: Auditirs Report FY 14-15.pdf | - |
| Auditor's Report 2013 - 2014File: Auditirs Report FY 13-14.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR ACK FY 15-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR ACK FY 14-15.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR ACK FY 13-14.pdf | - |
| Declartation (2) | - |
| Prospectus/BrochureFile: Prakruti Phase 2 Brochure.pdf | - |
| Advertisement Copy 1File: Advertisement - Prakruthi Phase II.jpeg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_171118_001135.xlsx | - |
| Occupancy CertificateFile: Release Order.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Architect certificate for Completion .pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: CA Certificate for Completion.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Completion Affidavit.pdf | - |
| Engineer CertificateFile: Eng Certificate for Completion .pdf | - |
| Sale AgreementFile: Sale Agreement.pdf | - |
| Sale DeedFile: Sale Deed.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Peninsula Prakruthi Phase - 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Peninsula Infra Developments Pvt. Ltd.,
Peninsula Infra Developments Pvt. Ltd., has 5 registrations on RERA Karnataka, including Peninsula Solitaire and Peninsula Prakruthi Phase - 2. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Peninsula Prakruthi Phase - 2 is delayed beyond 26 Mar 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Peninsula Prakruthi Phase - 2?
The registered promoter entity is Peninsula Infra Developments Pvt. Ltd.,, a company as per the filing. Its CIN U45201KA2009PTC051504 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Peninsula Prakruthi Phase - 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Peninsula Prakruthi Phase - 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback