Home / Browse projects / Mumbai Suburban, Maharashtra / PEAK 25

Registration lapsed No litigation declared Residential / Group Housing project

PEAK 25

By VLKRISHNAPINGAKSHA DEVELOPERS LLP

RG-MH-62808 · RERA P51800032526 · Last updated on MahaRERA portal: 21 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
24 of 109Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

PEAK 25 is a Residential / Group Housing project by VLKRISHNAPINGAKSHA DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032526 on 10 Jan 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 85 of the 109 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NamePEAK 25
  • TypeResidential / Group Housing
  • Location
    • KANNAMWAR NAGAR 1
    • VIKHROLI
    • Kurla
    • Mumbai Suburban
    • 400083
  • Pincode400083
  • RERA no.P51800032526
  • ReraGenie IDRG-MH-62808

Builder

  • NameVLKRISHNAPINGAKSHA DEVELOPERS LLP
  • Entity typePartnership
  • PartnersADITYA RAMDAS SANGLE, RAMDAS MARUTI SANGLE, AMIT PANGAM, ANITA RAMDAS SANGLE

Key dates

10 months past promisethis monthRegisteredJan 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Jan 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed67 files

Current status

78%85 of 109 units booked

Figures as on 21 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Peak 25NA26261090109

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Peak 25: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed52

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots52
Closed/Covered52

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area791 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Feb 2026
LandownerVillageDistrict
krishnapingaksha Chs LtdKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityBuilding Permission Cell, Greater Mumbai / MHADA
Permissible FSI6500.0
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVikhroli

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKishor Lotlikar
EngineerAjay Mahale
Chartered AccountantNarendra Kadav
Chartered AccountantUtsav Shah
PartnerRole in project
VLKRISHNAPINGAKSHA DEVELOPERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2021-2022)File: Form 2A FY 2021-2022.pdf21 Feb 2026
Form 2A (FY 2022-2023)File: Form 2A FY 2022-2023.pdf21 Feb 2026
Form 2A (FY 2023-2024)File: Form 2A F Y 2023-2024.pdf21 Feb 2026
Form 5 (FY 2021-2022)File: Signed Form 5 - March 22.pdf21 Feb 2026
Form 1File: Form 1 Architechs Certificate Bldg no 205 June 2023 Q1.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 June 2023 Q1.pdf31 Dec 2025
Form 3File: Form 3 C A Certificate Peak 25 Bldg no 205 June 2023 Q1.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory June 2023 Q1.pdf31 Dec 2025
Form 1File: Form 1 Architechs Certificate Bldg no 205 Sept 2023 Q2.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 Sept 2023 Q2.pdf31 Dec 2025
Form 3File: Form 3 C A Certificate Peak 25 Bldg no 205 Sept 2023 Q2.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory Sept 2023 Q2.pdf31 Dec 2025
Form 1File: Form 1 Architechs Certificate Bldg no 205 Dec 2023 Q3.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 Dec 2023 Q3.pdf31 Dec 2025
Form 3File: Form 3 C A Certificate Peak 25 Bldg no 205 Dec 2023 Q3.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory Dec 2023 Q3.pdf31 Dec 2025
Form 1File: Form 1 Architechs Certificate Bldg no 205 March 2024 Q4.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 March 2024 Q4.pdf31 Dec 2025
Form 3File: Form 3 C A Certificate Peak 25 Bldg no 205 March 2024 Q4.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory March 2024 Q4.pdf31 Dec 2025
Form 1File: Form 1 Architechs Certificate Bldg no 205 June 2024 Q1.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 June 2024 Q1.pdf31 Dec 2025
Form 3File: Form 3 C A Certificate Peak 25 Bldg no 205 June 2024 Q1.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory June 2024 Q1.pdf31 Dec 2025
Form 1File: Form 1 Architechs Certificate Bldg no 205 March 2023 Q4.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 March 2023 Q4.pdf31 Dec 2025
Form 3File: Form 3 C A Certificate Peak 25 Bldg no 205 March 2023 Q4.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory March 2023 Q4.pdf31 Dec 2025
Form 1File: Form 1 Architechs Certificate Bldg no 205 Dec 2022 Q3.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 Dec 2022 Q3.pdf31 Dec 2025
Form 3File: Form 3 C A Certificate Peak 25 Bldg no 205 Dec 2022 Q3.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory Dec 2002 Q3.pdf31 Dec 2025
Form 1File: Form 1 Architechs Certificate Bldg no 205 Sept 2022 Q2.pdf31 Dec 2025
Form 2File: Form 2 Engineers Certificate Peak 25 Bldg no 205 Sept 2022 Q2.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold unsold inventory Sept 2022 Q2.pdf31 Dec 2025
Form 3File: Form 3 peak 25 sep 2022.pdf31 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March-24.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Peak 25 Mar 22-Final.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Peak 25 Jun 22-Final.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Peak 25 Sep 22-Final.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Peak 25 Dec 22-Final.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Signed.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest-Krishnapingaksha_Aditya Sangle.pdf11 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest-Krishnapingaksha_Aditya Sangle.pdf11 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest-Krishnapingaksha_Anita Sangle.pdf11 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest-Krishnapingaksha_Ramdas Maruti Sangle.pdf11 Apr 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance-Legal-Krishnapingaksha.pdf28 Mar 2023
Details of encumbrances concerned to LegalFile: No Encumbrance-Legal-Krishnapingaksha.pdf28 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for seperate bank account-Krishnapingaksha.pdf18 Mar 2023
Proforma of Agreement for saleFile: 2 Proforma of Agreement of Sale.pdf21 Feb 2023
Copy of the legal title reportFile: Building no 205 Title report.pdf24 Dec 2021
CERSAI detailsFile: Cersai (2).pdf24 Dec 2021
Proforma of Allotment letterFile: Agreement for sale.pdf18 Dec 2021
Proforma of Allotment letterFile: Agreement for sale.pdf11 Dec 2021
Details of encumbrancesFile: Encumbrances.pdf8 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate of Bldg no-205 Kannamwar Nagar Dt-07-12-2021 (1)_11zon.pdf8 Dec 2021
Declaration about Commencement CertificateFile: declaration for cc.pdf8 Dec 2021
Declaration in FORM BFile: FORM B By devloper.pdf8 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Peak 25.pdf8 Dec 2021
Layout approvalFile: Zero FSI IOA bldg no 205 KN dt 27-09-2021_11zon.pdf3 Dec 2021
Building plan approvalFile: ZERO FSI PLAN-205.PDF3 Dec 2021
PAN CardFile: vl krishnapingakhsa PAN.pdf3 Dec 2021
Copy of Layout Approval (in case of layout)File: Zero FSI IOA bldg no 205 KN dt 27-09-2021_11zon.pdf3 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: ZERO FSI PLAN-205.PDF3 Dec 2021

How this compares with Mumbai Suburban

78%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PEAK 25 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIKHROLI6,700+ in Mumbai Suburban

Builder: VLKRISHNAPINGAKSHA DEVELOPERS LLP

VLKRISHNAPINGAKSHA DEVELOPERS LLP has 1 registration on MahaRERA, including PEAK 25. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that PEAK 25 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PEAK 25 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PEAK 25?

The registered promoter entity is VLKRISHNAPINGAKSHA DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PEAK 25?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PEAK 25?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PEAK 25?

The professionals named in the filing: Architect: Kishor Lotlikar; Engineer: Ajay Mahale; Chartered Accountant: Narendra Kadav; Chartered Accountant: Utsav Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PEAK 25?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PEAK 25. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PEAK 25 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.