Home / Browse projects / Bengaluru Urban, Karnataka / PAVANI MIRABILIA PHASE III

Registration approved No litigation declared Residential/Group Housing project

PAVANI MIRABILIA PHASE III

By Sai Sravanthi Infra Projects Pvt Ltd

RG-KA-00866 · RERA PRM/KA/RERA/1251/446/PR/240626/008750 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2031Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 75%
239 of 239Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 114 documents Report an error

PAVANI MIRABILIA PHASE III is a Residential/Group Housing project by Sai Sravanthi Infra Projects Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/240626/008750 on 24 Jun 2026. Possession is promised by 3 Mar 2031. 0 of the 239 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NamePAVANI MIRABILIA PHASE III
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 546004
  • Pincode546004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/240626/008750
  • ReraGenie IDRG-KA-00866

Builder

  • NameSai Sravanthi Infra Projects Pvt Ltd
  • Entity typeCompany
  • CINU45203TG2008PTC060151
  • GSTIN29AAPCS0464C1Z9
  • Authorized SignatoryP V RAGHAVA RAO
  • Managing DirectorP V RAGHAVA RAO
  • DirectorsP V RAGHAVA RAO, P PAVANI, D PAVANKUMAR
  • Project HeadRamesh Reddy K
  • Other registrations3 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2026PromisedMar 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Jun 2026
  • Promised completion3 Mar 2031
  • Revised completionNone
  • Buildings1 building record
  • Documents filed114 files

Current status

0%0 of 239 units booked
1.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER F---2390239

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 75%.

Building: 8% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work75%
Foundation footing work60%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,228 sq m
Named landowners2
LandownerVillageDistrict
SRAVYA SARVEPALLI--
sirisha sarvepalli--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 157.31 cr
Cost incurredRs 1.69 cr
Spent of the estimate1.08%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 118.94 crRs 1.55 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 27.00 cr-
On-site expenditure-Consultants FeesRs 6.61 crRs 7.39 lakh
On-site expenditure-Salaries of workersRs 4.76 crRs 7.39 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSNIGDHA DASH
EngineerRamesh B
Chartered AccountantRAMAKIRHNA REDDY ANIMIREDDY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed114

As listed on the registration, under the names the promoter filed them with; the newest 80 of 114 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/240626/008750 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA CERTIFICATE PAVANI MIRABILIA III.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCHITECT CERTIFICATE PAVANI MIRABILIA III.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGINEER CERTIFICATE PAVANI MIRABILIA III.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 1- CA CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ARCHITECT CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 3 ENGINEER CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Once again informed to Kindly upload the AFS with the following corrections earnest money/booking amFile: PROFORMA AGREEMENT FOR SALE 09062026.pdf9 Jun 2026
E khata in the name o0f owners issued by lacal bodyFile: E KATHA - SIRISHA & SRAVYA.pdf2 Jun 2026
The updated area details in the project details page do not match with the approved plan.Once againFile: COVERING LETTER FOR AREA STATEMENT PHASE WISE.pdf2 Jun 2026
Once again informed to kindly upload the amenities declaration.File: COVERING LETTER FOR AMENITIES AND COMMON AREA DETAILS.pdf2 Jun 2026
Once again informed to kindly upload the engineer certificate duly signed by engineer whose having vFile: FORM 3 ENGINEER CERTIFICATE.pdf2 Jun 2026
Once again informed to kindly upload elaborated structural stability certificate clearly stating theFile: STRUCTURAL STABILITY CERTIFICATE1.pdf2 Jun 2026
In the uploaded affidavits,you have not mentioned about responsibilities and liabilities of the builFile: AFFIDAVIT FOR NOC.pdf2 Jun 2026
Once again informed to kindly upload brief project estimation with licenced engineer signature.File: PROJECT_ESTIM BY ENGINEER.pdf2 Jun 2026
Once again informed to kindly upload the STP drawing certified by the Engineer as per the guidelinesFile: STP DRAWING CERTIFIED BY ENGINEER.pdf2 Jun 2026
Once again informed to kindly upload the Land cost calculation sheet as per the guidance value(SelfFile: COVERING LETTER FOR LAND COST WITH GUIDELINE VALUE.pdf2 Jun 2026
Once again informed to kindly clarify the main source of water supply to the project along with theFile: COVERING LETTER FOR WATER SOURCES.pdf2 Jun 2026
Once again informed to kindly upload AFS as per RERA proforma,some of the clauses are not as per RFile: PROFORMA AGREEMENT FOR SALE.pdf2 Jun 2026
Once again informed to kindly upload Proforma Allotment letter as per the standard prescribed formatFile: PROFORMA ALLOTMENT LETTER.pdf2 Jun 2026
1.Upload chartered accountant certificate (CA) in prescribed format form -01. ( with details of 3 baFile: FORM 1- CA CERTIFICATE.pdf18 May 2026
2. Upload the bank affidavit in the prescribed format documents.( Please upload 3 bank accounts as pFile: BANK ACCOUNT AFFIDAVIT.pdf18 May 2026
3. There is revenue from sales/ operation why it is not considered for section 3(1) violation of theFile: LETTER FOR SOURCE OF FUNDS.pdf18 May 2026
4.Upload the Bank 100%, 70%, and 30% account pass sheets or statements, the bank account name shouldFile: HDFC BANK PASS SHEET & LETTER.jpeg18 May 2026
5. What are all the sources of funds to complete the project? With supporting documents. Hence notFile: LETTER FOR SOURCE OF FUNDS.pdf18 May 2026
Title deed showing flow of title to the current ownersFile: SALE DEED - SY 21-3.pdf18 May 2026
E khata in the name o0f owners issued by lacal bodyFile: E KATHA.pdf18 May 2026
non litigation affidavit in correct formatFile: AFFIDAVIT 2.PDF18 May 2026
EC upto dateFile: EC.pdf18 May 2026
1)Single Plot layout/Development plan Approved by the competent authority (Original and clearly visiFile: DEVELOPMENT PLAN.pdf18 May 2026
2)Single Plot layout/Development plan order Approved by the competent authority(Original and clearlFile: DEVELOPMENT PLAN.pdf18 May 2026
3)Building License from Local Authority Original Copy.File: BUILDING LICENSE LETTER MODIFIED.pdf18 May 2026
4)ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR.PDF18 May 2026
7)Demarcation of proposed land in Approved Master plan Certified by the competent authority.File: CDP PLAN.pdf18 May 2026
8)Demarcation of proposed land in original Village map certified by the competent authorityFile: VILLAGE MAP.pdf18 May 2026
9)Approval/NOC under section 14 of the KTCP Act from competent Authority.File: NOC AFFIDAVIT.pdf18 May 2026
1)Kindly upload approved plan.File: SITE PLAN.pdf18 May 2026
1)Kindly upload approved plan. 2)1)Project address entered in project details page is not as per appFile: LETTER FOR PROJECT ADDRESS.pdf18 May 2026
11)Kindly upload elaborated structural stability certificate clearly stating the number of floors coFile: Form3 Pavani Mirabilia phase 3.pdf18 May 2026
13)Kindly upload Proforma Allotment letter as per the standard prescribed format available in RERAFile: ALLOTMENT LETTER AND BOOKING FORM.pdf18 May 2026
14)Uploaded BESCO NOC validity is expired,kindly upload the renewed one.File: NOC AFFIDAVIT.pdf18 May 2026
15)Kindly upload BWSSB NOC along with fee paid receipt.File: NOC AFFIDAVIT.pdf18 May 2026
16)Kindly upload renewed SEIAA NOC.File: NOC AFFIDAVIT.pdf18 May 2026
17)Kindly upload brief project estimation with licenced engineer signature.File: Form3 Pavani Mirabilia phase 3.pdf18 May 2026
18)Kindly upload the STP drawing certified by the Engineer as per the guidelines.File: STP DRAWING.pdf18 May 2026
19)Kindly upload the Land cost calculation sheet as per the guidance value(Self-attested copy) alongFile: GUIDE LINE VALUE SEGEHAALI.pdf18 May 2026
6)Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: GROUND AND FIRST FLOOR PLAN.pdf18 May 2026
6)Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: SECTION PLAN.pdf18 May 2026
6)Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: TYPICAL 2ND TO 19TH & TERRANCE FLOOR PLAN.pdf18 May 2026
6)Upload all original sanctioned drawings, floor plan, sectional drawings and elevations.File: ELEVATION PLAN.pdf18 May 2026
Proforma Sale AgreementFile: PROFORMA SALE AGREEMENT.pdf18 May 2026
RTC, survey 21/3-
Mutation, survey 21/3-
Encumbrance Certificate, survey 21/3-
Conversion/Alienation Order, survey 21/3-
JDA, survey 21/3-
Khatha, survey 21/3-
Registration CertificateFile: SSIPPL - COI.pdf-
Memorandum of AssociationFile: SSIPPL-MOA.pdf-
Article of AssociationFile: SSIPL-AOA.pdf-
GST CertificateFile: SAI SRAVANTHI GST REGN CERT - BLR.pdf-
Organization StructureFile: SSIPPL - COI.pdf-
Certificate issued by CA Form 1File: FORM 1- CA CERTIFICATE.pdf-
Certificate issued by Architect Form 2File: ARCHITECT CERTIFICATE.pdf-
Certificate issued by Engineer Form 3File: Form3 Pavani Mirabilia phase 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: AFFIDAVIT 2.PDF-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Pavani DivinePavani Divine , SR PalyaCompleted-No date filed

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep PAVANI MIRABILIA PHASE III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPAVANI MIRABILIA PHASE IOther 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 30 registered projects within 2 km.

Builder: Sai Sravanthi Infra Projects Pvt Ltd

Sai Sravanthi Infra Projects Pvt Ltd has 4 registrations on RERA Karnataka, including PAVANI MIRABILIA PHASE I and Pavani Divine. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if PAVANI MIRABILIA PHASE III is delayed beyond 3 Mar 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of PAVANI MIRABILIA PHASE III?

The registered promoter entity is Sai Sravanthi Infra Projects Pvt Ltd, a company as per the filing. Its CIN U45203TG2008PTC060151 and GSTIN 29AAPCS0464C1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in PAVANI MIRABILIA PHASE III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PAVANI MIRABILIA PHASE III?

The professionals named in the filing: Architect: SNIGDHA DASH; Engineer: Ramesh B; Chartered Accountant: RAMAKIRHNA REDDY ANIMIREDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PAVANI MIRABILIA PHASE III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PAVANI MIRABILIA PHASE III. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PAVANI MIRABILIA PHASE III to a free account