Home / Browse projects / Bengaluru Urban, Karnataka / Parkwest - Sequoia - Tower 11

Registration approved No litigation declared Residential/Group Housing project

Parkwest - Sequoia - Tower 11

By Relationship Properties Private Limited

RG-KA-61771 · RERA PRM/KA/RERA/1251/310/PR/220124/006569 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Feb 2029Possession promisedno revision filed
2 of 16Construction stages donefurthest along: Upto Plinth Level, 60%
2 of 182Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 121 documents Report an error

Parkwest - Sequoia - Tower 11 is a Residential/Group Housing project by Relationship Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/220124/006569 on 22 Jan 2024. Possession is promised by 27 Feb 2029. 180 of the 182 units on this registration are recorded sold or booked, and 2 of 16 construction stages are filed complete.

At a glance

Project

  • NameParkwest - Sequoia - Tower 11
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560023
  • Pincode560023
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/220124/006569
  • ReraGenie IDRG-KA-61771

Builder

  • NameRelationship Properties Private Limited
  • Entity typeCompany
  • CINU45200MH2008PTC178830
  • GSTIN29AADCR8947D1Z0
  • Authorized SignatoryAnand Rao
  • CeoVenkatesan Gopalakrishnan
  • DirectorsVenkatesan Gopalakrishnan, MONISH KRISHNA, SUMIT SAPRU, MANISH SWAROOP
  • Project HeadAnand Rao
  • Other registrations10 more →
  • Declared earlier projects9 →

Key dates

this monthRegisteredJan 2024PromisedFeb 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Jan 2024
  • Promised completion27 Feb 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed121 files

Current status

99%180 of 182 units booked
33.6%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Parkwest - Sequoia - Tower 11---1820182

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 16 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 60%.

Building: 21% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level60%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure44%
Masonry Construction29%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes40%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes40%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes15%
LiftsYes15%
Corridor/LobbiesYes15%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes90%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,320 sq m
Named landowners2
LandownerVillageDistrict
ETA Karnataka Estates Limited--
ETA Star Infopark--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 225.27 cr
Cost incurredRs 75.62 cr
Spent of the estimate33.57%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 158.84 crRs 60.15 cr
Payment of taxesRs 33.43 cr-
On-site expenditure-Site OverheadRs 24.30 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 6.15 cr-
On-site expenditure-Consultants FeesRs 2.56 crRs 15.47 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPAUL RAVI JOHN
EngineerSANJIV VASUDEO AUNDHE
Chartered AccountantBhavesh R Nagda

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed121

As listed on the registration, under the names the promoter filed them with; the newest 80 of 121 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/220124/006569 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 T11 Sequioa Q2 26-27.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 T11 Sequioa Q2 26-27.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 T11 Sequioa Q2 26-27.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 T11 Sequioa Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 T11 Sequioa Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 T11 Sequioa Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 T11 Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 T11 Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6-T11 Q4 FY2526.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 T11 Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 T11 Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 T11 Q3 25-26.pdf15 Jan 2026
Common Area and Amenities DetailsFile: 1 Common Area and Amenities Details.pdf18 Jan 2024
Charted Engineer Self-attested copyFile: 2 Charted Engineer Self-attested copy.pdf18 Jan 2024
BWSSB NOC Self-attestedFile: 3 BWSSB NOC Self-attested.pdf18 Jan 2024
BESCOM NOC with substation orderFile: 4 BESCOM NOC with substation order.pdf18 Jan 2024
Clarification on Validity of BESCOM and BWSSB NOCFile: 5 Clarification on Validity - Nocs.pdf18 Jan 2024
Guidelines ValueFile: 6 Guidelines Value.pdf18 Jan 2024
ParkWest - T 11 - Sequoia - Proforma Sale AgreementFile: 7 ParkWest - T 11 - Sequoia - Proforma Sale Agreement.pdf18 Jan 2024
Proforma Allotment Letter - T 11 - RERA FormatFile: 8 Proforma Allotment Letter - T 11 - RERA Format.pdf18 Jan 2024
Registration CertificateFile: Incorporation Certificate.pdf-
Organization StructureFile: Organisation structure.xlsx-
Certificate issued by CA Form 1File: Form 1 - T11 New Registration.pdf-
Certificate issued by Architect Form 2File: FORM 2 ARCHITECT TOWER-11 SEQUOIA.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer TOWER 11 SEQUOIA.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for Non-Litigation Details- With JDA.pdf-
Certificate from Chartered AccountFile: Form 1 - T11 New Registration .pdf-
Balance Sheet 2022 - 2023File: RPPL FINANCIALS 22-23.pdf-
Balance Sheet 2021 - 2022File: RPPL Full Set Financials - March 2022.pdf-
Balance Sheet 2020 - 2021File: Financial Statement 2020-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: RPPL FINANCIALS 22-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: RPPL Full Set Financials - March 2022.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Financial Statement 2020-21.pdf-
Director's Report 2022 - 2023File: RPPL FINANCIALS 22-23.pdf-
Director's Report 2021 - 2022File: RPPL Full Set Financials - March 2022.pdf-
Director's Report 2020 - 2021File: Financial Statement 2020-21.pdf-
Cash Flow Statement 2022 - 2023File: RPPL FINANCIALS 22-23.pdf-
Cash Flow Statement 2021 - 2022File: RPPL Full Set Financials - March 2022.pdf-
Auditor's Report 2022 - 2023File: RPPL ANNUAL AUDIT REPORT 22-23.pdf-
Auditor's Report 2021 - 2022File: RPPL Full Set Audit Report - March 2022.pdf-
Auditor's Report 2020 - 2021File: Auditor Report 2020-21.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: RPPL ITR Ackn FY 22-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: RPPL Form ITR 6 AY 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR Ack AY 2021-22.pdf-
BBMP License-
Bescom Noc dated 24-09-2015-
BWSSB NOC - dated 270310-
1 BBMP Approved Plan-
BBMP License-
BDA - DP dated 11032020-
Project Specifications-
Project Specifications-
Site Plan BBMP-
TOWER-11 STABILITY CERTIFICATE-
Legal Opinion-
JDA GPA AOS-
Title Deed-
ParkWest - T 11 - Sequoia - Proforma Sale Agreement-
Parkwest Application Form (Allotment letter) - T - 11-
RERA FORM B-
Notarized Affidavit for 3(1) Voilation-
Affidavit cum Declaration-notarized-
Bescom Noc dated 24-09-2015-

How this compares with Bengaluru Urban

99%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Parkwest - Sequoia - Tower 11 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmParkwest - Sequoia - TowOther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: Relationship Properties Private Limited

Relationship Properties Private Limited has 11 registrations on RERA Karnataka, including Parkwest - Olive - Tower 1 and Parkwest - Maple - Tower 4. Its filings declare 9 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Parkwest - Sequoia - Tower 11 is delayed beyond 27 Feb 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Parkwest - Sequoia - Tower 11?

The registered promoter entity is Relationship Properties Private Limited, a company as per the filing. Its CIN U45200MH2008PTC178830 and GSTIN 29AADCR8947D1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Parkwest - Sequoia - Tower 11?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Parkwest - Sequoia - Tower 11?

The professionals named in the filing: Architect: PAUL RAVI JOHN; Engineer: SANJIV VASUDEO AUNDHE; Chartered Accountant: Bhavesh R Nagda. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Parkwest - Sequoia - Tower 11?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Parkwest - Sequoia - Tower 11. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Parkwest - Sequoia - Tower 11 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.