Home / Browse projects / Bengaluru Urban, Karnataka / Parkwest - Oak - Tower 10

Registration approved No litigation declared Residential/Group Housing project

Parkwest - Oak - Tower 10

By Relationship Properties Private Limited

RG-KA-39957 · RERA PRM/KA/RERA/1251/310/PR/210216/003900 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • 9 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
Jun 2026Possession promisedmoved 12 months from the original
9 of 18Construction stages donefurthest along: Basic work of Water supply, 99%
0 of 222Units unsoldnot recorded sold or booked
9Complaints at RERA Karnatakaon this registration
Jump to the 133 documents Report an error

Parkwest - Oak - Tower 10 is a Residential/Group Housing project by Relationship Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210216/003900 on 16 Feb 2021. Possession is promised by 30 Jun 2026. The completion date has moved by 12 months from the original filing. 222 of the 222 units on this registration are recorded sold or booked, and 9 of 18 construction stages are filed complete. 9 complaints are on record with the regulator.

At a glance

Project

  • NameParkwest - Oak - Tower 10
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/210216/003900
  • ReraGenie IDRG-KA-39957

Builder

  • NameRelationship Properties Private Limited
  • Entity typeCompany
  • CINU45200MH2008PTC178830
  • Authorized SignatoryMr. Anand Rao
  • DirectorsMr VIJAY SHREENIVAS KARANAM, Mr MONISH KRISHNA, Mr ALEJANDRO JOSE FELEZ BUCHHOLZ, Mr VENKATESH GOPALKRISHNAN
  • Other registrations10 more →
  • Declared earlier projects9 →

Key dates

this monthRegisteredFeb 2021First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Feb 2021
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed133 files

Current status

100%222 of 222 units booked
83.0%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Oak - Tower 10---2220222

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 18 construction stages are filed complete. The stage furthest along is Basic work of Water supply, at 99%.

Building: 84% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc92%
Basic work of Water supply, Sanitary and Electrification99%
Dadoing, Skirting, Flooring, Tiles work (All types)93%
Railing and Grill fixing98%
Electrification, Water supply and Sanitary Finishing40%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting27%
Elevation work96%
Internal and External work including landscapes as per santioned drawings72%

Progress on shared amenities41

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes82%
Internal Roads & FootpathsYes85%
Sewage and Drainage SystemYes85%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes80%
Solid waste management and disposalYes0%
Water conservationYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes30%
Emergency Evacuation servicesYes100%
Storm water drainsYes80%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes30%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes80%
GasYes0%
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes85%
BasementYes90%
TerraceYes85%
Outer WallYes100%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,376 sq m
Named landowners2
LandownerVillageDistrict
ETA Karnataka Estates Limited--
ETA Star Infopark--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 155.42 cr
Cost incurredRs 128.92 cr
Spent of the estimate82.95%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 155.42 crRs 114.63 cr
On-site expenditure-Salaries of workers-Rs 14.29 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRSP Design Consultants India Private Limited
EngineerDesigntree Service Consultants Private Limited

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/250704/003900Jun 2025 → Jun 2026

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka9

Case no.ComplainantRespondentFiled
00931/2025-Relationship Properties Private Limited14/07/2025
00701/2026-Relationship Properties Private Limited16/06/2026
01081/2026-Relationship Properties Private Limited31/08/2026
01088/2026-Relationship Properties Private Limited01/09/2026
01103/2026-Relationship Properties Private Limited04/09/2026
01165/2026-Relationship Properties Private Limited01/10/2026
01173/2026-Relationship Properties Private Limited02/10/2026
01174/2026-Relationship Properties Private Limited02/10/2026
01291/2026-Relationship Properties Private Limited03/11/2026

Documents filed133

As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210216/003900 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 T10 Oak Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 T10 Oak Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 T10 Oak Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 T10 Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 T10 Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6-T10 Q4 FY2526.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 T10 Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 T10 Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 T10 Q3 25-26.pdf15 Jan 2026
Clarification letterFile: T10 clarification letter.pdf13 Jan 2021
Supplemental agreement dated 27052019File: Supplemental agreement 27052019.pdf13 Jan 2021
T10 Notarised Joint declaration affidavitFile: T10 Notarised Joint declaration affidavit.pdf13 Jan 2021
Architect demarcation plan with area statementFile: 1 Architect demarcation plan with area statement.pdf31 Dec 2020
BDA Approved planFile: 2 BDA Approved plan.pdf31 Dec 2020
Site Plan BBMPFile: 3 Site Plan BBMP.pdf31 Dec 2020
T10 sectionFile: 4 T10 section.pdf31 Dec 2020
T10 ground floorFile: 5 T10 ground floor.pdf31 Dec 2020
T10 first floorFile: 6 T10 first floor.pdf31 Dec 2020
T10 typical floor 2nd floorFile: 7 T10 typical floor 2nd floor.pdf31 Dec 2020
T10 3 4 10 11 12 13 19 20 21 22 floorFile: 8 T10 3 4 10 11 12 13 19 20 21 22 floor.pdf31 Dec 2020
T10 5 6 7 14 15 16 23 24 25 floorFile: 9 T10 5 6 7 14 15 16 23 24 25 floor.pdf31 Dec 2020
T10 8 17 26 floorFile: 10 T10 8 17 26 floor.pdf31 Dec 2020
T10 9 27 floorFile: 11 T10 9 27 floor.pdf31 Dec 2020
T10 10 18 floorFile: 12 T10 10 18 floor.pdf31 Dec 2020
T10 28 floorFile: 13 T10 28 floor.pdf31 Dec 2020
T10 29 30 31 32 floorFile: 14 T10 29 30 31 32 floor.pdf31 Dec 2020
T10 terrace floorFile: 15 T10 terrace floor.pdf31 Dec 2020
T10 elevationFile: 16 T10 elevation.pdf31 Dec 2020
BBMP plan approval letterFile: BBMP plan approval letter.pdf31 Dec 2020
BDA Work OrderFile: BDA Work Order.pdf31 Dec 2020
Lower basement plan 01File: Lower basement plan 01.pdf31 Dec 2020
Lower Basement Plan 02File: Lower Basement Plan 02.pdf31 Dec 2020
Upper Basement Plan 01File: Upper Basement Plan 01.pdf31 Dec 2020
Upper Basment Plan 02File: Upper Basment Plan 02.pdf31 Dec 2020
Reply the the query dated 14.12.2020File: Reply to notice Tower 10.pdf18 Dec 2020
Area demarcation planFile: 1. Architect demarcation plan with area statement.pdf18 Dec 2020
BDA work orderFile: BDA Work Order.pdf18 Dec 2020
BBMP plan approval letterFile: BBMP plan approval letter.pdf18 Dec 2020
BDA approved planFile: 2. BDA Approved plan.pdf18 Dec 2020
BBMP site planFile: 3. Site Plan BBMP.pdf18 Dec 2020
T10 sectionFile: 4. T10 - section.pdf18 Dec 2020
T10 elevationFile: 16. T10 - elevation.pdf18 Dec 2020
T10 ground floor planFile: 5. T10 - ground floor.pdf18 Dec 2020
T10 first floor planFile: 6. T10 - first floor.pdf18 Dec 2020
T10 2nd floor planFile: 7. T10 - typical floor (2).pdf18 Dec 2020
T10 - 3,4,10,11,12,13,19,20,21,22 floor planFile: 8. T10 - 3,4,10,11,12,13,19,20,21,22 floor.pdf18 Dec 2020
T10 - 5,6,7,14,15,16,23,24,25 floor planFile: 9. T10 - 5,6,7,14,15,16,23,24,25 floor.pdf18 Dec 2020
T10 - 8,17,26 floor planFile: 10. T10 - 8,17,26 floor.pdf18 Dec 2020
T10 - 9, 27 floor planFile: 11. T10 - 9, 27 floor.pdf18 Dec 2020
T10 - 10, 18 floor planFile: 12. T10 - 10, 18 floor.pdf18 Dec 2020
T10 28th floor planFile: 13. T10 - 28 floor.pdf18 Dec 2020
T10 - 29,30,31,32 floor planFile: 14. T10 - 29,30,31,32 floor.pdf18 Dec 2020
T10 terrace floor planFile: 15. T10 - terrace floor.pdf18 Dec 2020
Upper basement plan 1File: Upper Basement Plan 01.pdf18 Dec 2020
Upper basement plan 2File: Upper Basment Plan 02.pdf18 Dec 2020
Lower basement plan 1File: Lower basement plan 01.pdf18 Dec 2020
Lower basement plan 2File: Lower Basement Plan 02.pdf18 Dec 2020
Revenue documentsFile: Revenue documents merged.pdf18 Dec 2020
Reply to QueryFile: Reply to Tower-10.pdf1 Dec 2020
Document No 1File: Document No 1.pdf1 Dec 2020
Document No 2File: Document No 2.pdf1 Dec 2020
Document No 3File: Document No 3.pdf1 Dec 2020
Document No 4File: Document No 4.pdf1 Dec 2020
Document No 5File: Document No 5.pdf1 Dec 2020
Document No 6File: Document No 6.pdf1 Dec 2020
CertificateFile: RPPL_Registration Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: T10 ARCH CERTIFICATE WORK COMPLETE.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: T10 ARCHITECT CERTIFICATE WORK PENDING.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate Fund Utilized March 2025.pdf-
Architect Certificate for Pending Work Completion Schedule.File: T10 ARCHITECT CERTIFICATE WORK PENDING.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: T10 ENGR CERTIFICATE WORK PENDING.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate Fund Required March 2025.pdf-
AffidavitFile: Extension Affidavit.pdf-

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 not delivered by the promised date3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Parkwest - Mahogany - Tower 7-OngoingSep 2023Not delivered
Parkwest - Magnolia - Tower 6-OngoingOct 2022Not delivered
Parkwest - Sapphire - Tower 5-OngoingJun 2022Not delivered
Parkwest - Maple - Tower 4-OngoingJun 2021Not delivered
Parkwest - Olive - Tower 1-Completed-No date filed
Parkwest - Mulberry - Tower 3-Completed-No date filed
Parkwest - Emerald - Tower 2-Completed-No date filed

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Parkwest - Oak - Tower 10 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Relationship Properties Private Limited

Relationship Properties Private Limited has 11 registrations on RERA Karnataka, including Parkwest - Olive - Tower 1 and Parkwest - Maple - Tower 4. Its filings declare 9 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Parkwest - Oak - Tower 10 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Parkwest - Oak - Tower 10?

The registered promoter entity is Relationship Properties Private Limited, a company as per the filing. Its CIN U45200MH2008PTC178830 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Parkwest - Oak - Tower 10?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Parkwest - Oak - Tower 10?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Parkwest - Oak - Tower 10?

The professionals named in the filing: Architect: RSP Design Consultants India Private Limited; Engineer: Designtree Service Consultants Private Limited. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Parkwest - Oak - Tower 10?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Parkwest - Oak - Tower 10. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Parkwest - Oak - Tower 10 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.